a. Develop a list of activities and their immediate predecessors similar to the lists in this problem for this diagram:
b. Construct an activity-on-arrow precedence diagram for each of the following cases. Note that each case requires the use of a dummy activity.
c. Construct an AON diagram for each case.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
a. Construct an activity-on-arrow precedence diagram for each of the following cases. Note that
each case requires the use of a dummy activity.
b. Construct an AON diagram for each case.
Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin.
Activity
A
B
C
D
E
F
G
H
IMG_A2D52FAF8F3D-1.jpeg
Activity
This answer has not been graded yet.
A
B
с
(c) Develop the activity schedule for the project.
D
Survey building site
Develop initial design
Obtain board approval
E
F
G
Description
H
Select architect
Establish budget
Finalize design
Obtain financing
0
Hire contractor
L
L
|
(a) Draw a project network. (Submit a file with a maximum size of 1 MB.)
Choose File No file chosen
Immediate
Predecessor
Earliest
Start
(b) Identify the critical path. (Enter your answers as a comma-separated list.)
4
A, B
с
Latest
Start
с
D, E
E
F, G
Time
(weeks)
5
5
9
Earliest
Finish
13
4
7
15
11
6
9
Latest
Finish
4
Slack
(d) Does it appear…
2.1. Construct an Activity-On-Node (AON) Network Diagram for the HR Departments’system upgrade project.
2.2. Calculate the duration of all possible paths on the network diagram.2.3. Identify the critical path and project duration2.4. Briefly explain the meaning of merge activities. From the network diagram identify themerge activities.
Chapter 17 Solutions
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
Ch. 17 - A project manager may need two skill setsthose of...Ch. 17 - Explain the term project champion and list some...Ch. 17 - List the steps in risk management.Ch. 17 - Give some examples of ethical issues that may...Ch. 17 - What are the key advantages of using project...Ch. 17 - What is a work breakdown structure, and how is it...Ch. 17 - Identify the term being described for each of the...Ch. 17 - List the main advantages of PERT. List the main...Ch. 17 - Why might a probabilistic estimate of a projects...Ch. 17 - Define each of these terms, and indicate how each...
Ch. 17 - Why might a person wish to be involved with a...Ch. 17 - Prob. 12DRQCh. 17 - What are some aspects of the project managers job...Ch. 17 - What is the main benefit of a project organization...Ch. 17 - What trade-offs are associated with time and cost...Ch. 17 - Who needs to be involved in assessing the cost of...Ch. 17 - Prob. 3TSCh. 17 - Project management techniques have been used...Ch. 17 - Give three examples of unethical conduct involving...Ch. 17 - For each of the following network diagrams,...Ch. 17 - Chris received new word processing software for...Ch. 17 - Prepare a Gantt chart for each of the following in...Ch. 17 - a. Develop a list of activities and their...Ch. 17 - For each of the problems listed, determine the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Three recent college graduates have formed a...Ch. 17 - The new director of special events at a large...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - The project described in the following table is...Ch. 17 - The following precedence diagram reflects three...Ch. 17 - A project manager has compiled a list of major...Ch. 17 - Here is a list of activity times for a project as...Ch. 17 - The project manager of a task force planning the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Chucks Custom Boats (CCB) builds luxury yachts to...Ch. 17 - Prob. 17PCh. 17 - Create a risk matrix in the style of Figure 17.13...Ch. 17 - Create a risk matrix for this project: Explain...Ch. 17 - CASE: The Case of the Mexican crazy quilt 1. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 2. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 3. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 4. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 5. The...Ch. 17 - B. Smitty Smith is a project manager for a large...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The table below contains scheduling data for a software development project to be undertaken in an IT company. (i) Identify the critical activities and total duration for the project. (ii) Draw a network diagram using the Activity-on-Arrow (AOA) method to depict the flow of the activities showing interdependencies (iii) Using the data provided in the above table, create a float table for the project.arrow_forwardThe conditions and pert times for constructing a network diagram are given below.-Creation conditions:(0-1) It is the initial activity.(1-2) and (1-3) Activities begin together.It follows activity (2-4) (1-2), activity (3-4) (1-3), and ends together.( 4-5 ) It is the last activity. a-Create the network diagram.b-Calculate the critical path and show it on the diagram.c- If the expiry time is extended by 15 days, how much will the probability of expiry increase?arrow_forward1. A project has been defined to contain the following list of activities along with their required times for completion. What would happen if activity 6 were revised to take 6 weeks instead of 1 week? 2. Construct a Gantt chart for the project defined in Problem 1.arrow_forward
- 12. The best technique to identify the timeframe of project activities and the possible logical flow of all activities is which of the following? Group of answer choices Program Evaluation Review Technique Critical Path Method Ishikawa Diagram Gantt Chartarrow_forwardPlease do not give solution in image format thankuarrow_forwardPERT-CPM 1. Consider a project involving the following activities and precedence relationship. The cost of each activity is listed. The following activity time estimates have been provided for a preparation involving an MIS project. a. Draw the AON and AOA Diagram. b. Perform a Program Evaluation and Review Technique (PERT) to determine the expected total duration of the project. [Note: Use the diagramming convention agreed in class and tabulate the results for each activity's ES, EF, LS, LF, slack time and indication if it's in the critical path Note: Expected (Ave Time) = (0ptimistic Time + 4*Most Likely Time + PessimisticTime) / 6 = ( OT + 4MLT + PT ) / 6 c. If the project exceeds 11 weeks, there is an additional miscellaneous costs around Php 30,000. Will the company opt to speed up the project? Activity Predecessors Optimistic Most Pessimistic Crash Normal Crashed Likely Time Cost Cost A 2 4 6. 2 11,000 6,000 3,000 7,000 4,000 13,000 9,000 4,000 5,000 3,000 3 17.000 В 1 3 5 1…arrow_forward
- In a network diagram, an activity:A) Is the largest unit of work effort consuming both time and resources that a project manager can schedule and control?B) Should always be something the company has had experience with. C) Is the smallest unit of work effort consuming both time and resources that a project manager can schedule and control?D) Must always have a single, precise estimate for the time duration.arrow_forwardPlease do not give solution in image formate thanku PROJECT MANAGEMENT PROCESS GROUP A. INITIATING PROCESS GROUP B. PLANNING PROCESS GROUP C. EXECUTING PROCESS GROUP D. MONITORING AND CONTROLLING PROCESS GROUP E. CLOSING PROCESS GROUP F. Classify the activity below according to its stage in the Project Management Cycle: 1. Conduct of Feasibility Study 2. Testing and Commissioning 3. Geotechnical Survey and Investigations 4. Pile Driving 5. Punchlisting 6. Conduct of Traffic Impact Assessment 7. Finalization of Tender and Bidding Documents 8. Fit-out 9. Surveying 10. Materials Testing 11. Turn-over 12. Cost Estimation 13. Pouring of Foundation 14. Masonry Works 15. Field Density Test 16. Identification of Nearest Batching Plant 17. Testing of Concrete Cylinders 18. Options Analysis 19. Issuance of Notice of Proceed 20. Conduct of Toolbox Meetingarrow_forwardPlease try to answer it in detailsarrow_forward
- What project scheduling tool expands and contracts to share the right information to the right audience? a) Scheduling variance tools b) Network Diagrams C) Gantt Chart d) Histogram Chart.arrow_forwardThe project manager is working with his team in the planning stage for the construction of an industrial park. They are about to start with the network diagram. Which of the following items is NOT necessary for this process? A. Duration of activities B. Statement of project scope C. List of activities D. List of milestonesarrow_forwarda. Develop an AON network for this problem. b. What is the critical path? c. What is the total project completion time? d. What is the slack time for each individual activity? Discussion Question e. Why do you think project management is needed in this scenario?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY