Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
12th Edition
ISBN: 9780134741062
Author: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 2, Problem 22P
a.
Summary Introduction
Introduction: The learning rate or learning curve states that the total experience gained by a worker will help in reducing the time consumed to perform a task as cumulative output increases twofold.
To compute:the time to assemble the windows on manual line by considering learning rate.
b.
Summary Introduction
Introduction: The learning rate or learning curve states that the total experience gained by a worker will help in reducing the time consumed to perform a task as cumulative output increases twofold.
To calculate:the time to assemble the windows on semi-automatic line by considering learning rate.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
On RainTite Window’s manual assembly line, a newemployee can usually assemble their first window unit in30 minutes. Management assumes a 90 percent learning rate.a. How long should a new employee take to assemble theirsecond window if management is correct in their assumption? How long should the 16th window take?b. On RainTite’s semi-automated line, a new employeetakes 45 minutes to assemble their first window; however,the learning rate is 75 percent. At how many windowsproduced will the semi-automated line’s employee takeless time to produce a window than an employee on themanual line?
The product superx takes 9949 hours for production of 250 unit, where learning curve rate is 99.7% and what will be the total time taken by 2000 units of product superx using cumulative method ?
In wox limited the first 31 units takes 34 hours to be produced where the learning curve rate is 77%. Calculate how much time it will take to produce 124 units using the wright model , also find the unit time of 2nd slot .
Chapter 2 Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Ch. 2 - Prob. 3DQCh. 2 - Prob. 4DQCh. 2 - Consider the range of processes in the financial...Ch. 2 - Prob. 6DQCh. 2 - Continuous improvement recognizes that many small...Ch. 2 - Prob. 8DQCh. 2 - Paul O’Neill, former U.S. Treasury Secretary,...Ch. 2 - Dr. Gulakowicz is an orthodontist. She estimates...Ch. 2 - Two different manufacturing processes are being...Ch. 2 - The operations manager at Sebago Manufacturing is...
Ch. 2 - Consider the Custom Molds, Inc., case at the end...Ch. 2 - Founded in 1970, ABC is one of the world’s...Ch. 2 - Prepare a flowchart of the field service division...Ch. 2 - Big Bob’s Burger Barn would like to graphically...Ch. 2 - Prob. 10PCh. 2 - Suppose you are in charge of a large mailing to...Ch. 2 - Diagrams of two self-service gasoline stations,...Ch. 2 - Prob. 13PCh. 2 - Prob. 14PCh. 2 - A time study of an employee assembling peanut...Ch. 2 - Prob. 18PCh. 2 - Prob. 19PCh. 2 - Prob. 20PCh. 2 - Prob. 21PCh. 2 - Prob. 22PCh. 2 - Prob. 23PCh. 2 - Smith, Schroeder, and Torn (SST) is a short-haul...Ch. 2 - Prob. 25PCh. 2 - Prob. 26PCh. 2 - Prob. 27PCh. 2 - Prob. 28PCh. 2 - Prob. 29PCh. 2 - Prob. 30PCh. 2 - Prob. 31PCh. 2 - Prob. 32PCh. 2 - Prob. 33PCh. 2 - Prob. 1AMECh. 2 - What percentage of overall complaints do the three...Ch. 2 - Prob. 3AMECh. 2 - Prob. 1VCCh. 2 - What are the benefits that the POI program can...Ch. 2 - Prob. 3VCCh. 2 - What are the major issues facing Tom and Mason...Ch. 2 - Prob. 1.2CCh. 2 - Prob. 1.3CCh. 2 - Prob. 2.1CCh. 2 - Prob. 2.2CCh. 2 - Prob. 2.3C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Suad Alwan, the purchasing agent for Dubai Airlines, has determined that the second plane took 18,000 hours to produce. Using an 85% learning curve and a $35-per-hour labor charge, he wants to determine the cost of the six additional planes. Part 2 Time required for the sixth unit = 13900 hours (round your response to the nearest whole number). Part 3 Cost of the sixth unit = 486500 dollars (round your response to the nearest whole number). Part 4 Time required for the seventh unit = enter your response here hours (round your response to the nearest whole number). Part 5. Cost of the seventh unit?arrow_forwardK Girish Shambu and Delores Reisel are teammates at a discount store; their new job is assembling bicycles for customers. Assembly of a bike has a learning rate of 80%. They forgot to time their effort on the first bike, but st 5 hours on the second. They have 6 more bikes to do. Determine approximately how much time will be (was) required for: a) The 1st unit = 6.25 hours (round your response to two decimal places). b) The 8th unit = 3.20 hours (round your response to two decimal places). c) The total amount of hours to build the 8 units = hours (round your response to two decimal places).arrow_forwardHi, I need help solving this OM problem. Thank you!arrow_forward
- Schumacher & Company recently introduced a new ATM system. The Company’s MoneyMatic Division assembles these systems from purchased hardware, using its in-house developed software. It just completed assembling the first batch of 15 units. The last unit (#15) produced required 50 hours of labor, and the learning rate was estimated to be 94 percent for these systems. Another order for 25 units (#16 - #40) of the same system has just arrived. 1) What is the estimated time for the 40th unit? 2) How many total labor hours will be needed to satisfy this second batch (#16 - #40) ? 3) What is the average time to produce this second batch?arrow_forwardThe product TRX takes 9.99 hours for production of 1 unit, where learning curve rate is 77% and what will be the total time taken by 8th unit of product TRX using incremental unit time method ?arrow_forwardSusan Sherer, an IRS auditor, took 48 minutes to process her first tax return. The IRS uses an 82% learning curve. The amount of processing time that Susan is going to require for the 2nd return __ minutes 4th return __ minutes and 8th return __ minutesarrow_forward
- Girish Shambu and Delores Reisel are teammates at a discount store; their new job is assembling bicycles for customers. Assembly of a bike has a learning rate of 75%. They forgot to time their effort on the first bike, but spent 5 hours on the second. They have 6 more bikes to do. Determine approximately how much time will be (was) required for: a) The 1st unit= hours (round your response to two decimal places). b) The 8th unit-hours (round your response to two decimal places). c) The total amount of hours to build the 8 units-hours (round your response to two decimal places).arrow_forwardIn yuyox ltd the first 71 units takes 92 hours to be produced where learning curve is 83% , calculate how much time it will take to produce 568 units using the wrights model ? Solve asaparrow_forwardPlease do not give solution in image format thanku For a production process of 30 units with a learning rate of 85% and a cost of $75 to produce the first unit, construct a table displaying the Cost to Product the Nth Unit and the Cumulative Cost for units 1 through 30.arrow_forward
- * Girish Shambu and Delores Reisel are teammates at a discount store, their new job is assembling bicycles for customers. Assembly of a bike has a learning rate of 80%. They forgot to time their effort on the first bike, but spent 5 hours on the second. They have 6 more bikes to do. Determine approximately how much time will be (was) required for: a) The 1st unit 6.25 hours (round your response to two decimal places) b) The 8th unit = hours (round your response to two decimal places). -arrow_forwardGirish Shambu and William Reisel are teammates at a discount store; their new job is assembling bicycles for customers. Assembly of a bike has a learning rate of 70%. They forgot to time their effort on the first bike but spent 4 hours on the second. They have 6 more bikes to do. Determine approximately how much time will be (was) required for: a) The 1st unit = (round your answer to two decimal places)arrow_forwardA teacher wanted to know which learning delivery modes (pure online, pure modular, combination of online and modular) is most effective and has the fastest turnaround time in the submission of accomplished activities among her Grade 12 students. She divided the students into 3 groups, gave them the same activity sheets and asked them to submit as soon as it is completed. She then compared the scores and completion time of the 3 groups. Identify the independent, dependent and extraneous variablearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.