CASE: The Case of the Mexican crazy quilt
3. “The mission of the project which you will head is to get our new Mexican subsidiary ready for takeover by Mexican managers. My hope is that you will be able to do this in about two years,” explained Robert Linderman, president of Linderman Industries, Inc., to Carl Conway, newly appointed manager for “Operation Mexicano.” Conway had been hired specifically for this assignment because of his experience in managing large defense projects in the aerospace industry.
“The first thing that I will have to do is put a project team together,” said Conway. “I imagine that you have in mind my drawing people from the functional divisions.”
“Yes, I have already sent memoranda to the division managers informing them that you will be asking for some of their key people to work under you for about two years,” said Linderman. “In addition, I have advised them to be prepared to process work orders from Operation Mexicano with the personnel and equipment of their organizations. Later on in the project’s life, you will begin to get Mexican personnel, both managers and technicians, into your organization. These people will have Mexican supervisors, but until the mission is accomplished, they also will report to you. I will have to admit that you are going to have some complex authority relationships, especially as you personally will be responsible to the president of the subsidiary, Felix Delgado, as well as to me.”
Conway began to make his plans for the project team. The plant building was available and empty in Mexico City, and it was important to get equipment purchased and installed as soon as possible. A plant layout would have to be prepared, but before that could be done there would have to be a manufacturing plan. Therefore, he needed to recruit an industrial engineer, a production planner, and an equipment buyer. They, in turn, would have to build their own staffs.
He made an appointment with Sam Sargis, corporate manager of industrial engineering. “I have had a preliminary talk with Bob Cates about his joining Operation Mexicano, and he is quite interested,” Carl said. “Will you release him to me?”
“Why, I’m grooming Cates to take over my job when I retire,” replied Sargis. “He is my best man. Let me pick someone else for you, or better still, you just tell me what industrial engineering work you want done, and I will have it done for you.”
“Sorry, I want Cates,” said Carl firmly. “And besides, you are not due to retire for five years. This will be good experience for him.”
For production planning, Carl had in mind Bert Mill, an older man with extensive experience in managing production operations, but Mill rejected his offer. “I talked it over with my wife,” he said, “and we feel that at my age I shouldn’t take a chance on not having a job to come back to when Operation Mexicano is finished.”
Carl next talked to Emil Banowetz, who was assistant to Jim Burke, the vice president for manufacturing, and Banowetz decided that he would like to join the project team. However, Burke told Conway that if Banowetz were forcibly taken away from him, he would give Mr. Linderman his resignation, so Carl decided to back down. He finally accepted a man that Burke recommended.
Filling the equipment buyer’s slot was easy. The director of procurement phoned Carl and said that a senior buyer, Humberto Guzman, had requested permission to ask for the assignment, and that he strongly recommended him. Guzman has been purchasing agent for a large mining company in Mexico for about 10 years.
Carl had about the same experiences in getting the people he wanted for the functions of engineering, quality control, cost, marketing, and advertising as he did for the first three positions; in other words, he won some confrontations with the division managers and lost some. For personnel, he got Dr. Juan Perez, who was slated to be personnel director of the subsidiary company, to affiliate temporarily with the project team.
The first brush that Project Mexicano had in getting a functional division to do work for it came when Carl’s engineering man, Frank Fong, reported to him that the engineering vice president, who was formerly Fong’s boss, refused to authorize top priority to the changing of dimensions in the production drawings to the metric system. Carl had to take this issue to Linderman, who ruled in his favor. The defeated vice president, of course, did not take kindly to the decision.
The next incident revolved around Carl’s desire to have a pilot run of products made with metric measurements for shipment to Mexico. The purpose was to test the market acceptance of the Linderman articles. Jim Burke stated flatly that there was no way that his production workers could be trained to work with metric drawings. Carl quickly saw that this was an issue that he was not going to win, so he had his buyer, Guzman, work with the newly appointed manufacturing manager for the subsidiary in getting a run of the products subcontracted in Mexico City.
Bob Cates made a special trip from Mexico City to present Carl with an interesting problem. The Mexican industrial engineer, whom Bob was supposed to be training, had his own ideas about plant layout. When they differed from Bob’s as they usually did, he would take his complaint directly to Felix Delgado, the president of the Mexican subsidiary. Because Delgado’s competence was primarily in finance, he would not know how to decide the argument and would simply table it. Carl took examples of some of the disagreements to Bob’s former boss, Sam Sargis, who quite unexpectedly ruled against Bob’s proposed methods. Carl saw that there was bad feeling by Sargis against Bob for leaving his department, which boded ill for Bob’s return. To solve the immediate problem, however, Carl asked Dr. Perez to try to reconcile the situation in Mexico City.
Despite these problems, and many more of a similar nature, Project Mexicano was successful, and the transition to Mexican management was made in just a little over two years. By a curious twist, through Dr. Perez’s intercession Felix Delgado became very impressed by Bob Cates and convinced him to accept the job of director of industrial engineering for the Mexican company. Humberto Guzman also stayed on to head the procurement operation.
Other members of the project team were not so fortunate. Linderman Industries was laying off personnel when the project ended, and only the project production man was able to get a job in the company at as high a level as the one he had when he joined the team. The cost expert elected to leave Linderman because he said the glamour of Project Mexicano had spoiled him for any routine job.
Carl Conway had a difficult decision of his own to make. Robert Linderman said that he was extremely pleased with his performance and that something good would open up in the company for him soon. In the meantime, there was a staff assignment available for him. Carl had seen enough project managers in the aerospace industry who had figuratively rotted on staff assignments when their projects were completed to be somewhat wary.
Would you expect that many people would turn down a chance to join a project organization, as Bert Mill did?
Source: Clayton Reeser and Marvin Loper, Management: The Key to Organizational Effectiveness, rev. ed. Copyright © 1978.
Want to see the full answer?
Check out a sample textbook solutionChapter 17 Solutions
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
- Some projects do not continue to completion due to various reasons. Discuss any five reasons why a project could be terminated before the completion date.arrow_forwardStudents shall, with a point of view of him/herself as project manager (PM), submit a Project Management Plan (PMP) for the given engineering project below: - “Procurement & Installation of Emergency Generator at Fire station” Students are allowed to propose their own project, given that the projects shall have enough scale to address the element described below:- a. Student should produce a project definition statement regarding the proposed project. b. Student should propose a suitable project team to carry out the project. Student should in the PMP describe the duties and power of different team memebrs in the project. c. The PMP shall include a risk management plan, which student shall identify, analyse and proposed mitigations measures for smooth delivery of the project deliverables. The risk manamgenet plan shall include a risk register d. The PMP shall include a quality management plan, which student shall propose a method statement to control the quality of the delivery of…arrow_forwardBefore projects can proceed, a contract must be drawn up between the customer and contractor.Define what is a typical project contract then using practical examples, discuss two (2) types ofproject contracts that may be entered into between the customer and contractor.arrow_forward
- ScenarioImagine that you are a project manager responsible for a medical health services project which will benefit low-income earners, the unemployed, and the homeless. The project is quite large and consists of the sourcing and acquisition of medical professionals, medical supplies, and medical establishments to provide the services stipulated by the project charter. The sponsor of the project is the Ministry of Health of the local government of the country that you live in. Where should you begin? How do you decide which medical professionals to choose? What medical supplies are needed and where will you conduct your medical service checks? Take a look at the medical services project. What selection criteria based on the list of various criteria would you consider to be important for a project of this magnitude?arrow_forwardwhat is a project constraintarrow_forwardA project has three critical paths: A-B-C-D-E, A-G-H-E, and A-F-I-E. Crashing costs (in thousands, per week) for each activity is listed below: Activity Crashing 1st time Crashing 2nd time Crashing 3rd time 35 2 28 1 C 29 4 1 8 8 4 E 34 1 IF 34 28 3 G 27 19 1 8 7 1 5 4 What is the total cost of reducing this project by two weeks? а. 36 b. 58 С. 69 d. 43 57 LO e.arrow_forward
- The following bar chart shows the activities for a project. The total project cost is $1,545. Time (weeks) 6 7 Total Activity Cost 2 3 4 8 | 9 10 A $120 В $35 $80 D $270 E $60 F $180 $270 $90 G J $160 K $60 L $220 $1,545 After three weeks, Activities A, C, E, half of B, quarter of F, and two thirds of H are completed for a cost of $435. At this point in time (three weeks after the start date), what is the status of the project in terms of budget (over or under budget) and schedule (ahead or behind schedule)? Use SPI and CPI to determine your answers.arrow_forwardWhich company to be selected for project execution consiering the weighting factor for each criterion given in the attached table? show all your calculations?arrow_forwardI need assistance with the following questions in: Project Scheduling. This is a follow up to a question answered earlier. Question 1) was answered. 1) A company decides to plan a project, with activities, precedences and deterministic durations given in the following table: Activity i Duration (days) Immediate Predecessors A 32 none B 21 none C 30 none D 45 A E 26 A, B F 28 C G 20 E, F 2) The company decided that the project in the previous problem has to be expedited in order to optimize (minimize) the project cost. Expediting can be used to trade direct cost for indirect cost, since expediting the project reduces the indirect cost of the project by a fixed amount per day, while expediting an activity increases its total direct cost. The Accounting Department found that indirect costs amount to $100 per day, while activity direct costs as well as their normal and expedited times are given in the table below.…arrow_forward
- 9. A project has the following activities, with specified precedents, expected durations (in days), and crash cost/day. Each activity can be crashed to a minimum duration of 1 day. (This is the same network as a previous problem.) What is the minimum total cost to shorten the project by 2 days? Round your answers to 2 decimals. Activity Precedent Duration Crash cost/day A - 3 $350 B A 3.8 $250 C A 6 $400 D B 6 $150 E B 4.1 $200 F C 4 $275 G D 6.2 $500 H E 8 $300 Answer:arrow_forwardThe company decided that the project in the previous problem had to be expedite in order to optimize (minimize) the project cost. Expediting can be used to trade direct cost for indirect cost, since expediting reduces the indirect cost of the project by a fixed amount per day, while expediting an activity increases its total direct cost. The Accounting Department found that indirect costs amount to $100 per day, while activity direct costs as well as their normal and expedited times are given in the table below. Activity Duration (Days) Expedited Time (Days) Normal Direct Cost ($) Expedited Direct Cost ($) A 32 26 200 500 B 21 20 300 375 C 30 30 200 200 D 45 40 200 800 E 26 20 700 1,360 F 28 24 1,000 1,160 G 20 18 400 550 What is the optimal time to complete the project? What is the optimal project cost?arrow_forwardSometimes a decision needs to be made to shutdown a project through early termination. Describe the 'emotional issues' of the project team, and the 'intellectual issues' internal to the organisation, when shutting down a project through early termination.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.