Textbook Question
Chapter 19, Problem 19.33P
Waiting times, manufacturing cycle times. The Sandstone Corporation uses an injection molding machine to make a plastic product, Z35, after receiving firm orders from its customers. Sandstone estimates that it will receive 60 orders for Z35 during the coming year. Each order of Z35 will take 100 hours of machine time. The annual machine capacity is 8,000 hours.
- 1. Calculate (a) the average amount of time that an order for Z35 will wait in line before it is processed and (b) the average manufacturing cycle time per order for Z35.
Required
- 2. Sandstone is considering introducing a new product, Y21. The company expects it will receive 30 orders of Y21 in the coming year. Each order of Y21 will take 40 hours of machine time. Assuming the demand for Z35 will not be affected by the introduction of Y21, calculate (a) the average waiting time for an order received and (b) the average manufacturing cycle time per order for each product, if Sandstone introduces Y21.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The Sandstone Corporation uses an injection molding machine to make a plastic product, Z35, after receiving firm orders from its customers. Sandstone estimates that it will receive 60 orders for Z35 during the coming year. Each order of Z35 will take 100 hours of machine time. The annual machine capacity is 8,000 hours.
Q. Calculate (a) the average amount of time that an order for Z35 will wait in line before it is processed and (b) the average manufacturing cycle time per order for Z35.
Nash Corporation manufactures and sells custom snowmobiles. From the time an order is placed till
the time the snowmobile reaches the customer averages 50 days. This 50 days is spent as follows:
Wait time: 10 days
Move time: 5 days
Process time: 15 days
Queue time: 15 days
Inspection time: 5 days
What is Nash's manufacturing cycle efficiency (MCE) for its snowmobiles?
The Sandstone Corporation uses an injection molding machine to make a plastic product, Z35, after receiving firm orders from its customers. Sandstone estimates that it will receive 60 orders for Z35 during the coming year. Each order of Z35 will take 100 hours of machine time. The annual machine capacity is 8,000 hours.
Q. Sandstone is considering introducing a new product, Y21. The company expects it will receive 30 orders of Y21 in the coming year. Each order of Y21 will take 40 hours of machine time. Assuming the demand for Z35 will not be affected by the introduction of Y21, calculate (a) the average waiting time for an order received and (b) the average manufacturing cycle time per order for each product, if Sandstone introduces Y21.
Chapter 19 Solutions
Horngren's Cost Accounting: A Managerial Emphasis (16th Edition)
Ch. 19 - Describe two benefits of improving quality.Ch. 19 - Prob. 19.2QCh. 19 - Name two items classified as prevention costs.Ch. 19 - Give two examples of appraisal costs.Ch. 19 - Distinguish between internal failure costs and...Ch. 19 - Describe three methods that companies use to...Ch. 19 - Companies should focus on financial measures of...Ch. 19 - Give two examples of nonfinancial measures of...Ch. 19 - Give two examples of nonfinancial measures of...Ch. 19 - When evaluating alternative ways to improve...
Ch. 19 - Distinguish between customer-response time and...Ch. 19 - Prob. 19.12QCh. 19 - Give two reasons why delays occur.Ch. 19 - Companies should always make and sell all products...Ch. 19 - Prob. 19.15QCh. 19 - Rector Corporation is examining its quality...Ch. 19 - Six Sigma is a continuous quality improvement...Ch. 19 - Costs of quality. (CMA, adapted) Osborn, Inc.,...Ch. 19 - Costs of quality analysis. Adirondack Company...Ch. 19 - Costs-of-quality analysis. Safe Travel produces...Ch. 19 - Costs of quality, quality improvement. iCover...Ch. 19 - Prob. 19.22ECh. 19 - Prob. 19.23ECh. 19 - Waiting time. Its a Dogs World (IDW) makes toys...Ch. 19 - Waiting time, service industry. The registration...Ch. 19 - Waiting time, cost considerations, customer...Ch. 19 - Nonfinancial measures of quality and time. For the...Ch. 19 - Nonfinancial measures of quality, manufacturing...Ch. 19 - Statistical quality control. Harvest Cereals...Ch. 19 - Quality improvement, Pareto diagram,...Ch. 19 - Quality improvement, relevant costs, and relevant...Ch. 19 - Quality improvement, relevant costs, and relevant...Ch. 19 - Waiting times, manufacturing cycle times. The...Ch. 19 - Prob. 19.34PCh. 19 - Manufacturing cycle times, relevant revenues, and...Ch. 19 - Compensation linked with profitability, waiting...Ch. 19 - Ethics and quality. Weston Corporation...Ch. 19 - Prob. 19.38P
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Explain the computation needed. We have been producing product A for several years and look forward to several more years of sales at 500,000 units per year or 2,000 units per day. The present method requires a standard time of 2.0 mins per unit or 30 pcs per hour. At this rate, it takes 33.33 hrs to make 1,000 units. All production will run on the day shift. Present Method and Costs- with a labor rate of $10.00/hr, the labor cost will be $333.30 to produce 1,000 units. The cost of 500,000 units per year would be $166,650.00 in direct labor. New Method and Cost- we have a reduction idea. If we buy this new machine attachment for $1000, the new time standard would be lowered to 1.5 minutes per unit. Will this investment be good for us?arrow_forwardSoutheastern Bell stocks a certain switch connector at its central warehouse for supplying field service offices. The yearly demand for these connectors is 15,300 units. Southeastern estimates its annual holding cost for this item to be $23 per unit. The cost to place and process an order from the supplier is $74. The company operates 300 days per year, and the lead time to receive an order from the supplier is 2 working days. a) What is the economic order quantity? units (round your response to the nearest whole number).arrow_forwardWhat is the number of workdays in an order cycle?arrow_forward
- TimsTabletCo (TTC) produces tablet computers, and it must determine the number of units to be produced during each of the next four months. The following table gives the monthly demand and the monthly cost of producing each unit: Month 1 2 3 4 Demand (in units) 5000 2000 6000 1000 Production Cost (dollars per unit) 400 600 200 300 At the start, before Month 1, TTC has an inventory of 2000 units. Each month, up to 4000 units can be produced. TTC can use the units produced in a particular month in two ways: either use some units to satisfy the demand in the same month, or store some units in inventory for future use. The cost of storing units in inventory is $100 per unit per month. (a) Formulate an LP problem (P) to minimize the total cost of meeting the demands of the next four months. (b) Write the dual LP (D) of (P).arrow_forwardCan someone help me figure out this problem ? Pretty Lady Cosmetic Products has an average production process time of 40 days. Finished goods are kept on hand for an average of 15 days before they are sold. Accounts receivable are outstanding an average of 35 days, and the firm receives 40 days of credit on its purchases from suppliers. Estimate the average length of the firm's short-term operating cycle. How often would the cycle turn over in a year? A. 90 days and 4.06 times B. 80 days and 4.06 times C. 70 days and 3.06 times D. 90 days and 3.06 timesarrow_forwardMCE Craig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 200 units (per hour) Move time: 11 minutes Inspection time: 12 minutes Rework time: 12 minutes 1. MCE is 0.42 2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times. If required, round your answers to two decimal places. Theoretical cycle time fill in the blank minutes Actual cycle time 0.3 minutes MCE fill in the blankarrow_forward
- K Radovilsky Manufacturing Company, in Hayward, California, makes flashing lights for toys. The company operates its production facility 300 days per year. It has orders for about 12,400 flashing lights per year and has the capability of producing 95 per day. Setting up the light production costs $49. The cost of each light is $0.95. The holding cost is $0.15 per light per year. a) What is the optimal size of the production run? units (round your response to the nearest whole number).arrow_forwardA manual assembly line is being designed for a product with annual demand = 100,000 units. The line will operate 50 wks/year, 5 shifts/wk, and 7.5 hr/shift. Work units will be attached to a continuously moving conveyor. Work content time = 42.0 min. Assume line efficiency E = 0.97, balancing efficiency Eb = 0.92, and repositioning time Tr = 6 sec. Determine: (a) hourly production rate to meet demand, (b) number of workers required.arrow_forwardA. Compute the total targeted production of the finished product for the coming year. B. Compute the required amount of plastic to be purchased for the coming year.arrow_forward
- There are currently 5 docks at the UPS port facility and it takes 3.7 hours to process a truck. The facility operates 15 hours a day 365 days a year. During a year they expect 4500 trucks. The current operational costs are $56K per dock per year. The waiting costs are estimated at $80 per day. UPS wants to determine if eliminating one dock will reduce or increase total costs. Answer the following. Complete all calculations with at least 2 decimal points. What is the arrival rate per day? What are the WCe when there are 5 docks? What are the RCe when there are 5 docks? What are the ICe when there are 4 docks? How many docks should UPS have to minimize total costs?arrow_forwardA. Compute the total targeted production of the finished product for the coming year. B. Compute the required amount of plastic to be purchased for the coming year.arrow_forwardplease answer in details with full work within 30 minutes.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Essentials of Business Analytics (MindTap Course ...StatisticsISBN:9781305627734Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. AndersonPublisher:Cengage LearningPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College
- Excel Applications for Accounting PrinciplesAccountingISBN:9781111581565Author:Gaylord N. SmithPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
Essentials of Business Analytics (MindTap Course ...
Statistics
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Excel Applications for Accounting Principles
Accounting
ISBN:9781111581565
Author:Gaylord N. Smith
Publisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Responsibility Accounting| Responsibility Centers and Segments| US CMA Part 1| US CMA course; Master Budget and Responsibility Accounting-Intro to Managerial Accounting- Su. 2013-Prof. Gershberg; Author: Mera Skill; Rutgers Accounting Web;https://www.youtube.com/watch?v=SYQ4u1BP24g;License: Standard YouTube License, CC-BY