Concept explainers
a)
To generate: An intended bill of material of for the product A.
Introduction:
Intended bill of material:
An intended bill of material is also defined as a multi-level bill of material. It will list the assemblies, subparts and other components that are needed to make a product. It will also display the parent children relationship between the products.
b)
To generate: A net requirements plan for each part to produce 10 A’s in week 8 using Lot for lot.
Introduction:
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the
Want to see the full answer?
Check out a sample textbook solutionChapter 14 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- The table given below shows a partially completed MPS record for product A. What is the remaining ATP inventory (discrete) for week 7 after the company receives a 20 units of customer order for week 6? Order policy: 60 units Lead time: 1 week Item: A Quantity on hand: 30 Week 3 30 7. 34 11 4. Forecast requirements Customer orders (booked) Projected on-hand inventory MPS quantity MPS start ATP inventory 22 24 18 27 36 28 26 12 24 O a 59 Ob. 29 OcO Od. 49 Oe. 39arrow_forwardIn the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank-be certain to enter "0" wherever required.) ITEM 3 Gross requirements On-hand Net requirements Planned order receipt Planned order release Period Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases WEEK NUMBER 2 3 76 4 48 76 5 72 48 72arrow_forwardUsing the accompanying diagram, do the following:a. Draw a tree diagram for the scissors.b. Prepare an MRP plan for scissors. Lead times are one day for each component and final scissorassembly, but two days for the plastic grips. Six hundred pairs of scissors are needed on day 6. Note:There are 200 straight blades and 350 bent blades on hand, and 40 top blade assemblies on hand.Use lot-for-lot ordering for all items.arrow_forward
- Please do not give solution in image formate thanku.arrow_forwardBrown and Brown Electronics manufactures a line of digital audiotape (DAT) players. The bill of materials, showing the number of each item required is shown below follows: F(2) C(1) I(2) F(2) H(1) I(2) Data for A: Gross requirement is 100 units on 9th week, Lead time is 2 weeks, Lot for lot A G(2) D(2) Data for C: Lead time is 1 weeks, Lot for lot Data for D: Lead time is 2 weeks, schedule receipt is 30 on 1st week, lot size 170 units Data for F: Lead time is 1 weeks, scheduled receipt is 60 on 1st week, on hand inventory is 15, lot for lot Data for G: Lead time is 1 weeks, scheduled receipt is 100 on 1st week, on hand inventory is 50, lot for lot Data for H: Lead time is 1 weeks, scheduled receipt is 50 on 1st week, lot size is 200 Data for I: Lead time is 1 weeks, scheduled receipt is 60 on 1st week, on hand inventory is 15, lot for lot Prepare an MRP schedule to satisfy the demand.arrow_forwardGiven the product structure, master productionschedule, and inventory status in Figure 14.13, and assuming therequirements for each BOM item is I:a) develop a gross requirements plan for Item C;b) develop a net requirements plan for Item C.arrow_forward
- Answer all 3 parts please!arrow_forwardProduct M is made of two units of N and two of P. N is made of two units of R and four units of S. R is made of one unit of S and three units of T. P is made of two units of T and four units of U. a. Show the bill-of-materials (product structure tree). b. If 100 Ms are required, how many units of each component are needed? c. Show both a single-level parts list and an indented parts list.arrow_forwardMultiple Choice Question, Pls solve it quicklyarrow_forward
- Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the startof week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are inproduction and will be completed by the start of week 2. Lot-for-lot ordering will be used for all items.arrow_forwardLead time for a certain part is 2 weeks, and the order quantity is 50. By completing this MRP record below, answer the following question: What are the Net requirements of the part in Week 3? What action should be taken? O Week Gross Requirements Projected Available Net Requirements Planned Order Receipt Planned Order Release 50 30 O 25 O None of the above 40 1 20 2 15 3 25 4 25arrow_forwardIt is Friday afternoon and the following production information is available for the following week: EOQ Lead time b) c) d) 100 units 2 days Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases 0 Monday Tuesday Wednesday Thursday Friday 40 70 80 50 40 100 Complete the MRP matrix for the following week with this information. At the production meeting on Monday morning the following information is shared: a) The planned order for 100 units on Monday is released. Thirty of the scheduled receipts for Monday are scrapped. An order for 20 units is received for delivery on Wednesday. An order for 40 units is received for delivery on Monday of the following week. EOQ Lead time 50 100 units 2 days Use this information to update the MRP matrix for the week.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.