PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
11th Edition
ISBN: 9780135226742
Author: HEIZER
Publisher: PEARSON
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 14, Problem 16P

a)

Summary Introduction

To determine: The change in the items due to the change in the lead time of item G.

Introduction:

Net requirements plan:

The Net requirements plan is the plan which is established on the Gross requirements plan formed by deducting the stock on and the Scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.

a)

Expert Solution
Check Mark

Answer to Problem 16P

The change will take place only with item G because it has no children. The Lead time of 4 weeks will preempt the Planned order release by 1 one week.

Explanation of Solution

Given information:

  • 10 units for service and production department for B and F.
  • 10 units of A at week 8.
  • Lead time of G has been changed to 4 weeks.
Part A B C D E F G H
On hand 0 2 10 5 4 5 1 10

Product structure:

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 14, Problem 16P , additional homework tip  1

Net requirements plan:

Item A:

Week
Item A 1 2 3 4 5 6 7 8
Gross requirements 10
Scheduled receipt
On-hand (0) 0
Net requirement 10
Planned order receipt 10
Planned order release 10

Week 8:

The gross requirement is 10 (1 assembly). The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 7 which will be the Planned order receipt in week 8.

Item B:

Week
Item B 1 2 3 4 5 6 7 8
Gross requirements 10 10
Scheduled receipt
On-hand (2) 2 0
Net requirement 8 10
Planned order receipt 8 10
Planned order release 8 10

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 2. Hence, the Net requirement is 8. The lead time is 1 week. Therefore, the planned order release will be 8 in week 5 which will be the planned order receipt in week 6.

Week 7:

The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the planned order release will be 10 in week 6 which will be the planned order receipt in week 7.

Item F:

Week
Item F 1 2 3 4 5 6 7 8
Gross requirements 10 10
Scheduled receipt
On-hand (5) 5 0
Net requirement 5 10
Planned order receipt 5 10
Planned order release 5 10

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.

Week 7:

The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 6 which will be the Planned order receipt in week 7.

Item D:

Week
Item D 1 2 3 4 5 6 7 8
Gross requirements 8 10
Scheduled receipt
On-hand (5) 5 0
Net requirement 3 10
Planned order receipt 3 10
Planned order release 3 10

Week 5:

The gross requirement is 8 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 5. Hence, the Net requirement is 3. The lead time is 1 week. Therefore, the Planned order release will be 3 in week 4 which will be the Planned order receipt in week 5.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 5 which will be the Planned order receipt in week 6.

Item G (Lead Time = 3):

Week
Item G 1 2 3 4 5 6 7 8
Gross requirements 5 10
Scheduled receipt
On-hand (1) 1 0
Net requirement 4 10
Planned order receipt 4 10
Planned order release 4  10

Week 5:

The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 3 weeks. Therefore, the Planned order release will be 4 in week 2 which will be the Planned order receipt in week 5.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 3 weeks. Therefore, the Planned order release will be 10 in week 3 which will be the Planned order receipt in week 6.

Item G (Lead Time = 4):

Week
Item G 1 2 3 4 5 6 7 8
Gross requirements 5 10
Scheduled receipt
On-hand (1) 1 0
Net requirement 4 10
Planned order receipt 4 10
Planned order release 4 10

Week 5:

The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 4 weeks. Therefore, the Planned order release will be 4 in week 1 which will be the Planned order receipt in week 5.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 4 weeks. Therefore, the Planned order release will be 10 in week 2 which will be the Planned order receipt in week 6.

Item H:

Week
Item H 1 2 3 4 5 6 7 8
Gross requirements 5 10
Scheduled receipt
On-hand (10) 10 5
Net requirement 5
Planned order receipt 5
Planned order release 5

Week 5:

The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 10. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 6.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.

Item C:

Week
Item C 1 2 3 4 5 6 7 8
Gross requirements 13 10
Scheduled receipt
On-hand (10) 10 0
Net requirement 3 10
Planned order receipt 3 10
Planned order release 3 10

Week 5:

The gross requirement is 13 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 10. Hence, the Net requirement is 3. The lead time is 2 weeks. Therefore, the Planned order release will be 3 in week 3 which will be the Planned order receipt in week 5.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 2 weeks. Therefore, the Planned order release will be 10 in week 4 which will be the Planned order receipt in week 6.

 Item E:

Week
Item E 1 2 3 4 5 6 7 8
Gross requirements 3 15
Scheduled receipt
On-hand (4) 4 1
Net requirement 14
Planned order receipt 14
Planned order release 14

Week 4:

The gross requirement is 3 (1 assembly) derived from the Planned order release of D. The on-hand inventory is 4. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 5.

Week 5:

The gross requirement is 15 (1 assembly) derived from the Planned order release of H. The on-hand inventory is 1. Hence, the Net requirement is 14. The lead time is 1 week. Therefore, the Planned order release will be 14 in week 4 which will be the Planned order receipt in week 5.

Hence, the change will take place only with item G because it has no children. The Lead time of 4 weeks will preempt the Planned order release by 1 one week.

b)

Summary Introduction

To determine: The implications of the production plan because of change in the lead time of item G.

Introduction:

Net requirements plan:

The Net requirements plan is the plan which is established on the Gross requirements plan formed by deducting the stock on and the Scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.

b)

Expert Solution
Check Mark

Answer to Problem 16P

The production plan will be altered such that item F and four units of A will be delayed by 1 week.

Explanation of Solution

Given information:

  • 10 units for service and production department for B and F.
  • 10 units of A at week 8.
  • Lead time of G has been changed to 4 weeks.
Part A B C D E F G H
On Hand 0 2 10 5 4 5 1 10

Product structure:

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 14, Problem 16P , additional homework tip  2

Net requirements plan:

Item A:

Week
Item A 1 2 3 4 5 6 7 8
Gross requirements 10
Scheduled receipt
On-hand (0) 0
Net requirement 10
Planned order receipt 10
Planned order release 10

Week 8:

The gross requirement is 10 (1 assembly). The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 7 which will be the Planned order receipt in week 8.

Item B:

Week
Item B 1 2 3 4 5 6 7 8
Gross requirements 10 10
Scheduled receipt
On-hand (2) 2 0
Net requirement 8 10
Planned order receipt 8 10
Planned order release 8 10

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 2. Hence, the Net requirement is 8. The lead time is 1 week. Therefore, the Planned order release will be 8 in week 5 which will be the Planned order receipt in week 6.

Week 7:

The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 6 which will be the Planned order receipt in week 7.

Item F:

Week
Item F 1 2 3 4 5 6 7 8
Gross requirements 10 10
Scheduled receipt
On-hand (5) 5 0
Net requirement 5 10
Planned order receipt 5 10
Planned order release 5 10

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.

Week 7:

The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 6 which will be the Planned order receipt in week 7.

Item D:

Week
Item D 1 2 3 4 5 6 7 8
Gross requirements 8 10
Scheduled receipt
On-hand (5) 5 0
Net requirement 3 10
Planned order receipt 3 10
Planned order release 3 10

Week 5:

The gross requirement is 8 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 5. Hence, the Net requirement is 3. The lead time is 1 week. Therefore, the Planned order release will be 3 in week 4 which will be the Planned order receipt in week 5.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 5 which will be the Planned order receipt in week 6.

Item G (Lead Time = 3):

Week
Item G 1 2 3 4 5 6 7 8
Gross requirements 5 10
Scheduled receipt
On-hand (1) 1 0
Net requirement 4 10
Planned order receipt 4 10
Planned order release 4  10

Week 5:

The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 3 weeks. Therefore, the Planned order release will be 4 in week 2 which will be the Planned order receipt in week 5.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 3 weeks. Therefore, the Planned order release will be 10 in week 3 which will be the Planned order receipt in week 6.

Item G (Lead Time = 4):

Week
Item G 1 2 3 4 5 6 7 8
Gross requirements 5 10
Scheduled receipt
On-hand (1) 1 0
Net requirement 4 10
Planned order receipt 4 10
Planned order release 4 10

Week 5:

The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 4 weeks. Therefore, the Planned order release will be 4 in week 1 which will be the Planned order receipt in week 5.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 4 weeks. Therefore, the Planned order release will be 10 in week 2 which will be the Planned order receipt in week 6.

Item H:

Week
Item H 1 2 3 4 5 6 7 8
Gross requirements 5 10
Scheduled receipt
On-hand (10) 10 5
Net requirement 5
Planned order receipt 5
Planned order release 5

Week 5:

The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 10. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 6.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.

Item C:

Week
Item C 1 2 3 4 5 6 7 8
Gross requirements 13 10
Scheduled receipt
On-hand (10) 10 0
Net requirement 3 10
Planned order receipt 3 10
Planned order release 3 10

Week 5:

The gross requirement is 13 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 10. Hence, the Net requirement is 3. The lead time is 2 weeks. Therefore, the Planned order release will be 3 in week 3 which will be the Planned order receipt in week 5.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 2 weeks. Therefore, the Planned order release will be 10 in week 4 which will be the Planned order receipt in week 6.

 Item E:

Week
Item E 1 2 3 4 5 6 7 8
Gross requirements 3 15
Scheduled receipt
On-hand (4) 4 1
Net requirement 14
Planned order receipt 14
Planned order release 14

Week 4:

The gross requirement is 3 (1 assembly) derived from the Planned order release of D. The on-hand inventory is 4. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 5.

Week 5:

The gross requirement is 15 (1 assembly) derived from the Planned order release of H. The on-hand inventory is 1. Hence, the Net requirement is 14. The lead time is 1 week. Therefore, the Planned order release will be 14 in week 4 which will be the Planned order receipt in week 5.

If this week is week 1 of the production plan, the increase in the lead time will make that only 1 assembly of G will be available for F in week 5. Hence, item F and consequently 4 units of item A will be delayed by a time of 1 week.

c)

Summary Introduction

To determine: The options the production manager has to manage these changes.

c)

Expert Solution
Check Mark

Explanation of Solution

Options the production manager has to manage these changes:

The production manager can do the following. They are:

  • The production manager can inform the customer in advance that the 4 units will be delayed by a time of 1 week.
  • The production manager can ask the supplier of item G to expedite the production or the delivery.
  • The production manager can reduce the time take for production of item F or A.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Given the following parents and components, construct a product tree. Figures inparentheses show the quantities per item. How many Gs are needed to make one A?
BJMP2033/CH 7 MRP/A211 EXERCISE #9 Based on the statement below, construct a product structure tree. Product ALPHA is built from two components of BETA and COMMA. The BETA is built from two components of DELTA and two components of COLT. The COMMA is built from ELTA and two components of FEMA. The COLT is built from three sub-components of ERRA and four sub-components of FESA.
As the production planner for Xiangling Hu​ Products, Inc., you have been given a bill of material for a bracket that is made up of a​ base, 1 spring​, and 3 clamps. The base is assembled from 2 clamp and 1 housing. Each clamp has 1 handle and 1 casting. Each housing has 2 bearing and 2 shaft. There is no inventory on hand. Part 2 ​a) Design a product structure noting the quantities for each item and show the​ low-level coding. Match each number in the structure below with the corresponding item. Number Item I Bracket II Spring Subscript left parenthesis 1 right parenthesis III Clamp Subscript left parenthesis 3 right parenthesis IV Bearing Subscript left parenthesis 2 right

Chapter 14 Solutions

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB

Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Prob. 17PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 19PCh. 14 - Prob. 20PCh. 14 - Prob. 21PCh. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 28PCh. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1CSCh. 14 - Prob. 2CSCh. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - Prob. 2.1VCCh. 14 - Prob. 2.2VCCh. 14 - Prob. 2.3VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY