
Concept explainers
a)
To determine:The probability of completing the project in 17 months.
Introduction:
The activity times of various tasks in a PERT project network are assumed to follow a probability distribution. For calculating the expected times and standard deviation, the parameters required are the following:
- Optimistic time: This is the time denoted by “a”, which is the best possible or in other words, the quickest time in which an activity can be completed, assuming that everything goes as per plan.
- Pessimistic time: This is the worst case scenario, where all the conditions are adverse or unfavorable. The maximum time which may be taken in such a situation is the pessimistic time denoted by “b”.
- Most likely time: The most realistic estimate of the time, denoted by “m” in normal conditions, is another parameter which is important in the computation of expected times and variances.
a)

Answer to Problem 23P
The probability that the project completion time is 17 months is 0.0228.
Explanation of Solution
Given information:
Calculation of probability of completing the project in 17 months:
The standard deviationis
Z is calculated by dividing the difference of 17 and 21 with 2 which gives -2. From the
Hence, the probability that the project completion time is 17 months is 0.0228.
b)
To determine:The probability of completing the project in 20 months.
b)

Answer to Problem 23P
The probability that the project completion time is 20 months is 0.3085.
Explanation of Solution
Given information:
Calculation of probability of completing the project in 20 months:
Calculate the standard deviation
Z is calculated by dividing the difference of 21 and 20 with 2 which gives -0.5. From the normal distribution tables z value -0.5 corresponds to 0.3085.
Use the normal distribution tables to calculate the probability
The probability of project completion in 20 months is 0.3085.
Hence, the probability that the project completion time is 20 months is 0.3085.
c)
To determine:The probability of completing the project in 23 months.
c)

Answer to Problem 23P
The probability that the project completion time is 23 months is 0.8413.
Explanation of Solution
Given information:
Calculation of probability of completing the project in 23 months:
Calculate the standard deviation
Z is calculated by dividing the difference of 23 and 21 with 2 which gives 1. From the normal distribution tables z value 1 corresponds to 0.8413.
Use the normal distribution tables to calculate the probability
The probability of project completion in 23 months is 0.8413.
Hence, the probability that the project completion time is 23 months is 0.8413.
d)
To determine:The probability of completing the project in 25 months.
d)

Answer to Problem 23P
The probability that the project completion time is 25 months is 0.9772.
Explanation of Solution
Given information:
Calculation of probability of completing the project in 25 months:
Calculate the standard deviation
Z is calculated by dividing the difference of 25 and 21 with 2 which gives 2. From the normal distribution tables z value 2 corresponds to 0.9772.
Use the normal distribution tables to calculate the probability
The probability of project completion in 25 months is 0.9772.
Hence, the probability that the project completion time is 25 months is 0.9772.
e)
To compute: The due date that yields a 95% chance of completion.
e)

Answer to Problem 23P
The due date that yields a 95% chance of completionis 24.2 months.
Explanation of Solution
Given information:
Calculation of due date that yields a 95% chance of completion:
The z value from the normal distribution tables as shown below,
From the above tables, observe that the z value is 1.65.
Compute the due date that yields a 95% chance of completion.
The due date is calculated by adding 21 months with the product of 1.6 and 2 which yields 24.2 months.
Hence, the due date that yields a 95% chance of completion is 24.2 months.
Want to see more full solutions like this?
Chapter 3 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- Following their early success and growth, Listo hired a number of new managers and employees. In response to the expansion of staff, Listo reorganized by adding layers of supervisors and managers between executive management and line staff; however, growth occurred so rapidly that proper training was not provided to the new employees. Management was less concerned with the employees’ opinions and was more focused on production and profit. Instead of enlisting employees’ opinions, more directive orders were given. The change and increased complexity associated with adding new layers to the hierarchy resulted in the organization’s goals and objectives becoming unclear. Employees began to complain about the new bureaucratic processes and the slow pace of decision-making. While the organization has been growing in size, productivity has slowed and quality has decreased. The turnover rate is higher than it has ever been, and the number of sick days that people take has doubled over the past…arrow_forwardFollowing their early success and growth, Listo hired a number of new managers and employees. In response to the expansion of staff, Listo reorganized by adding layers of supervisors and managers between executive management and line staff; however, growth occurred so rapidly that proper training was not provided to the new employees. Management was less concerned with the employees’ opinions and was more focused on production and profit. Instead of enlisting employees’ opinions, more directive orders were given. The change and increased complexity associated with adding new layers to the hierarchy resulted in the organization’s goals and objectives becoming unclear. Employees began to complain about the new bureaucratic processes and the slow pace of decision-making. While the organization has been growing in size, productivity has slowed and quality has decreased. The turnover rate is higher than it has ever been, and the number of sick days that people take has doubled over the past…arrow_forwardDiscuss in detail any five types of authority. give citations and referencearrow_forward
- Can you guys help me with this? Thank you! Business Environment: Provide insights into the guidelines for conducting business in the chosen country and working there as an expatriate. This information is vital for understanding the practicalities of engagement in that particular environment. The country in here is India Put the answer as bullet points, provide sources that have relevant information for the answer on economic factorsarrow_forwardCan you guys help me with this? Thank you! Intriguing Facts: Incorporate engaging facts about the country that enhance its value and uniqueness within the global supply chain landscape. These can include cultural anecdotes, technological innovations, or historical achievements. The country in here is India Put the answer as bullet points, provide sources that have relevant information for the answer on economic factorsarrow_forwardCan you guys help me with this? Thank you! Economic Factors: Evaluate the country's economic performance by analyzing key indicators such as GDP (Gross Domestic Product), GDP per capita, exports, and imports. These metrics provide insight into the country's economic prowess and its position in global trade. The country in here is India Put the answer as bullet points, provide sources that have relevant information for the answer on economic factorsarrow_forward
- provide scholarly reseach and define legal and complince risk and reputational risk in banking. Additionally 1. What more can be done about it 2. the department where the risk is exposed to 3. what strategy can be used 4. responsible personarrow_forwardRead the case in the link below and Develop a risk management programme appropriate for this case using the attached template. https://finopsinfo.com/investors/citis-900m-blunder-casts-light-on-poor-loan-ops/arrow_forwardDo the inherent differences between private and public sector objectives—profit versus publicgood—render private sector category management practices unsuitable for public sectorpurchasing, where open tendering is the norm?You have now undergone the Category Management classes and your superiors have requestedfor your input on how to integrate some of the learnings into the public sector policy. Discuss and elaborate what are the activities and governance you would introduce in yourrecommendations without violating the principle of transparency and accountability withinyour organisation. This is based on Singapore context. Pls provide a draft with explanation, examples and useful links for learning purposes. Citations will be good too. This is a module in SUSS called category management and supplier evaluationarrow_forward
- provide scholarly answers for what risk was associated with the Citibank bank loosing 50 million in August 2020arrow_forwardConclusion: The report recommendations and broad conclusion to the essay. TOTAL 5 100arrow_forwardAs part of your new role, as a strategy consultant and member of the steering committee, discuss what logistics and transportation strategies you will execute to achieve operational efficiencies and facilitate economic growth in SA. The committee would like to have a implementable strategic transport and logistics plan to realise the roadmap vision based on the subsection numbering given below! QUESTION ONE Introduction: Must include an overview and history of South Africa's Road, rail and freight transport network. Marks 5arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning

