Concept explainers
a)
To determine: The change in the items due to the change in the lead time of item G.
Introduction:
Net requirements plan:
The Net requirements plan is the plan which is established on the Gross requirements plan formed by deducting the stock on and the
a)
Answer to Problem 16P
The change will take place only with item G because it has no children. The Lead time of 4 weeks will preempt the Planned order release by 1 one week.
Explanation of Solution
Given information:
- 10 units for service and production department for B and F.
- 10 units of A at week 8.
- Lead time of G has been changed to 4 weeks.
Part | A | B | C | D | E | F | G | H |
On hand | 0 | 2 | 10 | 5 | 4 | 5 | 1 | 10 |
Product structure:
Net requirements plan:
Item A:
Week | ||||||||
Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | |||||||
Scheduled receipt | ||||||||
On-hand (0) | 0 | |||||||
Net requirement | 10 | |||||||
Planned order receipt | 10 | |||||||
Planned order release | 10 |
Week 8:
The gross requirement is 10 (1 assembly). The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 7 which will be the Planned order receipt in week 8.
Item B:
Week | ||||||||
Item B | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (2) | 2 | 0 | ||||||
Net requirement | 8 | 10 | ||||||
Planned order receipt | 8 | 10 | ||||||
Planned order release | 8 | 10 |
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 2. Hence, the Net requirement is 8. The lead time is 1 week. Therefore, the planned order release will be 8 in week 5 which will be the planned order receipt in week 6.
Week 7:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the planned order release will be 10 in week 6 which will be the planned order receipt in week 7.
Item F:
Week | ||||||||
Item F | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (5) | 5 | 0 | ||||||
Net requirement | 5 | 10 | ||||||
Planned order receipt | 5 | 10 | ||||||
Planned order release | 5 | 10 |
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.
Week 7:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 6 which will be the Planned order receipt in week 7.
Item D:
Week | ||||||||
Item D | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 8 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (5) | 5 | 0 | ||||||
Net requirement | 3 | 10 | ||||||
Planned order receipt | 3 | 10 | ||||||
Planned order release | 3 | 10 |
Week 5:
The gross requirement is 8 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 5. Hence, the Net requirement is 3. The lead time is 1 week. Therefore, the Planned order release will be 3 in week 4 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 5 which will be the Planned order receipt in week 6.
Item G (Lead Time = 3):
Week | ||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (1) | 1 | 0 | ||||||
Net requirement | 4 | 10 | ||||||
Planned order receipt | 4 | 10 | ||||||
Planned order release | 4 | 10 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 3 weeks. Therefore, the Planned order release will be 4 in week 2 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 3 weeks. Therefore, the Planned order release will be 10 in week 3 which will be the Planned order receipt in week 6.
Item G (Lead Time = 4):
Week | ||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (1) | 1 | 0 | ||||||
Net requirement | 4 | 10 | ||||||
Planned order receipt | 4 | 10 | ||||||
Planned order release | 4 | 10 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 4 weeks. Therefore, the Planned order release will be 4 in week 1 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 4 weeks. Therefore, the Planned order release will be 10 in week 2 which will be the Planned order receipt in week 6.
Item H:
Week | ||||||||
Item H | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (10) | 10 | 5 | ||||||
Net requirement | 5 | |||||||
Planned order receipt | 5 | |||||||
Planned order release | 5 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 10. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 6.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.
Item C:
Week | ||||||||
Item C | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 13 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (10) | 10 | 0 | ||||||
Net requirement | 3 | 10 | ||||||
Planned order receipt | 3 | 10 | ||||||
Planned order release | 3 | 10 |
Week 5:
The gross requirement is 13 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 10. Hence, the Net requirement is 3. The lead time is 2 weeks. Therefore, the Planned order release will be 3 in week 3 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 2 weeks. Therefore, the Planned order release will be 10 in week 4 which will be the Planned order receipt in week 6.
Item E:
Week | ||||||||
Item E | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 3 | 15 | ||||||
Scheduled receipt | ||||||||
On-hand (4) | 4 | 1 | ||||||
Net requirement | 14 | |||||||
Planned order receipt | 14 | |||||||
Planned order release | 14 |
Week 4:
The gross requirement is 3 (1 assembly) derived from the Planned order release of D. The on-hand inventory is 4. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 5.
Week 5:
The gross requirement is 15 (1 assembly) derived from the Planned order release of H. The on-hand inventory is 1. Hence, the Net requirement is 14. The lead time is 1 week. Therefore, the Planned order release will be 14 in week 4 which will be the Planned order receipt in week 5.
Hence, the change will take place only with item G because it has no children. The Lead time of 4 weeks will preempt the Planned order release by 1 one week.
b)
To determine: The implications of the production plan because of change in the lead time of item G.
Introduction:
Net requirements plan:
The Net requirements plan is the plan which is established on the Gross requirements plan formed by deducting the stock on and the Scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.
b)
Answer to Problem 16P
The production plan will be altered such that item F and four units of A will be delayed by 1 week.
Explanation of Solution
Given information:
- 10 units for service and production department for B and F.
- 10 units of A at week 8.
- Lead time of G has been changed to 4 weeks.
Part | A | B | C | D | E | F | G | H |
On Hand | 0 | 2 | 10 | 5 | 4 | 5 | 1 | 10 |
Product structure:
Net requirements plan:
Item A:
Week | ||||||||
Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | |||||||
Scheduled receipt | ||||||||
On-hand (0) | 0 | |||||||
Net requirement | 10 | |||||||
Planned order receipt | 10 | |||||||
Planned order release | 10 |
Week 8:
The gross requirement is 10 (1 assembly). The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 7 which will be the Planned order receipt in week 8.
Item B:
Week | ||||||||
Item B | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (2) | 2 | 0 | ||||||
Net requirement | 8 | 10 | ||||||
Planned order receipt | 8 | 10 | ||||||
Planned order release | 8 | 10 |
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 2. Hence, the Net requirement is 8. The lead time is 1 week. Therefore, the Planned order release will be 8 in week 5 which will be the Planned order receipt in week 6.
Week 7:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 6 which will be the Planned order receipt in week 7.
Item F:
Week | ||||||||
Item F | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (5) | 5 | 0 | ||||||
Net requirement | 5 | 10 | ||||||
Planned order receipt | 5 | 10 | ||||||
Planned order release | 5 | 10 |
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.
Week 7:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 6 which will be the Planned order receipt in week 7.
Item D:
Week | ||||||||
Item D | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 8 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (5) | 5 | 0 | ||||||
Net requirement | 3 | 10 | ||||||
Planned order receipt | 3 | 10 | ||||||
Planned order release | 3 | 10 |
Week 5:
The gross requirement is 8 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 5. Hence, the Net requirement is 3. The lead time is 1 week. Therefore, the Planned order release will be 3 in week 4 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 5 which will be the Planned order receipt in week 6.
Item G (Lead Time = 3):
Week | ||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (1) | 1 | 0 | ||||||
Net requirement | 4 | 10 | ||||||
Planned order receipt | 4 | 10 | ||||||
Planned order release | 4 | 10 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 3 weeks. Therefore, the Planned order release will be 4 in week 2 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 3 weeks. Therefore, the Planned order release will be 10 in week 3 which will be the Planned order receipt in week 6.
Item G (Lead Time = 4):
Week | ||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (1) | 1 | 0 | ||||||
Net requirement | 4 | 10 | ||||||
Planned order receipt | 4 | 10 | ||||||
Planned order release | 4 | 10 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 4 weeks. Therefore, the Planned order release will be 4 in week 1 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 4 weeks. Therefore, the Planned order release will be 10 in week 2 which will be the Planned order receipt in week 6.
Item H:
Week | ||||||||
Item H | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (10) | 10 | 5 | ||||||
Net requirement | 5 | |||||||
Planned order receipt | 5 | |||||||
Planned order release | 5 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 10. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 6.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.
Item C:
Week | ||||||||
Item C | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 13 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (10) | 10 | 0 | ||||||
Net requirement | 3 | 10 | ||||||
Planned order receipt | 3 | 10 | ||||||
Planned order release | 3 | 10 |
Week 5:
The gross requirement is 13 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 10. Hence, the Net requirement is 3. The lead time is 2 weeks. Therefore, the Planned order release will be 3 in week 3 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 2 weeks. Therefore, the Planned order release will be 10 in week 4 which will be the Planned order receipt in week 6.
Item E:
Week | ||||||||
Item E | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 3 | 15 | ||||||
Scheduled receipt | ||||||||
On-hand (4) | 4 | 1 | ||||||
Net requirement | 14 | |||||||
Planned order receipt | 14 | |||||||
Planned order release | 14 |
Week 4:
The gross requirement is 3 (1 assembly) derived from the Planned order release of D. The on-hand inventory is 4. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 5.
Week 5:
The gross requirement is 15 (1 assembly) derived from the Planned order release of H. The on-hand inventory is 1. Hence, the Net requirement is 14. The lead time is 1 week. Therefore, the Planned order release will be 14 in week 4 which will be the Planned order receipt in week 5.
If this week is week 1 of the production plan, the increase in the lead time will make that only 1 assembly of G will be available for F in week 5. Hence, item F and consequently 4 units of item A will be delayed by a time of 1 week.
c)
To determine: The options the
c)
Explanation of Solution
Options the production manager has to manage these changes:
The production manager can do the following. They are:
- The production manager can inform the customer in advance that the 4 units will be delayed by a time of 1 week.
- The production manager can ask the supplier of item G to expedite the production or the delivery.
- The production manager can reduce the time take for production of item F or A.
Want to see more full solutions like this?
Chapter 14 Solutions
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
- The Betterbilt Construction Company designs and builds residential mobile homes. Thecompany is ready to construct, in sequence, 16 new homes of 2,400 square feet each. Thesuccessful bid for the construction materials in the first home is $64,800, or $27 per square foot.The purchasing manager believes that several actions can be taken to reduce material costs by8% each time the number of homes constructed doubles. Based on this information,a. What is the estimated cumulative average material cost per square foot for the first fivehomes?b. What is the estimated material cost per square foot for the last (16th) home?arrow_forwardRefer to this product tree If 17 Ps are needed, and no on-hand inventory exists for any items, how many Cs will be needed?arrow_forwarduestions wi1ps06h.ch06.11 The bill of materials for product A with the associated component parts and planning factors (in parenthesis) are showed below. C (1) B (2) Icon Key D (1) D (3) A C (6) E (4) F (2) D (1) G (4) How many units of the component parts are required to make one unit of the product A? Round your answers to the nearest whole number. Component B: unit(s) Component C: unit(s) Component D: unit(s) Component E: unit(s) Component F: unit(s) Component G: unit(s)arrow_forward
- As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 1 clamp and 1 housing. Each clamp has 1 handle and 2 castings. Each housing has 1 bearing and 2 shafts. There is no inventory on hand. Part 2 a) Design a product structure noting the quantities for each item and show the low-level coding. Match each number in the structure below with the corresponding item. Number Item I Spring Subscript left parenthesis 2 right parenthesisSpring(2) II Housing Subscript left parenthesis 1 right parenthesisHousing(1) III Casting Subscript left parenthesis 2 right parenthesisCasting(2) IV Shaft Subscript left parenthesis 2 right parenthesisShaft(2) Bracket Base(1) Clamp(1) Handle(1) Clamp(4) Bearing(1) Handle(1) Casting(2) IIIIIIIV Part 3 b) Determine the…arrow_forwardDraw an approximate bill-of-materials (BOM) for a kid’s toy of your choice following these requirements: I would like to use the Jollibee plush Bee toy. (a) clearly label the end item and each component, (b) the BOM must contain no more than 20 items, (c) the BOM must contain at least three levels (you may count the end-item level zero).arrow_forwardGiven the preceding information, what are Jerry’s options? How should they be evaluated? Make assumptions where necessary.arrow_forward
- 1. Give examples of industries in which demand forecasting is dependent in the demand for other products. 2. What are the three specific ways in which a computer-aided design (CAD) benefits the design engineer? 3. Pick a product that you are familiar with and produce a Bill of Materials (BOM).arrow_forwardAn electric hand drill would take 15, 40, 10, 20, 50, and 30 units in the next 6 weeks. The marketing department has booked orders for the first, second, third, and fourth weeks for 20, 25, 10 and 20 units in all. Currently, there are 30 hand boxes in order. The strategy should be ordered in several 60 units. One week is lead period. Lead time. A. Develop the MPS hand drill log. b. A hand drill dealer puts an order for 15 units. What is the correct date of shipment for the whole order?arrow_forwardIn which product life cycle the scope, schedule, and cost are determined early, and changes to scope are carefully managed? 1) Iterative 2) Incremental 3) Predictive 4) Adaptivearrow_forward
- Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forwardDraw a simple bill-of-materials (BOM) for a smart phone given the following requirements: (a) clearly label the end item and each component, (b) the BOM must contain no more than ten items, (c) the BOM must contain at least three levels (you may count the end-item level zero).arrow_forwardComplete the following table. Lead time for the part is 2 weeks, and the order quantity is 50. What action should be taken?arrow_forward