Operations Management
Operations Management
13th Edition
ISBN: 9781259667473
Author: William J Stevenson
Publisher: McGraw-Hill Education
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 14, Problem 9P
Summary Introduction

To determine: Takt time if match capacity and demand.

Introduction: Takt refers to “musical meter” or “pulse” in German. Takt time is the process duration required in a production system to counterpart the velocity of manufacturing to the request rate. It is once in a while said to be the pulse of a lean production system. It is the greatest measure of time in which an item should be delivered with a specific end goal to fulfill client request.

Blurred answer
Students have asked these similar questions
A call center has been serving 900 customers per day, with a 10% capacity cushion. There have been complaints about the length of time customers have to wait before their call is answered. If the manager of the call center wants to double the capacity cushion, how much extra capacity is needed?
Raj’s Dental Clinic provides general dental care to residents of Hoboken on a walk-in basis. Theclinic has started receiving complaints from patients that the waiting time is too long and has askedyou to investigate whether this problem can be solved.Upon arrival, customers first receive a series of paperwork from the receptionist and fill out relevantinformation such as personal health records and insurance provider. The form is then handed backto the receptionist who enters the information into the computer system for the dentist to see. Adental assistant then takes an X-ray from the patient. A dentist then performs the checkup anddiscusses any issues with the patient.Based on conversations with staff members at the clinic, you have obtained the following informationon the process:• It takes about 5 minutes for a customer to fill out the paperwork.• Entry of information on the paperwork into the system and verification with past recordstakes another 5 minutes for a receptionist.…
Compute the capacity (i.e. processing rate) for each of the following scenarios. Convertyour answers to parts per hour.a. A four-station line with single-machine stations, where the average processing timesare 15, 20, 10 and 12 minutes, respectively.b. A three-station line where the number of machines at stations 1, 2 and 3 is 2, 6, and3, respectively; and the average processing times are 10, 24 and 18 minutes,respectively.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY