EBK PRINCIPLES OF OPERATIONS MANAGEMENT
10th Edition
ISBN: 8220102744059
Author: HEIZER
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 14, Problem 4P
Your boss at Xiangling Hu Products, Inc., has just provided you with the
a) Prepare the time-phased product structure for the bracket.
b) In what week do you need to start the castings?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Your boss at Xiangling Hu Products, Inc., has just provided you with the schedule and lead times for the bracket. The unit is to be prepared in week 10. The lead times for the components a re bracket (I week), base (1 week), spring ( I week), clamp (I week), housing (2 weeks), handle (I week), casting (3 weeks), bearing (I week), and shaft (1 week).a) Prepare the time-phased product structure for the bracket.b) In what week do you need to start the castings?
solve all the parts within 30 minutes.
Can you assist me with Problem 7 errors. Thank you greatly
Chapter 14 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
Ch. 14 - Ethical Dilemma For many months your prospective...Ch. 14 - What is the difference between a gross...Ch. 14 - Prob. 2DQCh. 14 - What are the similarities between MRP and DRP?Ch. 14 - How does MRP II differ from MRP?Ch. 14 - Which is the best lot-sizing policy for...Ch. 14 - What impact does ignoring carrying cost in the...Ch. 14 - MRP is more than an inventory system; what...Ch. 14 - What are the options for the production planner...Ch. 14 - Master schedules are expressed in three different...
Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- One unit of A is made of two units of B and one unit of C. B is made of three units of Dand one unit of F. C is composed of three units of B, one unit of D, and four units of E.D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F havetwo-week lead times; and Item D has a lead time of three weeks. Lot-for-lot (L4L) lot sizingis used for Items C, E, and F; lots of size 20, 40, and 160 are used for Items A, B, andD, respectively. Items A, B, D, and E have on-hand (beginning) inventories of 5, 10, 100,and 100, respectively; all other items have zero beginning inventories. We are scheduledto receive 10 units of A in Week 3, 20 units of B in Week 7, 40 units of F in Week 5, and60 units of E in Week 2; there are no other scheduled receipts. If 20 units of A are requiredin Week 10, use the low-level-coded bill-of-materials (product structure tree) to i nd thenecessary planned order releases for all components.arrow_forwardTable B shows a partially completed MPS record for ball Develop the MPS for ball Four customer orders arrived in the following sequences (Table B). Table A Order Quantity Week desired 1 500 4 2 400 5 3 300 1 4 300 7 Assume that you must commit to the orders in the sequence of arrival and cannot change the desired shipping dates or your MPS. Which orders should you accept? Table B Item: Ball bearings Quantity on hand: 400 Order policy: 500 units Lead time: 1 week Week 1 2 3 4 5 6 7 8 9 10 Forecast 550 300 400 450 300 350 200 300 450 400 Customer order booked 300 350 250 250 200 150 100 100 100 100 Projected on-hand inventory MPS quantity 500 MPS start Available to promise (ATP)arrow_forwardSniparrow_forward
- The product structure for product X is illustrated below. Level 0 Level 1 4 Level 2 Level 3 Part H B C D H K M N X Z с K B Lead Time (in weeks) 1 1 3 2 3 2 3 3 4 M D N The lead time for manufacturing any number units for an item and the required number of units for the lower level part in the product structure are reported in the following table. For example, each unit of Part X requires 1 units of Part C and, in turn, each unit of Part C requires 2 units of Part H and 2 units of Part K. 2 1 4 2 2 2 4 1 2 Required number of units X Z H K 100 units of product X are to shipped at the end of week 25. There is no inventory on hand. How many units of part N are required for production? 3200 Specify only the number.arrow_forwardDevelop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the startof week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are inproduction and will be completed by the start of week 2. Lot-for-lot ordering will be used for all items.arrow_forwardOne unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of three weeks. Lot-for-lot (L4L) lot sizing is used for Items A, D, and E; lots of size 50, 100, and 50 are used for Items B, C, and F, respectively. Items A, C, D, and E have on-hand (beginning) inventories of 15, 55, 100, and 10, respectively; all other items have zero beginning inventory. We are scheduled to receive 10 units of A in Week 1, 100 units of C in Week 1, and 100 units of D in Week 3; there are no other scheduled receipts.If 50 units of A are required in week 10, use the low-level-coded bill-of-materials (product structure tree) to find the necessary planned-order releases for all components. (Leave the cells blank, whenever zero (0) is required.)arrow_forward
- One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; items A, B, E, and F have two-week lead times; and item D has a lead time of three weeks. Lot-for-lot (L4L) lot sizing is used for items A, D, and E; lots of sizes 50, 100, and 50 are used for items B, C, and F, respectively. Items A, C, D, and E have on-hand (beginning) inventories of 20, 50, 100, and 10, respectively; all other items have zero beginning inventory. We are scheduled to receive 10 units of A in week 1, 100 units of C in week 1, and 100 units of D in week 3; there are no other scheduled receipts. If 50 units of A are required in week 10, use the low-level-coded bill-of-materials (product structure tree) to find the necessary planned-order releases for all components.arrow_forwardProduct Z is made from three units of A, two of B, and four of C. A, in turn, is made of one unit of C and five of D. A customer order was received for 200 units of Z in Week 8. (Hint: You will need to use "low-level coding", i.e., pull each item to the lowest level it appears on the BOM.) Item Lot Size On Hand Lead Time Z LFL 30 3 A LFL 40 1 B LFL 100 4 C 1000 50 3 D 500 2000 3 a. Show the Bill of Materials b. Develop MRP schedules showing gross/net requirements and planned order releases/receipts for each item.arrow_forwardOne unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; items A, B, E, and F have two-week lead times; and item D has a lead time of three weeks. Lot-for-lot (L4L) lot sizing is used for items C, E, and F; lots of size 20, 40, and 160 are used for items A, B, and D, respectively. Items A, B, D, and E have on-hand (beginning) inventories of 5, 10, 100, and 100, respectively; all other items have zero beginning inventories. We are scheduled to receive 10 units of A in week 3, 20 units of B in week 7, 40 units of F in week 5, and 60 units of E in week 2; there are no other scheduled receipts. If 20 units of A are required in week 10, use the low-level-coded bill-of-materials (product structure tree) to find thenecessary planned order releases for all components.arrow_forward
- help please I need it to be done in excelarrow_forwardEach A (finished product) requires 1 of component B and 2 of component C. Each B requires 2 of part D and 1 of part E and each C requires 1 of part D and 1 of part F.If the demand for product A is 50 units., and there are 15 units of B on hand and 50 units of C, how many units of Part D will be needed?arrow_forwardHeather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 8. Subscripts indicate quantity required for each parent. Assume lot-for-lot ordering. b. Choose correct time phased-structures c. Develop a net material requirements plan for F (enter your responses as whole numbers).arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY