Concept explainers
Grace Greenberg, production planner for Science and Technology Labs, in New Jersey, has the master production plan shown below:
Lead time = 1 period; setup cost = $200; holding cost = $10 per week; stockout cost = $10 per week. Develop an ordering plan and costs for Grace, using these techniques:
a) Lot-for-lot.
b) EOQ.
c) POQ.
d) Which plan has the lowest cost?
a)
To determine: The ordering plan and cost for Lot for lot.
Introduction:
Lot for Lot:
The lot for lot method of requirements plan is the process where the planned order release will be equal to the net requirement of the period.
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.
Answer to Problem 27P
The cost for Lot for lot is $1,200.
Explanation of Solution
Given information:
Period (weeks) | |||||||||||||
Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | Total |
Gross requirements | 35 | 40 | 10 | 25 | 10 | 45 | 165 |
Holding cost = $10 / week
Setup cost = $200
Lead time = 1 period
Stockout cost = $10 / week
Lot for lot:
Net requirements plan:
Period (weeks) | |||||||||||||
Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | Total |
Gross requirements | 35 | 40 | 10 | 25 | 10 | 45 | 165 | ||||||
Scheduled receipt | |||||||||||||
On hand (0) | 0 | 0 | 0 | 0 | 0 | 0 | |||||||
Ending inventory | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||||||
Net requirement | 35 | 40 | 10 | 25 | 10 | 45 | |||||||
Planned order receipt | 35 | 40 | 10 | 25 | 10 | 45 | |||||||
Planned order release | 35 | 40 | 10 | 25 | 10 | 45 |
Week 2:
The gross requirement is 35 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 35. The lead time is 1 week. Therefore, the planned order release will be 35 in week 1 which will be the planned order receipt in week 2.
Week 4:
The gross requirement is 40 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 40. The lead time is 1 week. Therefore, the planned order release will be 40 in week 3 which will be the planned order receipt in week 4.
Week 6:
The gross requirement is 10 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 10. The lead time is 1 week. Therefore, the planned order release will be 10 in week 5 which will be the planned order receipt in week 6.
Week 9:
The gross requirement is 25 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 25. The lead time is 1 week. Therefore, the planned order release will be 25 in week 8 which will be the planned order receipt in week 9. There is no ending inventory.
Week 10:
The gross requirement is 10 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 10. The lead time is 1 week. Therefore, the planned order release will be 10 in week 9 which will be the planned order receipt in week 10.
Week 12:
The gross requirement is 45 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 45. The lead time is 1 week. Therefore, the planned order release will be 45 in week 11 which will be the planned order receipt in week 12. There is no ending inventory.
Number of planned orders = 6
Inventory holding units= 0
Formula to calculate total cost of the plan:
Calculation of total cost:
The total cost is calculated by adding the product of number of planned order and setup cost with the product of inventory holding period and holding cost.
Hence, the cost for Lot for lot is $1,200.
b)
To determine: The ordering plan and cost for EOQ.
Introduction:
Economic order quantity (EOQ):
The economic order quantity is the number of units a firm must add to their stock while making each order. The notion of EOQ is to reduce the total cost of inventory of the firm.
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.
Answer to Problem 27P
The cost for EOQ is $2,370.
Explanation of Solution
Given information:
Period (weeks) | |||||||||||||
Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | Total |
Gross requirements | 35 | 40 | 10 | 25 | 10 | 45 | 165 |
Holding cost = $10 / week
Setup cost = $200
Lead time = 1 period
Stockout cost = $10 / week
Formula to calculate EOQ:
Calculation of EOQ:
The EOQ can be rounded off to 23 units.
Net requirements plan:
Period (weeks) | |||||||||||||
Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | Total |
Gross requirements | 35 | 40 | 10 | 25 | 10 | 45 | 165 | ||||||
Scheduled receipt | |||||||||||||
On hand (0) | 0 | 11 | 11 | 17 | 17 | 7 | 7 | 7 | 5 | 18 | 18 | ||
Ending inventory | 11 | 11 | 17 | 17 | 7 | 7 | 7 | 5 | 18 | 18 | 19 | 137 | |
Net requirement | 35 | 29 | 0 | 18 | 5 | 27 | |||||||
Planned order receipt | 46 | 46 | 0 | 23 | 23 | 46 | |||||||
Planned order release | 46 | 46 | 23 | 23 | 46 |
Week 2:
The gross requirement is 35 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 35. The lead time is 1 week. Therefore, the planned order release will be 46 (1 Lot = 23) in week 1 which will be the planned order receipt in week 2. The ending inventory is 11 which will be available at week 3.
Week 3:
The on hand inventory is 11. Since there is no requirement, the ending inventory at week 3 is 11 which will be available at week 4.
Week 4:
The gross requirement is 40 (1 assembly). The on hand inventory is 11. Hence, the net requirement is 29. The lead time is 1 week. Therefore, the planned order release will be 46 (1 Lot = 23) in week 3 which will be the planned order receipt in week 4. The ending inventory is 17 which will be available at week 5.
Week 5:
The on hand inventory is 17. Since there is no requirement, the ending inventory at week 5 is 17 which will be available at week 6.
Week 6:
The gross requirement is 10 (1 assembly). The on hand inventory is 17. Hence, the net requirement is 0. Therefore there will be no planned order assembly. The ending inventory is 7 which will be available at week 7.
Week 7:
The on hand inventory is 7. Since there is no requirement, the ending inventory at week 7 is 7 which will be available at week 8.
Week 8:
The on hand inventory is 7. Since there is no requirement, the ending inventory at week 8 is 7 which will be available at week 9.
Week 9:
The gross requirement is 25 (1 assembly). The on hand inventory is 7. Hence, the net requirement is 18. The lead time is 1 week. Therefore, the planned order release will be 23 (1 Lot = 23) in week 8 which will be the planned order receipt in week 9. The ending inventory is 5 which will be available at week 10.
Week 10:
The gross requirement is 10 (1 assembly). The on hand inventory is 5. Hence, the net requirement is 5. The lead time is 1 week. Therefore, the planned order release will be 23 (1 Lot = 23) in week 9 which will be the planned order receipt in week 10. The ending inventory is 18 which will be available at week 11.
Week 11:
The on hand inventory is 18. Since there is no requirement, the ending inventory at week 11 is 18 which will be available at week 12.
Week 12:
The gross requirement is 45 (1 assembly). The on hand inventory is 18. Hence, the net requirement is 27. The lead time is 1 week. Therefore, the planned order release will be 46 (1 Lot = 23) in week 11 which will be the planned order receipt in week 12. The ending inventory is 19 which will be available in the next week.
Number of planned order releases = 5
Total Ending inventory = 137
Calculation of total setup cost:
Calculation of total holding cost:
Calculation of total cost:
The total cost is calculated by summing the total setup cost and total holding cost.
Hence, the total cost for EOQ is $2,370
c)
To determine: The ordering plan and cost for POQ.
Introduction:
Periodic order quantity (POQ):
The POQ is the standard quantity of units that will be ordered over a fixed period of time. This method is followed when the usage of raw materials is consistent and is predictable.
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.
Answer to Problem 27P
The cost for POQ is $1,100.
Explanation of Solution
Given information:
Period (weeks) | |||||||||||||
Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | Total |
Gross requirements | 35 | 40 | 10 | 25 | 10 | 45 | 165 |
Holding cost = $10 / week
Setup cost = $200
Lead time = 1 period
Stockout cost = $10 / week
Net requirements plan:
The planned ordered release in the POQ plan is planned in a way such that the demand for next two periods is satisfied.
Net requirements plan:
Period (weeks) | |||||||||||||
Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | Total |
Gross requirements | 35 | 40 | 10 | 25 | 10 | 45 | 165 | ||||||
Scheduled receipt | |||||||||||||
On hand (0) | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 10 | 0 | 0 | ||
Ending inventory | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 10 | 0 | 0 | 0 | 10 | |
Net requirement | 35 | 40 | 10 | 25 | 45 | ||||||||
Planned order receipt | 35 | 40 | 10 | 35 | 45 | ||||||||
Planned order release | 35 | 40 | 10 | 35 | 45 |
Week 2:
The gross requirement is 35 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 35. The lead time is 1 week. Therefore, the planned order release will be 35 in week 1 which will be the planned order receipt in week 2. There is no ending inventory.
Week 4:
The gross requirement is 40 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 40. The lead time is 1 week. Therefore, the planned order release will be 40 in week 3 which will be the planned order receipt in week 4. There is no ending inventory.
Week 6:
The gross requirement is 10 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 10. Therefore, the planned order release will be 10 in week 5 which will be the planned order receipt in week 6. There is no ending inventory.
Week 9:
The gross requirement is 25 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 25. The lead time is 1 week. Therefore, the planned order release will be 35 in week 8 which will be the planned order receipt in week 9. The ending inventory is 10 which will be available at week 10.
Week 10:
The gross requirement is 10 (1 assembly). The on hand inventory is 10. Hence, the net requirement is 0. Therefore there will be no planned order inventory.
Week 12:
The gross requirement is 45 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 45. The lead time is 1 week. Therefore, the planned order release will be 45 in week 11 which will be the planned order receipt in week 12. There is no ending inventory.
Number of planned orders = 5
Inventory holding units= 10
Formula to calculate total cost of the plan:
Calculation of total cost:
The total cost is calculated by adding the product of number of planned order and setup cost with the product of inventory holding period and holding cost.
Hence, the cost for POQ is $1,100.
d)
To determine: The plan which has the lowest cost.
Answer to Problem 27P
The plan which has the lowest cost is POQ.
Explanation of Solution
The total cost for Lot for lot is $1,200. The total cost for EOQ is $2,370. The total cost for POQ is $1,100. The total cost is less for POQ when compared with EOQ and Lot for lot. ($1,100 < $2,370, $1,200)
Hence, the plan which has the lowest cost is POQ.
Want to see more full solutions like this?
Chapter 14 Solutions
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
- Help me with this practice problem. Please provide pictures of you doing the problem so I can better understand how to complete it. Please show equations and be clear. Thank you so much,arrow_forwardAssume you are the manager of a shop that assembles power tools. You have just received an order for 55 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws follows: Item Lead Time (weeks) On Hand Saw A B C D E F 2 1 2 2 1 1 2 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipt Planned order release Ĉ E(3) & E(2) LT = 1 week Lot size: Lot-for-Lot 15 10 5 65 20 10 30 Skip Extension Tip: Double click to open in new tab Show Transcribed Text Develop the material requirements plan for component E using lot-for-lot ordering for all items. (Leave no cells blank - be certain to enter "0" wherever required.) Components A(2), B(1), C(4) E(3), D(1) D (2), F(3) E(2), D (2) Beg. Inv. 1 2 3 190 5 210 6arrow_forwardCan you assist me with Problem 5arrow_forward
- please solve the question.arrow_forwardGrace Greenberg, production planner for Science and Technology Labs, in New Jersey, has the master production plan shown here: Lead time= I period; setup costs = $200; holding cost = $10 perweek; stockout cost = $10 per week. Develop an ordering planand costs for Grace, using these techniques:a) Lot-for-lot. b) EOQ.c) POQ. d) Which plan has the lowest cost?arrow_forwardPlease do not give solution in image format thankuarrow_forward
- Describe the link between inventory levels and production schedule?arrow_forwardThe following information is given for a particular part. Using a lead time of two weeks, complete the table. Use L4L with On hand = 80 and SS=0.arrow_forwardDetermine the lot sizing technique that has the minimum cost given thefollowing gross requirements for 6 weeks. There are 10 units on hand, ordering cost isPhp150.00 per order, and inventory cost is Php5.00 per unit per week. Need answer asap. Please include the solution/computation. Thank youarrow_forward
- Explain the economic order quantity (EOQ) and its impact on cost of operations.arrow_forwardComplete the MPS record below for an end item. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Order Policy: 100 units Lead Time: 2 weeks Quantity on Hand: 80 Week 1 2 3 4 5 6 7 8 9 10 Forecast 25 25 35 45 25 20 45 55 Customer orders 25 30 7 11 (booked) Projected on-hand inventory MPS quantityarrow_forwardPlease do not give solution in image format thankuarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.