Textbook Question
Book Icon
Chapter 17, Problem 12P

A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships.

Chapter 17, Problem 12P, A project manager has compiled a list of major activities that will be required to install a

a. Construct a network diagram. You can use either AOA or AON (see Example 5).

b. If the project is finished within 26 weeks of its start, the project manager will receive a bonus of $1,000; and if the project is finished within 27 weeks of its start, the bonus will be $500. Find the probability of each bonus.

a)

Expert Solution
Check Mark
Summary Introduction

To construct: A network diagram.

Answer to Problem 12P

Answer

Network diagram:

Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences), Chapter 17, Problem 12P , additional homework tip  1

Explanation of Solution

Given information:

Activity Immediate predecessor Optimistic time Most likely time Pessimistic time
A 2 4 6
D A 6 8 10
E D 7 9 12
H E 2 3 5
F A 3 4 8
G F 5 7 9
B 2 2 3
I B 2 3 6
J I 3 4 5
K J 4 5 8
C 5 8 12
M C 1 1 1
N M 6 7 11
O N 8 9 13
End H, G, K, O

Formula to calculate expected time and variance:

Expected time=Optimistic time+(4×Most likely time)+Pessimistic time6

Standard deviation=Pessimistic timeOptimistic time6

Variance=(Pessimistic timeOptimistic time)262

Calculation of mean and variance:

Activity Optimistic time Most likely time Pessimistic time Expected time Standard deviation Variance
A B C (A+(4*B)+C)/6 (C-A)/6 (C-A)^2/6^2
A 2 4 6 4 0.667 0.444
D 6 8 10 8 0.667 0.444
E 7 9 12 9.17 0.833 0.694
H 2 3 5 3.17 0.500 0.250
F 3 4 8 4.5 0.833 0.694
G 5 7 9 7 0.667 0.444
B 2 2 3 2.17 0.167 0.028
I 2 3 6 3.33 0.667 0.444
J 3 4 5 4 0.333 0.111
K 4 5 8 5.33 0.667 0.444
C 5 8 12 8.17 1.167 1.361
M 1 1 1 1 0.000 0.000
N 6 7 11 7.5 0.833 0.694
O 8 9 13 9.5 0.833 0.694
End

Network diagram:

Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences), Chapter 17, Problem 12P , additional homework tip  2

The activity on arrow diagram is constructed. The activities are mentioned on the arrows. The arrows in the diagram are mentioned in the precedence order. The arrows indicates the successor for each node.

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The probability of each bonus.

Answer to Problem 12P

The probability of achieving a bonus of $1,000 is 0.4099. The probability of achieving a bonus of $500 is 0.6742.

Explanation of Solution

Given information:

  • If the project is finished in 26 weeks the bonus is $1,000.
  • If the project is finished in 27 weeks the bonus is $500.

Calculation of expected duration, variance and standard deviation for each path:

Path A-D-E-H:

Expected duration=4+8+9.17+3.17=24.34

Variance=0.444+0.444+0.694+0.250=1.832

Standard deviation=Variance=1.832=1.3535=1.354

Path A-F-G:

Expected duration=4+4.5+7=15.50

Variance=0.444+0.694+0.444=1.582

Standard deviation=Variance=1.582=1.2577=1.258

Path B-I-J-K:

Expected duration=2.17+3.33+4+5.33=14.83

Variance=0.028+0.444+0.111+0.444=1.027

Standard deviation=Variance=1.027=1.014

Path C-M-N-O:

Expected duration=8.17+1+7.50+9.50=26.17

Variance=1.361+0.0+0.694+0.694=2.749

Standard deviation=Variance=2.749=1.658

Bonus of $1,000 (less than or equal to 26 weeks):

Calculation of probability of completion in less than or equal to 26 weeks:

Calculation of z value for all paths:

Formula:

Z=Specified time-Path meanPath standard deviation

Path A-D-E-H:

Z=26-24.341.354=1.23

From the standard normal distribution table,

The probability value for (z = 1.23) is 0.8907.

Path A-F-G:

Z=26-15.501.258=8.35

Since z value is greater than +3.00, probability of completion is 1.0000.

Path B-I-J-K:

Z=26-14.831.014=11.02

Since z value is greater than +3.00, probability of completion is 1.0000.

Path C-M-N-O:

Z=26-26.171.658=0.10

From the standard normal distribution table,

The probability value for (z = -0.10) is 0.4602.

Probability of completion in less than or equal to 26 weeks:

Probability=0.8907×1.0000×1.0000×0.4602=0.4099

The probability of achieving a bonus of $1,000 is 0.4099.

Bonus of $500 (less than or equal to 27 weeks):

Calculation of probability of completion in less than or equal to 27 weeks:

Calculation of z value for all paths:

Formula:

Z=Specified timePath meanPath standard deviation

Path A-D-E-H:

Z=27-24.341.354=1.96

From the standard normal distribution table,

The probability value for (z = 1.96) is 0.9750.

Path A-F-G:

Z=27-15.501.258=9.14

Since z value is greater than +3.00, probability of completion is 1.0000.

Path B-I-J-K:

Z=27-14.831.014=12

Since z value is greater than +3.00, probability of completion is 1.0000.

Path C-M-N-O:

Z=27-26.171.658=0.50

From the standard normal distribution table,

The probability value for (z = 0.50) is 0.6915.

Probability of completion in less than or equal to 27 weeks:

Probability=0.9750×1.0000×1.0000×0.6915=0.6742

The probability of achieving a bonus of $500 is 0.6742.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
1) View the video Service Processing at BuyCostumes (10.41 minutes, Ctrl+Click on the link); what are your key takeaways (tie to one or more of the topics discussed in Chapter 3) after watching this video. (viddler.com/embed/a6b7054c)   Note: As a rough guideline, please try to keep the written submission to one or two paragraphs.   2) Orkhon Foods makes hand-held pies (among other products). The firm’s weekly sales of hand-held pies over the past seven weeks are given in the table. The firm’s operations manager, Amarjargal, wants to forecast sales for week 8.   Weeks Sales of hand-held pies(000s) 1 19 2 18 3 17 4 20 5 18 6 22 7 20 Forecast the week 8 sales using the following approaches:   a) Naïve approach b) 5-month moving average c) 3-month weighted moving average using the following weights: 0.50 for week 7, 0.30 for week 6, and 0.20 for week 5. d) Exponential smoothing using a smoothing constant of 0.30, assume a week 2…
What area of emotional intelligence refers to the ability to manage your emotions, particularly in stressful situations, and maintain a positive outlook despite setbacks?   relationship management   self awareness   social awareness   self management
What area of emotional intelligence refers to the ability to manage your emotions, particularly in stressful situations, and maintain a positive outlook despite setbacks?   relationship management   self awareness   social awareness   self management

Chapter 17 Solutions

Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)

Ch. 17 - Why might a person wish to be involved with a...Ch. 17 - Prob. 12DRQCh. 17 - What are some aspects of the project managers job...Ch. 17 - What is the main benefit of a project organization...Ch. 17 - What trade-offs are associated with time and cost...Ch. 17 - Who needs to be involved in assessing the cost of...Ch. 17 - Prob. 3TSCh. 17 - Project management techniques have been used...Ch. 17 - Give three examples of unethical conduct involving...Ch. 17 - For each of the following network diagrams,...Ch. 17 - Chris received new word processing software for...Ch. 17 - Prepare a Gantt chart for each of the following in...Ch. 17 - a. Develop a list of activities and their...Ch. 17 - For each of the problems listed, determine the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Three recent college graduates have formed a...Ch. 17 - The new director of special events at a large...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - The project described in the following table is...Ch. 17 - The following precedence diagram reflects three...Ch. 17 - A project manager has compiled a list of major...Ch. 17 - Here is a list of activity times for a project as...Ch. 17 - The project manager of a task force planning the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Chucks Custom Boats (CCB) builds luxury yachts to...Ch. 17 - Prob. 17PCh. 17 - Create a risk matrix in the style of Figure 17.13...Ch. 17 - Create a risk matrix for this project: Explain...Ch. 17 - CASE: The Case of the Mexican crazy quilt 1. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 2. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 3. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 4. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 5. The...Ch. 17 - B. Smitty Smith is a project manager for a large...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY