PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
11th Edition
ISBN: 9780135226742
Author: HEIZER
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 14, Problem 29P
Summary Introduction
To determine: The capacity plan for the 10 week period.
Introduction:
Capacity plan:
Capacity plan is the plan determined by a firm to meet its changing demand requirements. The plan is formulated keeping in mind the maximum design capacity of the firm.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Coleman Rich, Ltd., has received the followingorders:Period 1 2 3 4 5 6 7 8 9 10Order size 60 30 10 40 70 10 40 30 40 0The entire fabrication for these units is scheduled on one machine.There are 2,250 usable minutes in a week, and each unit will take
65 minutes to complete. Develop a capacity plan, using lot split-ting, for the 10-week time period.
Coleman Rich, Ltd., has received the followingorders:
The entire fabrication for these units is scheduled on onemachine. There are 2,250 usable minutes in a week, and eachunit will take 65 minutes to complete. Develop a capacityplan, using lot splitting, for the 10-week time period
Balance the assembly line using Ranked Positional Weight method using the data in Table 2 and determine the idle time at each station. The
cycle time for meeting the demand is 38 minutes.
тable 2
Time
Immediate
Operation
(min)
predecessor
A
B
3
C
10
А, В
D
13
E
19
24
22
16
Chapter 14 Solutions
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
Ch. 14 - Ethical Dilemma For many months your prospective...Ch. 14 - What is the difference between a gross...Ch. 14 - Prob. 2DQCh. 14 - What are the similarities between MRP and DRP?Ch. 14 - How does MRP II differ from MRP?Ch. 14 - Which is the best lot-sizing policy for...Ch. 14 - What impact does ignoring carrying cost in the...Ch. 14 - MRP is more than an inventory system; what...Ch. 14 - What are the options for the production planner...Ch. 14 - Master schedules are expressed in three different...
Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Prob. 17PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 19PCh. 14 - Prob. 20PCh. 14 - Prob. 21PCh. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 28PCh. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1CSCh. 14 - Prob. 2CSCh. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - Prob. 2.1VCCh. 14 - Prob. 2.2VCCh. 14 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- What information is necessary for random stocking towork?arrow_forwardAn assembly plant for the Blood Pressure RX, a portable blood pressure device, has 400 minutes available daily in the plant for the device, and the average demand is 80 units per day. Final assembly requires 6 separate tasks. Information concerning these tasks is given in the following table. Task Performance Time (minutes) Task Must Follow Task Listed Below A 4 - B 1 - C 1 A, B D 3 C E 4 D F 2 E b) Given the demand, what is the cycle time for this operation? The cycle time for this operation is enter your response here minutes/unit (enter your response as a whole number). c) What is the theoretical minimum number of workstations? The theoretical minimum number of workstations is enter your response here stations (enter your response as a whole number and, if your unrounded answer includes decimal values,…arrow_forwardFor manufacturing electric bus Total labor hours, estimation process, and summary resultsarrow_forward
- Answer both clearlyarrow_forwardExplain the techniques to deal with bottleneck operations and some of those techniques that does not decrease throughput time ?arrow_forward9. Item WWW is produced in a transfer line. Determine daily output rate given the following processing times and unit transfer strategy between the machines. 1 process 3nd process 5th process Machine J process 4th process Machine LL Machine D Machine RR Machine S Unit process .15 hr |.12 .18 .16 .12 time Note: 2 shifts work. 8 hours/shift. 10. How can we increase the output in the above problem? Discuss and show results. 11. Item YYY is processed on machine M1 first and then machine M2. The desired annual output is 5000 units. Unfortunately, there are quality issues and the scrap factor for M1 is 0.05 and for M2 is 0.10. Determine how many units we have to start the process with. 12. Repeat problem 11 if we could recover 2% of scraps on M1 and 4% of scraps on M2.arrow_forward
- Describe the techniques to deal with bottleneck operations and some of those techniques that does not decrease throughput time ?arrow_forwardFour hundred and eighty minutes of production time are available per day. Scheduled production is 120 units per day. What is the required cycle time?arrow_forwardYou've just been assigned the job of setting up an electric fan assembly line with the following tasks and precedence relationships The assemtly line wil be nunning 8 hours per day and 5 days per week, The demand forast is 600 Items per week. Your goal is to minimie the numbor of workstations necesary to complete enough units to satisfy the demand forecast. What is the takt time (in minutes) needed to produce the required number of units? (Integer Answer, do not put anything other than numbers.) What is the theoretical minimum number of workstations that you will need (apply the round-up rule)? (Integer Answer, do not put anything other than numbers.)arrow_forward
- manufacturer operates 8 hours per day for 340 days per year, and has a demand of 2,000 units per day. There are four production cycles per day. Assume the following: 7,700 units produced per day, holding cost per unit is $5 per year, labor rate to do line set-ups is $13 per hour. With quick set-ups, the production line must be quickly re-organized. a. What is the target set-up cost? b. What is the set-up time in minutes?arrow_forwardManufacturing Company uses FIFO method of accumulating costs in a two-department process. Materials are introduced at the inception of the process except for a special material which is added in department 2 at 60% completion as to overhead. Inspection is done at the end of the process in both departments. Production data for Department 2 are given below: In process, beginning, (80% labor, 70% overhead)2,000 Transferred in 14,900 In process, ending (40% labor, 20% overhead) 3,000 Normal spoilage 200 Abnormal spoilage (found at 30% completion as to laborand 15% as to overhead due to internal failure) 400 Cost data for the month:In process beginning:Transferred in 15,020 Special materials 1,900 Direct labor 4,388 Overhead 11,044 Current costs:Transferred in 137,080 Special materials 14,030 Direct labor 46,000 Overhead 113,564 The cost of units transferred to finished goods is?The cost of spoilage charged to revenue is?arrow_forwardWhich operation is the bottleneck of this process? a. Stocking b. Pricing c. Spotting d. Shipping e. Impossible to determinearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY