What might Stephanie determine as the best production quantity per cycle for each day of the week?
To determine: The production sequence for cycle are S7, S8, S9, S1 and S2.
Introduction: A production cycle is a period through which the factors required by labors such as raw materials and goods stay in the creation process from the initial starting point of assembling through yield of finished goods.
Answer to Problem 1CQ
Explanation of Solution
Given Information:
Model | Weekly Quantity |
S1 | 120 |
S2 | 102 |
S7 | 48 |
S8 | 90 |
S9 | 25 |
The department operates five days a week. The production sequence is S7-S8-S9-S1-S2.
Calculate the daily demand for each model:
The demand for each model is calculated by dividing daily quantity of each model with total operational days.
Calculate the number of units per cycle for each model
It is calculated by dividing the daily demands with total operational days.
Calculate the production quantity per cycle for each day for 5 days from Monday to Friday.
This can be subjective. Production cycle should be on the sequence S7-S8-S9-S1-S2 done each cycle. We attempted to produce the same aggregate amount of units for every cycle. Whether this might have been not possible, we attempted with plan fewer units on the most last cycle of a day will consider getting up every day.
Excel Spreadsheet:
Calculate the production quantity per cycle for each model:
It is calculated by adding all the total values of each cycle from Monday to Friday.
Hence, the production sequence for cycle S7 is 48, S8 is 90, S9 is 25, S1 is 120 and S2 is 102.
Want to see more full solutions like this?
Chapter 14 Solutions
Operations Management
- What do the expressions order winner and order qualifiers mean? What was the order winner for your last major purchase of a product or service?arrow_forwardEZ-Windows, Inc. manufacturers replacement windows for the home remodeling business. In January, the company produces 15,000 windows and ended the month with 9,000 windows in inventory. EZ-Windows' management team would like to develop a production schedule for the next three months. A smooth production schedule is obviously desirable because it maintains the current workforce and provides a similar month-to-month operation. However, given the sales forecasts, the productioncapacities, and the storage capabilities as shown in Table 2, the management team does not think a smooth production schedule with the same production quantity each month possible.The company's cost accounting department estimates that increasing production by one window from one month to the next will increase total costs by $1.00 for each unit increase in the production level. In addition, decreasing production by one unit from one month to the next will increase total costs by $0.65 for each unit decrease in the…arrow_forwardWhen creating an Event, which field reflects the current stage of the negotiating process and controls whether the rooms, space, and items will deduct from inventory?arrow_forward
- A forecast of 240 units in January, 320 units in February, and 240 units in March has been approved for the seismic-sensory product family manufactured at the Rockport facility of Maryland Automated, Inc. Three products, A, B, and C, comprise this family. The product mix ratio for products A, B, and C for the past 2 years has been 35 percent, 40 percent,and 25 percent, respectively. Management believes that the monthly forecast requirements are evenly spread over the 4 weeks of each month. Currently, 10 units of product C are on hand. The company produces product C in lots of 40, and the lead time is 2 weeks. A production quantity of 40 units from the previous period is scheduled to arrive in week 1. Thecompany has accepted orders of 25, 12, 8, 10, 2, and 3 units of product C in weeks 1 through 6, respectively. Prepare a prospective MPS for product C and calculate the availableto-promise inventory quantities.arrow_forwardExplain how can minimization be performed with simplex methods ?arrow_forwardINSTRUCTIONS: We're looking to work with a new publisher that is interested in selling us two different placements. The publisher has told us that placement 1 has an approximate CTR of 0.3% and will get 2M impressions per month. Placement 2 has an approximate CTR of 0.4% and will get 3M impressions. The CPM for Placement 1 is $5, CPM for Placement 2 is 6$ The conversion rate of our landing page is 8% and the leads generated all are worth $50. Please use the worksheet outlined below to fill in the highlighted cells with the answers you find. 1. What is the total cost? 2. What is the total revenue and retutn on ad spend? 3. What is the total clickthrough rate (CTR)? 4. Which placement is more effective in terms of ROAS? Placement 1 Placement 2 Total Impressions 2,000,000 3,000,000 CTR 0.30% 0.40% CR 8.00% 8.00% Clicks Leads = Impressions * CTR = Clicks * CR Revenue = Leads RPL DEFINITIONS: Revenue: Money generated from leads submitted by visitors filling out forms. Impressions: The…arrow_forward
- 1. Develop an aggregate plan for the following forecast Period 3 4 5 6 7 Total 1 2 8 Forecast 190 230 260 280 210 170 160 260 180 1,940 There are 20 workers who can produce 10 units per period at a cost of P6.00 per unit. There is no beginning invetory and the cost of carrying inventory is P5.00 per unit per period. Backlog cost is P10.00 per unit per period. Will the present workforce able to produce the forecast? b. What is the total cost of the plan? a.arrow_forwardCompile and discuss a simple cattle production plan. Which date will you mate them,when will the calves be born, when will you wean the calves.arrow_forwarda. How much should be produced each period? b. What is ending inventory for each period? c. If inventory carrying cost is $3 per case per period based on ending inventory, what is the total cost of carrying inventory? d. What is the total plan cost and why? 4. The opening backlog is 1200 units. Forecast demand is shown below. a. Calculate the weekly production for level production if the backlog is to be reduced to 1000 units, b. Calculate the projected backlog for each week. Week 2 4 3 1200 1200 Forecast 1200 Demand Planned Production Projected Backlog 1200 1100 5 1100 25 20 6 1000 Total 5. A firm plans to make 400 wagons, 200 carts, and 100 sleds. The resource bill shown below displays the amount of critical resources needed to make one average unit of product family: Wood (Board Feet) Labor (Standard Hours) Product Wagon 0.75 0.50 1.00 Cart Sled 30 Calculate the total wood AND labor needed to make the total number of items in the product family.arrow_forward