Textbook Question
Chapter 14, Problem 1P
You have developed the following simple product structure of items needed for your gift bag for a rush party for prospective pledges in your organization. You
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Shown below is a partially completed MPS record for ball bearings.
a. Develop the MPS for ball bearings. (Enter your responses as integers. A response of "0" is equivalent to being
not applicable.)
Item: Ball bearings
Quantity
on Hand: 400
Forecast
Customer
orders (booked)
Projected on-hand
inventory
MPS quantity
MPS start
1
550
300
350
500
2
250
350
0
0
3
450
250
50
500
4
450
200
100
500
Order Policy: 500 units
Lead Time: 1 week
Week
5
250
150
350
500
6
400
100
450
500
7
200
50
250
0
8
250
100
To o
9
450
50
50
10
450
150
100
500 500
You have developed the following simple product structure of items needed for your gift bag for a rush party for prospective pledges in your organization. You forecast 200 attendees. Assume that there is no inventory on ha nd of any of the items. Explode the bill of material. (Subscripts indicate the number of units required.)
Shown below is a partially completed MPS record for hand drills.
a. Develop the MPS record for the hand drills. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.)
Item: Hand drills
Quantity
on Hand: 30
Forecast
Customer orders
(booked)
Projected on-hand
inventory
MPS quantity
MPS start
1
15
20
N
40
25
3
15
15
Week
Available-to-
promise (ATP)
inventory
b. A distributor of the hand drills places an order for 15 units. What is the appropriate shipping date for the entire order?
The order should ship on week
(Enter your response as an integer.)
4
20
20
Order Policy: 60 units
Lead Time: 1 week
5
55
0
6
35
0
Chapter 14 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
Ch. 14 - Ethical Dilemma For many months your prospective...Ch. 14 - What is the difference between a gross...Ch. 14 - Prob. 2DQCh. 14 - What are the similarities between MRP and DRP?Ch. 14 - How does MRP II differ from MRP?Ch. 14 - Which is the best lot-sizing policy for...Ch. 14 - What impact does ignoring carrying cost in the...Ch. 14 - MRP is more than an inventory system; what...Ch. 14 - What are the options for the production planner...Ch. 14 - Master schedules are expressed in three different...
Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Complete the MPS record below for a single item. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: A Order Policy: 100 units Lead Time: 1 week January February Quantity on Hand: 80 Week 1 2 3 4 5 6 7 8 Forecast 65 70 65 45 50 45 45 55 Customer orders (booked) 40 10 90 0 35 75 0 0 Projected on-hand inventory nothing nothing nothing nothing nothing nothing nothing nothing MPS quantity nothing nothing nothing nothing nothing nothing nothing nothing MPS start nothing nothing nothing nothing nothing nothing nothing nothingarrow_forwardAssume you are the manager of a shop that assembles power tools. You have just received an order for 55 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws follows: Item Lead Time (weeks) On Hand Saw A B C D E F 2 1 2 2 1 1 2 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipt Planned order release Ĉ E(3) & E(2) LT = 1 week Lot size: Lot-for-Lot 15 10 5 65 20 10 30 Skip Extension Tip: Double click to open in new tab Show Transcribed Text Develop the material requirements plan for component E using lot-for-lot ordering for all items. (Leave no cells blank - be certain to enter "0" wherever required.) Components A(2), B(1), C(4) E(3), D(1) D (2), F(3) E(2), D (2) Beg. Inv. 1 2 3 190 5 210 6arrow_forwardComplete the MPS record below for a single item. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: A Quantity on Hand: 80 Forecast Customer orders (booked) Projected on-hand inventory MPS quantity 1 70 40 ☐☐ January 2 70 65 80 Order Policy: 100 units Lead Time: 1 week February Week 4 40 0 5 45 35 50 70 45 0 8 50 0arrow_forward
- As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 1 clamp and\ 1 housing. Each clamp has 1 handle and 2 castings.Each housing has 1 bearing and 2 shafts.There is no inventory on hand. C) Compute the net quantities needed if there are 25 of the base and 75 of the clamp in stock. (Product structure picture attached) Base = (?) units Spring = (?) units Clamp = (?) units Housing = (?) units Handle = (?) units Casting = (?) units Bearing = (?) units Shaft = (?) unitsarrow_forwardI need correct and non plagiarised answer. I will rate accordingly. What is the difference between Quantity Production and Flow Line Production?arrow_forwardI understand that as per the calculations, the gross requirement for week 3 is 50 (25*2) (Item A's order releases), week 5 is 190 (20*2) + (150*1) (Item A's order releases + Item B's order releases), and week 6 is 300 (150*2) (Item A's order releases). But I want to know why do we do it that way because If I have a similar question do I always multiply item A's order release for week 3 by 2, week 5 (Item A's order releases x 2 + Item B's order releases x 1), and and week 6 (Item A's order releases x 2 ) I want to understand why we do that so I can anwser a similar question I don't understand why we do that have way just that you did it that wayarrow_forward
- Heather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 8. Subscripts indicate qua ntity req ui red for each p arent. Assume lot-for-lot ordering. Below is information about the steppers: a) Develop a product structure for Heather.b) Develop a time-phased structure.arrow_forwardConsider the bill of materials (BOM) shown to the right. Part 2 If inventory consists of 33 units of B, 11 unitunit of F, and 33 units of G, how many units of G, E, and D must be purchased to produce 55 units of product A? enter your response here unit(s) of item G, enter your response here units of item E, and enter your response here units of item D. (Enter your responses as integers.)arrow_forwardWhat part does work-in-process inventory play in the production process?arrow_forward
- opm please help ....arrow_forwardAs the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 2 clamps and 1 housing. Each clamp has 1handle and 1 casting. Each housing has 2 bearings and 2 shafts. There is no inventory on hand. c) Compute the net quantities needed if there are 25 of the base and 100 of the clamp in stock. Base: units (enter your response as a whole number). Spring: units Clamp: units Housing: units Handle units Casting: units Bearing: units Shaft: unitsarrow_forwardThe Alpha Beta Company produces two products; A and B, that are made from components C and D. Given the follow-ing product structures, master scheduling requirements, and inventory information, determine when orders shouldbe released for A, B, C, and D and the size of those orders.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY