Concept explainers
Three recent college graduates have formed a
a. Draw the precedence diagram.
b. What is the probability that the project can be completed in 24 days or less? In 21 days or less?
c. Suppose it is now the end of the seventh day and that activities A and B have been completed while activity D is 50 percent completed. Time estimates for the completion of activity D are 5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing the project by day 24 and the probability of finishing by day 21.
d. The partners have decided that shortening the project by two days would be beneficial, as long as it doesn’t cost more than about $20,000. They have estimated the daily crashing costs for each activity in thousands, as shown in the following table. Which activities should be crashed, and what further analysis would they probably want to do?
a)
To draw: A precedence diagram.
Answer to Problem 7P
Precedence diagram:
Explanation of Solution
Given information:
Activity | Immediate Predecessor | Optimistic time | Most likely time | Pessimistic time |
A | 5 | 6 | 7 | |
B | 8 | 8 | 11 | |
C | A | 6 | 8 | 11 |
D | 9 | 12 | 15 | |
E | C | 5 | 6 | 9 |
F | D | 5 | 6 | 7 |
G | F | 2 | 3 | 7 |
H | B | 4 | 4 | 5 |
I | H | 5 | 7 | 8 |
End | E, G, I |
Activity | First crash | Second crash |
C | $ 8.00 | $ 10.00 |
D | $ 10.00 | $ 11.00 |
E | $ 9.00 | $ 10.00 |
F | $ 7.00 | $ 9.00 |
G | $ 8.00 | $ 9.00 |
H | $ 7.00 | $ 8.00 |
I | $ 6.00 | $ 8.00 |
Precedence diagram:
The precedence diagram is drawn from the first task till the last task. The activities are placed from left to right. The directions are represented with arrows to indicate the relationship between activities. The arrows are represented with the activity name.
b)
To determine: The probability at which the projected can be completed in 24 days or less and 21 days or less.
Answer to Problem 7P
24 days or less = 0.9686
21 days or less = 0.2350
Explanation of Solution
Given information:
Activity | Immediate Predecessor | Optimistic time | Most likely time | Pessimistic time |
A | 5 | 6 | 7 | |
B | 8 | 8 | 11 | |
C | A | 6 | 8 | 11 |
D | 9 | 12 | 15 | |
E | C | 5 | 6 | 9 |
F | D | 5 | 6 | 7 |
G | F | 2 | 3 | 7 |
H | B | 4 | 4 | 5 |
I | H | 5 | 7 | 8 |
End | E, G, I |
Activity | First crash | Second crash |
C | $ 8.00 | $ 10.00 |
D | $ 10.00 | $ 11.00 |
E | $ 9.00 | $ 10.00 |
F | $ 7.00 | $ 9.00 |
G | $ 8.00 | $ 9.00 |
H | $ 7.00 | $ 8.00 |
I | $ 6.00 | $ 8.00 |
Formula to calculate expected time and variance:
Calculation of expected time and variance:
Activity | Optimistic time | Most likely time | Pessimistic time | Expected time | Standard deviation | Variance |
A | B | C | (A+(4*B)+C)/6 | (C-A)/6 | (C-A)^2/6^2 | |
A | 5 | 6 | 7 | 6 | 0.333 | 0.111 |
B | 8 | 8 | 11 | 8.5 | 0.500 | 0.250 |
C | 6 | 8 | 11 | 8.17 | 0.833 | 0.694 |
D | 9 | 12 | 15 | 12 | 1.000 | 1.000 |
E | 5 | 6 | 9 | 6.33 | 0.667 | 0.444 |
F | 5 | 6 | 7 | 6 | 0.333 | 0.111 |
G | 2 | 3 | 7 | 3.5 | 0.833 | 0.694 |
H | 4 | 4 | 5 | 4.17 | 0.167 | 0.028 |
I | 5 | 7 | 8 | 6.83 | 0.500 | 0.250 |
Calculation of expected duration, variance and standard deviation for each path:
A-C-E:
D-F-G:
B-H-I:
Calculation of z value for all paths:
Formula:
24 days or less:
A-C-E:
Since z value is greater than +3.00, probability of completion is 1.00.
D-F-G:
From the standard normal distribution table,
The probability value for (z = 1.86) is 0.9686.
B-H-I:
Since z value is greater than +3.00, probability of completion is 1.00.
Probability of completion in 24 days or less:
The probability at which the project can be completed in 24 days or less is 0.9686.
21 days or less:
A-C-E:
From the standard normal distribution table,
The probability value for (z = 0.45) is 0.6736.
D-F-G:
From the standard normal distribution table,
The probability value for (z = -0.37) is 0.3557.
B-H-I:
From the standard normal distribution table,
The probability value for (z = 2.07) is 0.9808.
Probability of completion in 21 days or less:
The probability at which the project can be completed in 21 days or less is 0.2350.
c)
To determine: The probability of completing the project by day 24 and day 21.
Answer to Problem 7P
Day 24 = 0.9328
Day 21 = 0.0186
Explanation of Solution
Given information:
- At the end of 7th day activities A and B are completed and D is 50% completed.
- Time estimates of activity D completion are 5, 6 and 7.
- Activities C and H are ready to begin.
Activity | Immediate Predecessor | Optimistic time | Most likely time | Pessimistic time |
A | 5 | 6 | 7 | |
B | 8 | 8 | 11 | |
C | A | 6 | 8 | 11 |
D | 5 | 6 | 7 | |
E | C | 5 | 6 | 9 |
F | D | 5 | 6 | 7 |
G | F | 2 | 3 | 7 |
H | B | 4 | 4 | 5 |
I | H | 5 | 7 | 8 |
End | E, G, I |
Activity | First crash | Second crash |
C | $ 8.00 | $ 10.00 |
D | $ 10.00 | $ 11.00 |
E | $ 9.00 | $ 10.00 |
F | $ 7.00 | $ 9.00 |
G | $ 8.00 | $ 9.00 |
H | $ 7.00 | $ 8.00 |
I | $ 6.00 | $ 8.00 |
Formula to calculate expected time and variance:
Calculation of expected time and variance:
Activity | Optimistic time | Most likely time | Pessimistic time | Expected time | Standard deviation | Variance |
A | B | C | (A+(4*B)+C)/6 | (C-A)/6 | (C-A)^2/6^2 | |
A | 5 | 6 | 7 | 6 | 0.333 | 0.111 |
B | 8 | 8 | 11 | 8.5 | 0.500 | 0.250 |
C | 6 | 8 | 11 | 8.17 | 0.833 | 0.694 |
D | 5 | 6 | 7 | 6 | 0.333 | 0.111 |
E | 5 | 6 | 9 | 6.33 | 0.667 | 0.444 |
F | 5 | 6 | 7 | 6 | 0.333 | 0.111 |
G | 2 | 3 | 7 | 3.5 | 0.833 | 0.694 |
H | 4 | 4 | 5 | 4.17 | 0.167 | 0.028 |
I | 5 | 7 | 8 | 6.83 | 0.500 | 0.250 |
Revised project diagram:
Calculation of expected duration, variance and standard deviation for each path:
C-E:
D-F-G:
H-I:
Calculation of z value for all paths:
Formula:
24 days or less:
C-E:
From the standard normal distribution table,
The probability value for (z = 2.34) is 0.9904.
D-F-G:
From the standard normal distribution table,
The probability value for (z = 1.57) is 0.9418.
H-I:
Since z value is greater than +3.00, probability of completion is 1.00.
Probability of completion in 24 days or less:
The probability at which the project can be completed in 24 days is 0.9328.
21 days or less:
C-E:
From the standard normal distribution table,
The probability value for (z = -0.47) is 0.3192.
D-F-G:
From the standard normal distribution table,
The probability value for (z = -1.57) is 0.0582.
H-I:
Since z value is greater than +3.00, probability of completion is 1.00.
Probability of completion in 21 days or less:
The probability at which the project can be completed in 21 days is 0.0186.
d)
To determine: The activities that should be crashed and further analysis.
Explanation of Solution
Given information:
- The partners want to shorten the project by 2 days as long as the cost is not more than $20,000.
Activity | Immediate Predecessor | Optimistic time | Most likely time | Pessimistic time |
A | 5 | 6 | 7 | |
B | 8 | 8 | 11 | |
C | A | 6 | 8 | 11 |
D | 5 | 6 | 7 | |
E | C | 5 | 6 | 9 |
F | D | 5 | 6 | 7 |
G | F | 2 | 3 | 7 |
H | B | 4 | 4 | 5 |
I | H | 5 | 7 | 8 |
End | E, G, I |
Activity | First crash | Second crash |
C | $ 8.00 | $ 10.00 |
D | $ 10.00 | $ 11.00 |
E | $ 9.00 | $ 10.00 |
F | $ 7.00 | $ 9.00 |
G | $ 8.00 | $ 9.00 |
H | $ 7.00 | $ 8.00 |
I | $ 6.00 | $ 8.00 |
Paths and expected duration:
Paths | Expected Duration |
C-E | 21.50 |
D-F-G | 22.50 |
H-I | 18.00 |
The critical path is D – F – G.
The activities are crashed based on the cost of crash given.
Activity | Cost |
F | $7 |
G | $8 |
D | $10 |
Step 1:
Activity F has the lowest crashing cost ($7,000) and will be crashed first for 1 day. The expected duration of D-F-G will be 21.50 days.
Step 2:
Path | Expected Duration |
C-E | 21.50 |
D-F-G | 21.50 |
H-I | 18.00 |
Now there are two critical paths C-E and D-F-G.
The critical activities are arranged in the order of low crash costs.
Path | Activity | Cost |
C-E | C | $8 |
F | $9 |
Path | Activity | Cost |
D-F-G | D | $8 |
F | $9 | |
G | $10 |
One activity in each path is chosen to crash.
Activity C is crashed for 1 day since it has the lowest crashing cost ($8,000) on path C-E. The expected duration of path C-E is now 20.50 days.
Activity G is crashed for 1 day since it has the lowest crashing cost ($8,000) on path D-F-G. The expected duration of path D-F-G is now 20.50 days.
Calculation of total crashing cost:
The total cost of crashing is over the budget of $20,000 ($23,000 > $20,000). Hence, the partners will have to determine if crashing the project by 1 day or 2 days is really beneficial or not.
Want to see more full solutions like this?
Chapter 17 Solutions
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
- I need to forecast using a 3-Period-Moving-Average-Monthly forecasting model which I did but then I need to use my forecast numbers to generate a Master Production Schedule (MPS) I have to Start with actual sales (my own test data numbers) for August-2022 Oct-2022 i need to create MPS to supply demand starting November-2022 April 2023 I just added numbers without applying formulas to the mps on the right side of the spreadsheet because I do not know how to do it. The second image is the example of what it should look like. Thank You.arrow_forwardSolve the following Question 1. How do volume and variety affect the process selection and layout types? Discuss 2. How is the human resource aspect important to operation function? Discuss 3. Discuss the supply network design and its impact on the overall performance of the organization.arrow_forwardHelp with question?arrow_forward
- What are some good examples of bullet points on a resume for a Christian Elementary School?arrow_forwardWhat is an example of a cover letter for a Christian School Long-Term Substitute Teaching position?arrow_forwardThe supply chain is a conventional notion, but organizations are only really interested in making products that they can sell to customers. Provided they have reliable supplies of materials and reasonable transport for finished products, logistics is irrelevant. Do you think this is true? If yes, explain, and if no, clearly explain as well.arrow_forward
- working as a program operations managerarrow_forward12 X1, X230 1 x =0x2 write the Following linear Programming model by 1- general Form Canonical Forms Canonical formY 2- Standard Form Max Z=35X+ 4 X 2 +6 X3 ST. X+2X2-5x3 = 40 3X, + 6X2 + 7x 3 = 30 7x, +lox2 x3 = 50 X3 X 2 X 3 <0arrow_forwarda/ a Minimum cost assign each worker for one job at Jobs J1 12 33 WI 2 4 6 W2 5 W3 5 33 6 7arrow_forward
- وبة واضافة هذه القيمة الى القيم Ex: Assign each job for each worker at minimum total Cost عمل لكل عامل وبأقل كلفة ممكنة obs الأعمال Workors العمال J1 J2 J3 J4 W₁ 15 13 14 12 W2 11 12 15 13 W3 13 12 10 11 W4 15 17 14 16arrow_forwardThe average completion time (flow time) for the sequence developed using the FCFS rule = 11.75 days (round your response to two decimal places). The percentage utilization for the sequence developed using the FCFS rule = 42.55 % (enter your response as a percentage rounded to two decimal places). b) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: Job Due Date A 212 B 209 C 208 D 210 Duration (days) 6 3 3 8 Sequence 1 Job B 2 3 4 A D The average tardiness (job lateness) for the sequence developed using the SPT rule = 5.00 days (round your response to two decimal places). The average completion time (flow time) for the sequence developed using the SPT rule = 10.25 days…arrow_forwardWith the aid of examples, fully discuss any five (5) political tactics used in organisations.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.