EBK PRINCIPLES OF OPERATIONS MANAGEMENT
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
11th Edition
ISBN: 9780135175859
Author: Munson
Publisher: VST
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 3, Problem 17P

Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Draw the AON network and answer the questions that follow.

Chapter 3, Problem 17P, Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor

a) What is the expected (estimated) time for activity C?

b) What is the variance for activity C?

c) Based on the calculation of estimated times, what is the critical path?

d) What is the estimated time of the critical path?

e) What is the activity variance along the critical path?

f) What is the probability of completion of the project before week 36?

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The expected time for activity C.

Introduction: In the activity on nodes (AON) project network diagram, the nodes denote activities and the arrows show only the precedence and succession sequence.

Answer to Problem 17P

The expected time for activity C is 12 weeks.

Explanation of Solution

Given information:

Activity Immediate predecessor Time estimates
Optimistic Most likely Pessimistic
A 4 8 10
B A 2 8 24
C A 8 12 16
D A 4 6 10
E B 1 2 3
F E,C 6 8 20
G E,C 2 3 4
H F 2 2 2
I F 6 6 6
J D,G,H 4 6 12
K I,J 2 2 3

Calculation of expected time for activity C:

AON project network diagram shown below, given the precedence relationships of various activities,

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 3, Problem 17P , additional homework tip  1

Figure 1

With the given predecessor AON diagram is constructed. To Calculate the expected time for activity C given the data that the optimistic time estimate “a” of activity C of 8 weeks, the most likely time estimate “m” of 12 weeks and the pessimistic time estimate “b” of 16 weeks using the formula.

Expectedtime=a+4m+b6 (1)

Where ‘a’ is the optimistic time estimate, ‘m’ is the most likely time estimate and ‘b’ is the pessimistic time estimate

Substitute into the equation (1), the values of a=8 weeks, m=12 weeks and b=16 weeks to obtain the expected time for activity C.

t=8+(4×12)+166=726=12weeks

Therefore the expected time for activity C is calcualted by adding 8, 48 and16 and dividing the sum with 6 which gives 12weeks

Hence, the expected time for activity C is 12 weeks.

b)

Expert Solution
Check Mark
Summary Introduction

To calculate: The variance for activity C.

Answer to Problem 17P

The variance for activity C is 1.78 weeks.

Explanation of Solution

Given information:

Activity Immediate predecessor Time estimates
Optimistic Most likely Pessimistic
A 4 8 10
B A 2 8 24
C A 8 12 16
D A 4 6 10
E B 1 2 3
F E,C 6 8 20
G E,C 2 3 4
H F 2 2 2
I F 6 6 6
J D,G,H 4 6 12
K I,J 2 2 3

Calculation of variance for activity C:

Calculate the variance for activity C using the formula

σ2=(b-a6)2 (2)

Substitute in equation (2) the values of b=16 weeks and a=8 weeks and obtain

σ2=(1686)2=169=1.78

The variance of activity C is calculated by squaring the value obtained by dividing the difference of 16 and 8 with 6 which gives the resultant as 1.28 weeks.

The variance in activity C is 1.78 weeks.

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The critical path.

Answer to Problem 17P

The critical path AàCàFàHàJàK.

Explanation of Solution

Given information:

Activity Immediate predecessor Time estimates
Optimistic Most likely Pessimistic
A 4 8 10
B A 2 8 24
C A 8 12 16
D A 4 6 10
E B 1 2 3
F E,C 6 8 20
G E,C 2 3 4
H F 2 2 2
I F 6 6 6
J D,G,H 4 6 12
K I,J 2 2 3

Calculation of critical path:

Using equation (1) and (2)calculate the expected times and variances for all the activitiesand obtain the values shown in table.

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 3, Problem 17P , additional homework tip  2

Figure 1, shows the AON diagram which gives the critical path. The critical path is AàCàFàHàJàK.

Hence, the critical path AàCàFàHàJàK.

d)

Expert Solution
Check Mark
Summary Introduction

To Compute: The estimated time of the critical path.

Answer to Problem 17P

The critical path AàCàFàHàJàK which is 40.18 weeks.

Explanation of Solution

Given information:

Activity Immediate predecessor Time estimates
Optimistic Most likely Pessimistic
A 4 8 10
B A 2 8 24
C A 8 12 16
D A 4 6 10
E B 1 2 3
F E,C 6 8 20
G E,C 2 3 4
H F 2 2 2
I F 6 6 6
J D,G,H 4 6 12
K I,J 2 2 3

Calculation of estimated time of the critical path:

Figure 1, shows the AON diagram which gives the critical path. The critical path is AàCàFàHàJàK.

The various paths and the expected completion times are listed in the table

Various paths Completion times
AàBàEàFàIàK 37.18 weeks
AàBàEàGàJàK 31.18 weeks
AàCàFàHàJàK 40.18 weeks
AàCàGàJàK 31.51 weeks
AàDàJàK 22.84 weeks

Hence, the estimated time of the critical path AàCàFàHàJàK is 40.18 weeks.

e)

Expert Solution
Check Mark
Summary Introduction

To determine: The variance of the critical path.

Answer to Problem 17P

The variance of the critical path is 10.03 weeks.

Explanation of Solution

Given information:

Activity Immediate predecessor Time estimates
Optimistic Most likely Pessimistic
A 4 8 10
B A 2 8 24
C A 8 12 16
D A 4 6 10
E B 1 2 3
F E,C 6 8 20
G E,C 2 3 4
H F 2 2 2
I F 6 6 6
J D,G,H 4 6 12
K I,J 2 2 3

Calculation of variance of the critical path:

The activity variance σ2along the critical path AàCàFàHàJàK is the sum of the variances of individual activities A, C, F, H, J and K.

Therefore,

σ2=1+1.78+5.44+0+1.78+0.03=10.03

The activity variance along the critical path is the sum of 1, 1.78, 5.44, 0, 1.78, 0.03 is 10.03 weeks.

Hence, the variance of the critical path is 10.03 weeks

f)

Expert Solution
Check Mark
Summary Introduction

To compute: The probability of completion of the project before week 36 weeks.

Answer to Problem 17P

The probability of completion of the project before week 36 weeks is 9.34%.

Explanation of Solution

Given information:

Activity Immediate predecessor Time estimates
Optimistic Most likely Pessimistic
A 4 8 10
B A 2 8 24
C A 8 12 16
D A 4 6 10
E B 1 2 3
F E,C 6 8 20
G E,C 2 3 4
H F 2 2 2
I F 6 6 6
J D,G,H 4 6 12
K I,J 2 2 3

Calculation of probability of completion of the project before week 36 weeks:

Use the normal distribution tables given that the estimated mean time is 40.18 weeks and the standard deviation is square root of 10.03 weeks.

First compute the standard deviation σ by computing the square root of 10.03 weeks.

σ=10.03=3.17weeks

Calculate the z value as shown below

z=36-40.183.17=-1.32

For a z value of -1.32, the probability is 9.34%.

Therefore, there is a probability of 9.34% that the project may be completed on or before 36 weeks.

Hence, the probability of completion of the project before week 36 weeks is 9.34%.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
What is Bitcoin? How important is it to businesses and individuals? How does it cause environmental damage and is that damage worth continued uses of Bitcoin? Read the following articles to help answer these questions: United Nations University. (2023, October 24). UN study reveals the hidden environmental impacts of bitcoin: Carbon is not the only harmful by-product. https://unu.edu/press-release/un-study-reveals-hidden-environmental-impacts-bitcoin-carbon-not-only-harmful-product#:~:text=Bitcoin%2C%20the%20most%20popular%20cryptocurrency,the%20worldwide%20Bitcoin%20mining%20network. Salam, E. (2023, April 26). Bitcoin is terrible for the environment – can it ever go green? The Guardian. https://www.theguardian.com/technology/2023/apr/26/bitcoin-mining-climate-crisis-environmental-impact
419 X .com/courses/1546/assignments/49499?module_item_id=111573 Unlimited Attempts Allowed ✓ Details Directions: Record a video of yourself giving a business presentation. Imagine you are tasked with researching a professional development topic on business communication for 40 coworkers. You are then expected to give a 4 - 5 minute presentation on the topic. Choose any topic related to business communication, such as intercultural communication, effective leadership, professional writing, etc. Research the topic and prepare a 4 - 5 minute presentation that could be given over video conference call (such as Zoom). You may use visual aids if you choose. Upload a video file of your presentation. Provide all needed citations. Requirements: 4-5 minutes long Contains visual and audio Create your own work; do not plagiarize Cite your sources using APA citations Choose a submission type T
acts Container chips (s 150 cussion: Conflict X + e.com/courses/1546/discussion_topics/15722?module_item_id=111559 24 Winter > Discussions > Week 8 Discussion: Conflict 时☆ 26 Replies, 26 Unread Week 8 Discussion: Conflict Write a 200 - 300 word discussion post based on the prompt below. Reply to at least one other student in 50 - 100 words. Can you think of a time when a conflict led to a new opportunity, better understanding, or other positive result? If not, think of a past conflict and imagine a positive outcome. Discuss the impact of this conflict on your workplace relationships, productivity, and innovation. Source: Business Communication for Success. (2015). University of Minnesota Libraries Publishing. Attribution-NonCommerical-ShareAlike. Edit View Insert Format Tools Table 12ptv Paragraph BIUA T2

Chapter 3 Solutions

EBK PRINCIPLES OF OPERATIONS MANAGEMENT

Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY