Concept explainers
a)
To develop: A net requirements plan for items.
Introduction:
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the
a)

Explanation of Solution
Given information:
Product structure:
Period | 8 | 9 | 10 | 11 | 12 |
Gross requirements: A | 100 | 50 | 150 | ||
Gross requirements: H | 100 | 50 |
Inventory and lead time:
Item | A | B | C | D | E | F | G | H | J | K |
Lead time | 1 | 2 | 2 | 1 | 2 | 2 | 1 | 1 | 2 | 2 |
On hand | 0 | 100 | 50 | 50 | 75 | 75 | 75 | 0 | 100 | 100 |
- 1 assembly for each item
Item A:
Week | ||||||||||||
Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 50 | 150 | |||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | 0 | 0 | |||||||||
Net requirement | 100 | 50 | 150 | |||||||||
Planned order receipt | 100 | 50 | 150 | |||||||||
Planned order release | 100 | 50 | 150 |
Week 8:
The gross requirement is 100 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 1 week. Therefore, the planned order release will be 100 in week 7 which will be the planned order receipt in week 8.
Week 10:
The gross requirement is 50 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 1 week. Therefore, the planned order release will be 50 in week 9 which will be the planned order receipt in week 10.
Week 12:
The gross requirement is 150 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 1 week. Therefore, the planned order release will be 150 in week 11 which will be the planned order receipt in week 12.
Item H:
Week | ||||||||||||
Item H | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 50 | ||||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | 0 | ||||||||||
Net requirement | 100 | 50 | ||||||||||
Planned order receipt | 100 | 50 | ||||||||||
Planned order release | 100 | 50 |
Week 9:
The gross requirement is 100 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 1000. The lead time is 1 week. Therefore, the planned order release will be 100 in week 8 which will be the planned order receipt in week 10.
Week 11:
The gross requirement is 50 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 1 week. Therefore, the planned order release will be 50 in week 9 which will be the planned order receipt in week 11.
Item B:
Week | ||||||||||||
Item B | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 50 | 150 | |||||||||
Scheduled receipt | ||||||||||||
On hand (100) | 100 | 0 | 0 | |||||||||
Net requirement | 0 | 50 | 150 | |||||||||
Planned order receipt | 50 | 150 | ||||||||||
Planned order release | 50 | 150 |
Week 7:
The gross requirement is 100 (1 assembly) derived from planned order release of A. The on hand inventory is 100. Hence, the net requirement is 0. Therefore, there will be no planned order release.
Week 9:
The gross requirement is 50 (1 assembly) derived from the planned order release of A. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 7 which will be the planned order receipt in week 9.
Week 11:
The gross requirement is 150 (1 assembly) derived from planned order release of A. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 2 weeks. Therefore, the planned order release will be 150 in week 9 which will be the planned order receipt in week 11.
Item C:
Week | ||||||||||||
Item C | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 100 | 50 | 50 | 150 | |||||||
Scheduled receipt | ||||||||||||
On hand (50) | 50 | 0 | 0 | 0 | 0 | |||||||
Net requirement | 50 | 100 | 50 | 50 | 150 | |||||||
Planned order receipt | 50 | 100 | 50 | 50 | 150 | |||||||
Planned order release | 50 | 100 | 50 | 50 | 150 |
Week 7:
The gross requirement is 100 (1 assembly) derived from planned order release of A. The on hand inventory is 50. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 5 which will be the planned order receipt in week 7.
Week 8:
The gross requirement is 100 (1 assembly) derived from planned order release of H. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 6 which will be the planned order receipt in week 8.
Week 9:
The gross requirement is 50 (1 assembly) derived from the planned order release of A. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 7 which will be the planned order receipt in week 9.
Week 10:
The gross requirement is 50 (1 assembly) derived from planned order release of H. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 8 which will be the planned order receipt in week 10.
Week 11:
The gross requirement is 150 (1 assembly) derived from planned order release of A. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 2 weeks. Therefore, the planned order release will be 150 in week 9 which will be the planned order receipt in week 11.
Item J:
Week | ||||||||||||
Item J | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 50 | ||||||||||
Scheduled receipt | ||||||||||||
On hand (100) | 100 | 0 | ||||||||||
Net requirement | 0 | 50 | ||||||||||
Planned order receipt | 0 | 50 | ||||||||||
Planned order release | 50 |
Week 8:
The gross requirement is 100 (1 assembly) derived from planned order release of H. The on hand inventory is 100. Hence, the net requirement is 0. Therefore, there will be no planned order release.
Week 10:
The gross requirement is 50 (1 assembly) derived from the planned order release of H. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 8 which will be the planned order receipt in week 10.
Item K:
Week | ||||||||||||
Item K | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 50 | ||||||||||
Scheduled receipt | ||||||||||||
On hand (100) | 100 | 0 | ||||||||||
Net requirement | 0 | 50 | ||||||||||
Planned order receipt | 50 | |||||||||||
Planned order release | 50 |
Week 8:
The gross requirement is 100 (1 assembly) derived from planned order release of H. The on hand inventory is 100. Hence, the net requirement is 0. Therefore, there will be no planned order release.
Week 10:
The gross requirement is 50 (1 assembly) derived from the planned order release of H. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 8 which will be the planned order receipt in week 10.
Item D:
Week | ||||||||||||
Item D | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 50 | 150 | ||||||||||
Scheduled receipt | ||||||||||||
On hand (50) | 50 | 0 | ||||||||||
Net requirement | 150 | |||||||||||
Planned order receipt | 150 | |||||||||||
Planned order release | 150 |
Week 7:
The gross requirement is 50 (1 assembly) derived from planned order release of B. The on hand inventory is 500. Hence, the net requirement is 0. Therefore, there will be no planned order release.
Week 9:
The gross requirement is 150 (1 assembly) derived from the planned order release of B. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 1 week. Therefore, the planned order release will be 150 in week 8 which will be the planned order receipt in week 9.
Item E:
Week | ||||||||||||
Item E | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 50 | 100 | 150 | |||||||||
Scheduled receipt | ||||||||||||
On hand (75) | 75 | 25 | 0 | |||||||||
Net requirement | 0 | 75 | 150 | |||||||||
Planned order receipt | 75 | 150 | ||||||||||
Planned order release | 75 | 150 |
Week 7:
The gross requirement is 50 (1 assembly) derived from planned order release of B. The on hand inventory is 75. Hence, the net requirement is 0. Therefore, there will be no planned order release.
Week 8:
The gross requirement is 100 (1 assembly) derived from the planned order release of J and K. The on hand inventory is 25. Hence, the net requirement is 75. The lead time is 2 weeks. Therefore, the planned order release will be 75 in week 6 which will be the planned order receipt in week 8.
Week 9:
The gross requirement is 150 (1 assembly) derived from planned order release of B. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 2 weeks. Therefore, the planned order release will be 150 in week 7 which will be the planned order receipt in week 9.
Item F:
Week | ||||||||||||
Item F | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 50 | 100 | 50 | 100 | 150 | |||||||
Scheduled receipt | ||||||||||||
On hand (75) | 75 | 25 | 0 | 0 | 0 | |||||||
Net requirement | 0 | 75 | 50 | 100 | 150 | |||||||
Planned order receipt | 75 | 50 | 100 | 150 | ||||||||
Planned order release | 75 | 50 | 100 | 150 |
Week 5:
The gross requirement is 50 (1 assembly) derived from planned order release of C. The on hand inventory is 75. Hence, the net requirement is 0. Therefore, there will be no planned order release.
Week 6:
The gross requirement is 100 (1 assembly) derived from planned order release of C. The on hand inventory is 25. Hence, the net requirement is 75. The lead time is 2 weeks. Therefore, the planned order release will be 75 in week 4 which will be the planned order receipt in week 6.
Week 7:
The gross requirement is 50 (1 assembly) derived from the planned order release of C. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 5 which will be the planned order receipt in week 7.
Week 8:
The gross requirement is 100 (1 assembly) derived from planned order release of C and J. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 6 which will be the planned order receipt in week 8.
Week 9:
The gross requirement is 150 (1 assembly) derived from planned order release of C. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 2 weeks. Therefore, the planned order release will be 150 in week 7 which will be the planned order receipt in week 9.
Item G:
Week | ||||||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 50 | 100 | 50 | 100 | 150 | |||||||
Scheduled receipt | ||||||||||||
On hand (75) | 75 | 25 | 0 | 0 | 0 | |||||||
Net requirement | 0 | 75 | 50 | 100 | 150 | |||||||
Planned order receipt | 75 | 50 | 100 | 150 | ||||||||
Planned order release | 75 | 50 | 100 | 150 |
Week 5:
The gross requirement is 50 (1 assembly) derived from planned order release of C. The on hand inventory is 75. Hence, the net requirement is 0. Therefore, there will be no planned order release.
Week 6:
The gross requirement is 100 (1 assembly) derived from planned order release of C. The on hand inventory is 25. Hence, the net requirement is 75. The lead time is 1 week. Therefore, the planned order release will be 75 in week 5 which will be the planned order receipt in week 6.
Week 7:
The gross requirement is 50 (1 assembly) derived from the planned order release of C. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 1 week. Therefore, the planned order release will be 50 in week 6 which will be the planned order receipt in week 7.
Week 8:
The gross requirement is 100 (1 assembly) derived from planned order release of C and K. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 1 week. Therefore, the planned order release will be 100 in week 7 which will be the planned order receipt in week 8.
Week 9:
The gross requirement is 150 (1 assembly) derived from planned order release of C. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 1 week. Therefore, the planned order release will be 150 in week 8 which will be the planned order receipt in week 9.
b)
To develop: A net requirements plan for all items.
Introduction:
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.
b)

Explanation of Solution
Given information:
Product structure:
Period | 8 | 9 | 10 | 11 | 12 |
Gross requirements: A | 100 | 50 | 150 | ||
Gross requirements: H | 100 | 50 |
Inventory and lead time:
Item | A | B | C | D | E | F | G | H | J | K |
Lead time | 1 | 2 | 2 | 1 | 2 | 2 | 1 | 1 | 2 | 2 |
On hand | 0 | 100 | 50 | 50 | 75 | 75 | 75 | 0 | 100 | 100 |
- 1 assembly for each item
- 2 assemblies for item B, C and F.
Item A:
Week | ||||||||||||
Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 50 | 150 | |||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | 0 | 0 | |||||||||
Net requirement | 100 | 50 | 150 | |||||||||
Planned order receipt | 100 | 50 | 150 | |||||||||
Planned order release | 100 | 50 | 150 |
Week 8:
The gross requirement is 100 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 1 week. Therefore, the planned order release will be 100 in week 7 which will be the planned order receipt in week 8.
Week 10:
The gross requirement is 50 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 1 week. Therefore, the planned order release will be 50 in week 9 which will be the planned order receipt in week 10.
Week 12:
The gross requirement is 150 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 1 week. Therefore, the planned order release will be 150 in week 11 which will be the planned order receipt in week 12.
Item H:
Week | ||||||||||||
Item H | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 50 | ||||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | 0 | ||||||||||
Net requirement | 100 | 50 | ||||||||||
Planned order receipt | 100 | 50 | ||||||||||
Planned order release | 100 | 50 |
Week 9:
The gross requirement is 100 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 1000. The lead time is 1 week. Therefore, the planned order release will be 100 in week 8 which will be the planned order receipt in week 10.
Week 11:
The gross requirement is 50 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 1 week. Therefore, the planned order release will be 50 in week 9 which will be the planned order receipt in week 11.
Item B:
Week | ||||||||||||
Item B | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 200 | 100 | 300 | |||||||||
Scheduled receipt | ||||||||||||
On hand (100) | 100 | 0 | 0 | |||||||||
Net requirement | 100 | 100 | 300 | |||||||||
Planned order receipt | 100 | 100 | 300 | |||||||||
Planned order release | 100 | 100 | 300 |
Week 7:
The gross requirement is 200 (2 assembly) derived from planned order release of A. The on hand inventory is 100. Hence, the net requirement is 100. Therefore, the planned order release will be 100 in week 5 which will be the planned order receipt in week 7.
Week 9:
The gross requirement is 100 (2 assembly) derived from the planned order release of A. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 7 which will be the planned order receipt in week 9.
Week 11:
The gross requirement is 300 (2 assembly) derived from planned order release of A. The on hand inventory is 0. Hence, the net requirement is 300. The lead time is 2 weeks. Therefore, the planned order release will be 300 in week 9 which will be the planned order receipt in week 11.
Item C:
Week | ||||||||||||
Item C | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 200 | 200 | 100 | 100 | 300 | |||||||
Scheduled receipt | ||||||||||||
On hand (50) | 50 | 0 | 0 | 0 | 0 | |||||||
Net requirement | 150 | 200 | 100 | 100 | 300 | |||||||
Planned order receipt | 150 | 200 | 100 | 100 | 300 | |||||||
Planned order release | 150 | 200 | 100 | 100 | 300 |
Week 7:
The gross requirement is 200 (2 assembly) derived from planned order release of A. The on hand inventory is 50. Hence, the net requirement is 150. The lead time is 2 weeks. Therefore, the planned order release will be 150 in week 5 which will be the planned order receipt in week 7.
Week 8:
The gross requirement is 200 (2 assembly) derived from planned order release of H. The on hand inventory is 0. Hence, the net requirement is 200. The lead time is 2 weeks. Therefore, the planned order release will be 200 in week 6 which will be the planned order receipt in week 8.
Week 9:
The gross requirement is 100 (2 assembly) derived from the planned order release of A. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 7 which will be the planned order receipt in week 9.
Week 10:
The gross requirement is 100 (2 assembly) derived from planned order release of H. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 8 which will be the planned order receipt in week 10.
Week 11:
The gross requirement is 300 (2 assembly) derived from planned order release of A. The on hand inventory is 0. Hence, the net requirement is 300. The lead time is 2 weeks. Therefore, the planned order release will be 300 in week 9 which will be the planned order receipt in week 11.
Item J:
Week | ||||||||||||
Item J | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 50 | ||||||||||
Scheduled receipt | ||||||||||||
On hand (100) | 100 | 0 | ||||||||||
Net requirement | 0 | 50 | ||||||||||
Planned order receipt | 0 | 50 | ||||||||||
Planned order release | 50 |
Week 8:
The gross requirement is 100 (1 assembly) derived from planned order release of H. The on hand inventory is 100. Hence, the net requirement is 0. Therefore, there will be no planned order release.
Week 10:
The gross requirement is 50 (1 assembly) derived from the planned order release of H. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 8 which will be the planned order receipt in week 10.
Item K:
Week | ||||||||||||
Item K | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 50 | ||||||||||
Scheduled receipt | ||||||||||||
On hand (100) | 100 | 0 | ||||||||||
Net requirement | 0 | 50 | ||||||||||
Planned order receipt | 50 | |||||||||||
Planned order release | 50 |
Week 8:
The gross requirement is 100 (1 assembly) derived from planned order release of H. The on hand inventory is 100. Hence, the net requirement is 0. Therefore, there will be no planned order release.
Week 10:
The gross requirement is 50 (1 assembly) derived from the planned order release of H. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 8 which will be the planned order receipt in week 10.
Item D:
Week | ||||||||||||
Item D | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 100 | 300 | |||||||||
Scheduled receipt | ||||||||||||
On hand (50) | 50 | 0 | 0 | |||||||||
Net requirement | 50 | 100 | 300 | |||||||||
Planned order receipt | 50 | 100 | 300 | |||||||||
Planned order release | 50 | 100 | 300 |
Week 6:
The gross requirement is 100 (1 assembly) derived from the planned order release of B. The on hand inventory is 50. Hence, the net requirement is 50. The lead time is 1 week. Therefore, the planned order release will be 50 in week 5 which will be the planned order receipt in week 6.
Week 8:
The gross requirement is 100 (1 assembly) derived from the planned order release of B. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 1 week. Therefore, the planned order release will be 100 in week 7 which will be the planned order receipt in week 8.
Week 8:
The gross requirement is 300 (1 assembly) derived from the planned order release of B. The on hand inventory is 0. Hence, the net requirement is 300. The lead time is 1 week. Therefore, the planned order release will be 300 in week 9 which will be the planned order receipt in week 10.
Item E:
Week | ||||||||||||
Item E | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 100 | 100 | 300 | ||||||||
Scheduled receipt | ||||||||||||
On hand (75) | 75 | 0 | 0 | 0 | ||||||||
Net requirement | 25 | 100 | 100 | 300 | ||||||||
Planned order receipt | 25 | 100 | 100 | 300 | ||||||||
Planned order release | 25 | 100 | 100 | 300 |
Week 5:
The gross requirement is 100 (1 assembly) derived from planned order release of B. The on hand inventory is 75. Hence, the net requirement is 25. The lead time is 2 weeks. Therefore, the planned order release will be 25 in week 3 which will be the planned order receipt in week 5.
Week 7:
The gross requirement is 100 (1 assembly) derived from planned order release of B. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 5 which will be the planned order receipt in week 7.
Week 8:
The gross requirement is 100 (1 assembly) derived from the planned order release of J and K. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 6 which will be the planned order receipt in week 8.
Week 9:
The gross requirement is 300 (1 assembly) derived from planned order release of B. The on hand inventory is 0. Hence, the net requirement is 300. The lead time is 2 weeks. Therefore, the planned order release will be 300 in week 7 which will be the planned order receipt in week 9.
Item F:
Week | ||||||||||||
Item F | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 300 | 400 | 200 | 300 | 600 | |||||||
Scheduled receipt | ||||||||||||
On hand (75) | 75 | 0 | 0 | 0 | 0 | |||||||
Net requirement | 225 | 400 | 200 | 300 | 600 | |||||||
Planned order receipt | 225 | 400 | 200 | 300 | 600 | |||||||
Planned order release | 225 | 400 | 200 | 300 | 600 |
Week 5:
The gross requirement is 300 (2 assembly) derived from planned order release of C. The on hand inventory is 75. Hence, the net requirement is 225. The lead time is 2 weeks. Therefore, the planned order release will be 225 in week 3 which will be the planned order receipt in week 5.
Week 6:
The gross requirement is 400 (2 assembly) derived from planned order release of C. The on hand inventory is 0. Hence, the net requirement is 400. The lead time is 2 weeks. Therefore, the planned order release will be 400 in week 4 which will be the planned order receipt in week 6.
Week 7:
The gross requirement is 200 (2 assembly) derived from the planned order release of C. The on hand inventory is 0. Hence, the net requirement is 200. The lead time is 2 weeks. Therefore, the planned order release will be 200 in week 5 which will be the planned order receipt in week 7.
Week 8:
The gross requirement is 300 (2 assembly) derived from planned order release of C and J. The on hand inventory is 0. Hence, the net requirement is 300. The lead time is 2 weeks. Therefore, the planned order release will be 300 in week 6 which will be the planned order receipt in week 8.
Week 9:
The gross requirement is 600 (2 assembly) derived from planned order release of C. The on hand inventory is 0. Hence, the net requirement is 600. The lead time is 2 weeks. Therefore, the planned order release will be 600 in week 7 which will be the planned order receipt in week 9.
Item G:
Week | ||||||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 150 | 200 | 100 | 150 | 300 | |||||||
Scheduled receipt | ||||||||||||
On hand (75) | 75 | 0 | 0 | 0 | 0 | |||||||
Net requirement | 75 | 200 | 100 | 150 | 300 | |||||||
Planned order receipt | 75 | 200 | 100 | 150 | 300 | |||||||
Planned order release | 75 | 200 | 100 | 150 | 300 |
Week 5:
The gross requirement is 150 (1 assembly) derived from planned order release of C. The on hand inventory is 75. Hence, the net requirement is 75. The lead time is 1 week. Therefore, the planned order release will be 75 in week 4 which will be the planned order receipt in week 5.
Week 6:
The gross requirement is 200 (1 assembly) derived from planned order release of C. The on hand inventory is 0. Hence, the net requirement is 200. The lead time is 1 week. Therefore, the planned order release will be 200 in week 5 which will be the planned order receipt in week 6.
Week 7:
The gross requirement is 100 (1 assembly) derived from the planned order release of C. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 1 week. Therefore, the planned order release will be 100 in week 6 which will be the planned order receipt in week 7.
Week 8:
The gross requirement is 150 (1 assembly) derived from planned order release of C and K. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 1 week. Therefore, the planned order release will be 150 in week 7 which will be the planned order receipt in week 8.
Week 9:
The gross requirement is 300 (1 assembly) derived from planned order release of C. The on hand inventory is 0. Hence, the net requirement is 300. The lead time is 1 week. Therefore, the planned order release will be 300 in week 8 which will be the planned order receipt in week 9.
Want to see more full solutions like this?
Chapter 14 Solutions
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
- Not use ai pleasearrow_forwardSam's Pet Hotel operates 51 weeks per year, 6 days per week, and uses a continuous review inventory system. It purchases kitty litter for $11.00 per bag. The following information is available about these bags: > Demand 95 bags/week > Order cost $52.00/order > Annual holding cost = 25 percent of cost > Desired cycle-service level = 80 percent >Lead time 4 weeks (24 working days) > Standard deviation of weekly demand = 15 bags > Current on-hand inventory is 320 bags, with no open orders or backorders. a. Suppose that the weekly demand forecast of 95 bags is incorrect and actual demand averages only 75 bags per week. How much higher will total costs be, owing to the distorted EOQ caused by this forecast error? The costs will be $ higher owing to the error in EOQ. (Enter your response rounded to two decimal places.)arrow_forwardSam's Pet Hotel operates 50 weeks per year, 6 days per week, and uses a continuous review inventory system. It purchases kitty litter for $10.50 per bag. The following information is available about these bags: > Demand = 95 bags/week > Order cost = $55.00/order > Annual holding cost = 35 percent of cost > Desired cycle-service level = 80 percent > Lead time = 4 weeks (24 working days) > Standard deviation of weekly demand = 15 bags > Current on-hand inventory is 320 bags, with no open orders or backorders. a. Suppose that the weekly demand forecast of 95 bags is incorrect and actual demand averages only 75 bags per week. How much higher will total costs be, owing to the distorted EOQ caused by this forecast error? The costs will be $ 10.64 higher owing to the error in EOQ. (Enter your response rounded to two decimal places.) b. Suppose that actual demand is 75 bags but that ordering costs are cut to only $13.00 by using the internet to automate order placing. However, the buyer does…arrow_forward
- BUS-660 Topic 4: Intege... W Midterm Exam - BUS-66... webassign.net b Answered: The binding c... × W Topic 4 Assignment - BU... how to get more chegg... b My Questions | bartleby + macbook screenshot - G... C Consider the following m... As discussed in Section 8.3, the Markowitz model uses the variance of the portfolio as the measure of risk. However, variance includes deviations both below and above the mean return. Semivariance includes only deviations below the mean and is considered by many to be a better measure of risk. (a) Develop a model that minimizes semivariance for the Hauck Financial data given in the file HauckData with a required return of 10%. Assume that the five planning scenarios in the Hauck Financial Services model are equally likely to occur. Hint: Modify model (8.10)-(8.19). Define a variable d for each 5 - scenario and let d≥ Ŕ – R¸ with d¸ ≥ 0. Then make the objective function: Min 1 5 Σας Let Min s.t. 15 FS = proportion of portfolio invested in the foreign…arrow_forwardOn a daily basis, the van is dispatched from Maplewood Hospital to pickup blood and platelet donations made at its local donation centers. The distances in miles between all locations may be found in the table below. Click the icon to view mileage data for Vampire Van. a. The van travels from the Hospital (A) to (B) to (C) to (D) to (E) and then returns to the Hospital (A). What is the total number of miles that the van must travel using this route? Route ABCDEA requires a total distance of miles. (Enter your response rounded to one decimal place.) More Info Maplewood City Center Westbrook Hospital (A) Donation Site (B) Donation Site (C) Municipal Park Donation Site (D) Valley Hills Donation Site (E) Maplewood 3.1 5.3 3.2 4.4 Hospital (A) City Center 3.1 6.7 2.2 4.3 Donation Site (B) Westbrook 5.3 Donation Site (C) 19 6.7 | 6.2 2.5 Municipal Park 3.2 2.2 6.2 | 4.6 Donation Site (D) Valley Hills 4.4 4.3 2.5 4.6 Donation Site (E) - ☑arrow_forwardThe Harvey Motorcycle Company produces three models: the Tiger, a sure-footed dirt bike; the LX2000, a nimble cafe racer; and the Golden, a large interstate tourer. The month's master production schedule calls for the production of 32 Goldens, 31 LX2000s, and 38 Tigers per 10-hour shift. What average cycle time is required for the assembly line to achieve the production quota in 10 hours? 0.099 hours per motorcycle. (Enter your response rounded to three decimal places.) If mixed-model scheduling is used, how many of each model will be produced before the production cycle is repeated? The greatest common divisor of the production requirements is Therefore, the Harvey Motorcycle Company will produce Goldens, LX2000s, and Tigers. (Enter your responses as integers.)arrow_forward
- The Harvey Motorcycle Company produces three models: the Tiger, a sure-footed dirt bike; the LX2000, a nimble cafe racer; and the Golden, a large interstate tourer. The month's master production schedule calls for the production of 32 Goldens, 31 LX2000s, and 38 Tigers per 10-hour shift. What average cycle time is required for the assembly line to achieve the production quota in 10 hours? hours per motorcycle. (Enter your response rounded to three decimal places.)arrow_forwardThe binding constraints for this problem are the second and third constraints are binding. Min x1 + 2x2 s.t. x1 + x2 ≤ 300 2x1 + x2 ≥ 400 2x1 + 5x2 ≥750 X1, X220 (a) Keeping the second objective function coefficient fixed at 2, over what range can the first objective function coefficient vary before there is a change in the optimal solution point? The first objective coefficient can from a low of to a high of (b) Keeping the first objective function coefficient fixed at 1, over what range can the second objective function coefficient vary before there is a change in the optimal solution point? The second objective coefficient can from a low of to a high of (c) If the objective function becomes Min 1.5x₁ + 2x2, what will be the optimal values of x1 and x2? x1 = X2 = What is the value of the objective function at the minimum? (d) If the objective function becomes Min 7x₁ + 6x2, what constraints will be binding? (Select all that apply.) First Constraint Second Constraint Third Constraint…arrow_forward[-16.66 Points] DETAILS MY NOTES CAMMIMS16 4.E.008. 0/1 Submissions Used A linear programming computer package is needed. ASK YOUR TEACHER PRACTICE ANOTHER The Clark County Sheriff's Department schedules police officers for 8-hour shifts. The beginning times for the shifts are 8:00 a.m., noon, 4:00 p.m., 8:00 p.m., midnight, and 4:00 a.m. An officer beginning a shift at one of these times works for the next 8 hours. During normal weekday operations, the number of officers needed varies depending on the time of day. The department staffing guidelines require the following minimum number of officers on duty: Time of Day 8:00 A.M. Noon Noon - 4:00 P.M. Minimum Officers Time of Day on Duty 4 7 4:00 P.M. - 8:00 P.M. 11 8:00 P.M. Midnight 6 Midnight 4:00 A.M. 4:00 A.M. -8:00 A.M. 3 7 Determine the number of police officers that should be scheduled to begin the 8-hour shifts at each of the six times (8:00 a.m., noon, 4:00 p.m., 8:00 p.m., midnight, and 4:00 a.m.) to minimize the total number…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning

