Concept explainers
a)
To determine: The change in the items due to the change in the lead time of item G.
Introduction:
Net requirements plan:
The Net requirements plan is the plan which is established on the Gross requirements plan formed by deducting the stock on and the
a)

Answer to Problem 16P
The change will take place only with item G because it has no children. The Lead time of 4 weeks will preempt the Planned order release by 1 one week.
Explanation of Solution
Given information:
- 10 units for service and production department for B and F.
- 10 units of A at week 8.
- Lead time of G has been changed to 4 weeks.
Part | A | B | C | D | E | F | G | H |
On hand | 0 | 2 | 10 | 5 | 4 | 5 | 1 | 10 |
Product structure:
Net requirements plan:
Item A:
Week | ||||||||
Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | |||||||
Scheduled receipt | ||||||||
On-hand (0) | 0 | |||||||
Net requirement | 10 | |||||||
Planned order receipt | 10 | |||||||
Planned order release | 10 |
Week 8:
The gross requirement is 10 (1 assembly). The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 7 which will be the Planned order receipt in week 8.
Item B:
Week | ||||||||
Item B | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (2) | 2 | 0 | ||||||
Net requirement | 8 | 10 | ||||||
Planned order receipt | 8 | 10 | ||||||
Planned order release | 8 | 10 |
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 2. Hence, the Net requirement is 8. The lead time is 1 week. Therefore, the planned order release will be 8 in week 5 which will be the planned order receipt in week 6.
Week 7:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the planned order release will be 10 in week 6 which will be the planned order receipt in week 7.
Item F:
Week | ||||||||
Item F | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (5) | 5 | 0 | ||||||
Net requirement | 5 | 10 | ||||||
Planned order receipt | 5 | 10 | ||||||
Planned order release | 5 | 10 |
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.
Week 7:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 6 which will be the Planned order receipt in week 7.
Item D:
Week | ||||||||
Item D | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 8 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (5) | 5 | 0 | ||||||
Net requirement | 3 | 10 | ||||||
Planned order receipt | 3 | 10 | ||||||
Planned order release | 3 | 10 |
Week 5:
The gross requirement is 8 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 5. Hence, the Net requirement is 3. The lead time is 1 week. Therefore, the Planned order release will be 3 in week 4 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 5 which will be the Planned order receipt in week 6.
Item G (Lead Time = 3):
Week | ||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (1) | 1 | 0 | ||||||
Net requirement | 4 | 10 | ||||||
Planned order receipt | 4 | 10 | ||||||
Planned order release | 4 | 10 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 3 weeks. Therefore, the Planned order release will be 4 in week 2 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 3 weeks. Therefore, the Planned order release will be 10 in week 3 which will be the Planned order receipt in week 6.
Item G (Lead Time = 4):
Week | ||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (1) | 1 | 0 | ||||||
Net requirement | 4 | 10 | ||||||
Planned order receipt | 4 | 10 | ||||||
Planned order release | 4 | 10 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 4 weeks. Therefore, the Planned order release will be 4 in week 1 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 4 weeks. Therefore, the Planned order release will be 10 in week 2 which will be the Planned order receipt in week 6.
Item H:
Week | ||||||||
Item H | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (10) | 10 | 5 | ||||||
Net requirement | 5 | |||||||
Planned order receipt | 5 | |||||||
Planned order release | 5 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 10. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 6.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.
Item C:
Week | ||||||||
Item C | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 13 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (10) | 10 | 0 | ||||||
Net requirement | 3 | 10 | ||||||
Planned order receipt | 3 | 10 | ||||||
Planned order release | 3 | 10 |
Week 5:
The gross requirement is 13 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 10. Hence, the Net requirement is 3. The lead time is 2 weeks. Therefore, the Planned order release will be 3 in week 3 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 2 weeks. Therefore, the Planned order release will be 10 in week 4 which will be the Planned order receipt in week 6.
Item E:
Week | ||||||||
Item E | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 3 | 15 | ||||||
Scheduled receipt | ||||||||
On-hand (4) | 4 | 1 | ||||||
Net requirement | 14 | |||||||
Planned order receipt | 14 | |||||||
Planned order release | 14 |
Week 4:
The gross requirement is 3 (1 assembly) derived from the Planned order release of D. The on-hand inventory is 4. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 5.
Week 5:
The gross requirement is 15 (1 assembly) derived from the Planned order release of H. The on-hand inventory is 1. Hence, the Net requirement is 14. The lead time is 1 week. Therefore, the Planned order release will be 14 in week 4 which will be the Planned order receipt in week 5.
Hence, the change will take place only with item G because it has no children. The Lead time of 4 weeks will preempt the Planned order release by 1 one week.
b)
To determine: The implications of the production plan because of change in the lead time of item G.
Introduction:
Net requirements plan:
The Net requirements plan is the plan which is established on the Gross requirements plan formed by deducting the stock on and the Scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.
b)

Answer to Problem 16P
The production plan will be altered such that item F and four units of A will be delayed by 1 week.
Explanation of Solution
Given information:
- 10 units for service and production department for B and F.
- 10 units of A at week 8.
- Lead time of G has been changed to 4 weeks.
Part | A | B | C | D | E | F | G | H |
On Hand | 0 | 2 | 10 | 5 | 4 | 5 | 1 | 10 |
Product structure:
Net requirements plan:
Item A:
Week | ||||||||
Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | |||||||
Scheduled receipt | ||||||||
On-hand (0) | 0 | |||||||
Net requirement | 10 | |||||||
Planned order receipt | 10 | |||||||
Planned order release | 10 |
Week 8:
The gross requirement is 10 (1 assembly). The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 7 which will be the Planned order receipt in week 8.
Item B:
Week | ||||||||
Item B | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (2) | 2 | 0 | ||||||
Net requirement | 8 | 10 | ||||||
Planned order receipt | 8 | 10 | ||||||
Planned order release | 8 | 10 |
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 2. Hence, the Net requirement is 8. The lead time is 1 week. Therefore, the Planned order release will be 8 in week 5 which will be the Planned order receipt in week 6.
Week 7:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 6 which will be the Planned order receipt in week 7.
Item F:
Week | ||||||||
Item F | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (5) | 5 | 0 | ||||||
Net requirement | 5 | 10 | ||||||
Planned order receipt | 5 | 10 | ||||||
Planned order release | 5 | 10 |
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.
Week 7:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 6 which will be the Planned order receipt in week 7.
Item D:
Week | ||||||||
Item D | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 8 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (5) | 5 | 0 | ||||||
Net requirement | 3 | 10 | ||||||
Planned order receipt | 3 | 10 | ||||||
Planned order release | 3 | 10 |
Week 5:
The gross requirement is 8 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 5. Hence, the Net requirement is 3. The lead time is 1 week. Therefore, the Planned order release will be 3 in week 4 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 5 which will be the Planned order receipt in week 6.
Item G (Lead Time = 3):
Week | ||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (1) | 1 | 0 | ||||||
Net requirement | 4 | 10 | ||||||
Planned order receipt | 4 | 10 | ||||||
Planned order release | 4 | 10 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 3 weeks. Therefore, the Planned order release will be 4 in week 2 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 3 weeks. Therefore, the Planned order release will be 10 in week 3 which will be the Planned order receipt in week 6.
Item G (Lead Time = 4):
Week | ||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (1) | 1 | 0 | ||||||
Net requirement | 4 | 10 | ||||||
Planned order receipt | 4 | 10 | ||||||
Planned order release | 4 | 10 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 4 weeks. Therefore, the Planned order release will be 4 in week 1 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 4 weeks. Therefore, the Planned order release will be 10 in week 2 which will be the Planned order receipt in week 6.
Item H:
Week | ||||||||
Item H | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (10) | 10 | 5 | ||||||
Net requirement | 5 | |||||||
Planned order receipt | 5 | |||||||
Planned order release | 5 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 10. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 6.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.
Item C:
Week | ||||||||
Item C | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 13 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (10) | 10 | 0 | ||||||
Net requirement | 3 | 10 | ||||||
Planned order receipt | 3 | 10 | ||||||
Planned order release | 3 | 10 |
Week 5:
The gross requirement is 13 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 10. Hence, the Net requirement is 3. The lead time is 2 weeks. Therefore, the Planned order release will be 3 in week 3 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 2 weeks. Therefore, the Planned order release will be 10 in week 4 which will be the Planned order receipt in week 6.
Item E:
Week | ||||||||
Item E | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 3 | 15 | ||||||
Scheduled receipt | ||||||||
On-hand (4) | 4 | 1 | ||||||
Net requirement | 14 | |||||||
Planned order receipt | 14 | |||||||
Planned order release | 14 |
Week 4:
The gross requirement is 3 (1 assembly) derived from the Planned order release of D. The on-hand inventory is 4. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 5.
Week 5:
The gross requirement is 15 (1 assembly) derived from the Planned order release of H. The on-hand inventory is 1. Hence, the Net requirement is 14. The lead time is 1 week. Therefore, the Planned order release will be 14 in week 4 which will be the Planned order receipt in week 5.
If this week is week 1 of the production plan, the increase in the lead time will make that only 1 assembly of G will be available for F in week 5. Hence, item F and consequently 4 units of item A will be delayed by a time of 1 week.
c)
To determine: The options the
c)

Explanation of Solution
Options the production manager has to manage these changes:
The production manager can do the following. They are:
- The production manager can inform the customer in advance that the 4 units will be delayed by a time of 1 week.
- The production manager can ask the supplier of item G to expedite the production or the delivery.
- The production manager can reduce the time take for production of item F or A.
Want to see more full solutions like this?
Chapter 14 Solutions
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
- Negotiators can gain several benefits from using the strategy of multiple equivalent simultaneous offers. By offering multiple options it reduces the chance of rejection. It also improves the chances of reaching reaching an agreement. By presenting multiple offers, it shows you are flexible. disagree with this post or add on to the postarrow_forwardThe strategy of Multiple Equivalent Simultaneous Offers involves presenting several equally valuable options to the other party during negotiations. This approach benefits negotiators by creating flexibility and increasing the chances of finding a mutually agreeable solution. By offering multiple options, negotiators show that they are open to compromise, which can build trust and make the negotiation process smoother. It also helps avoid getting stuck on one issue, as the other party can choose from several alternatives that meet their needs. In my experience, using MESOs in a work negotiation helped both parties reach an agreement more quickly because each option was carefully thought out to address different needs, and this made it easier for us to settle on one that worked for both sides. This strategy can also reveal what is most important to the other party, helping negotiators understand their priorities better. agree or disagree with the postarrow_forwardExamine the conflicts between improving customer service levels and controlling costs in sales. Strategies to Balance Both customer service levels and controlling costs in sales 1.Outsourcing and workforce optimization 2. AI-driven customer supportarrow_forward
- how can you gain trust in a negotiation setting?arrow_forward✓ Custom $€ .0 .on File Home Insert Share Page Layout Formulas Data Review View Help Draw Arial 10 B B14 ✓ X✓ fx 1400 > 甘く 曲 > 冠 > Comments Editing ✓ . . . P Q R S T 3 A Production cost ($/unit) B с D E F G H J K L M N $74.00 4 Inventory holding cost ($/unit) $1.50 5 Lost sales cost ($/unit) $82.00 6 Overtime cost ($/unit) $6.80 7 Undertime cost ($/unit) $3.20 8 Rate change cost ($/unit) $5.00 9 Normal production rate (units) 2,000 10 Ending inventory (previous Dec.) 800 11 Cumulative 12 13 Month Demand Cumulative Demand Product Production Availability Ending Inventory Lost Cumulative Cumulative Product Sales 14 January 1,400 1,475 15 FUERANZ222222223323333BRUINE 14 February 1,000 2,275 Month January February Demand Demand Production Availability Ending Inventory Lost Sales 1,400 #N/A 1,475 #N/A #N/A #N/A 1,000 #N/A 2,275 #N/A #N/A #N/A 16 March 1,800 2,275 March 1,800 #N/A 2,275 #N/A #N/A #N/A 17 April 2,700 2,275 April 2,700 #N/A 2,275 #N/A #N/A #N/A 18 May 3,000 2,275 May 3,000 #N/A…arrow_forwardFollow guidelines and summarize in a paragrapharrow_forward
- MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningContemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage Learning
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,


