Question
Chapter 14, Problem 13PA
Summary Introduction
Interpretation:The minimum make span
Concept Introduction:The total amount of time taken to complete a job recommended is called as the make span. The objective behind this concept is to reduce the amount of time consumed to complete a job work and thereby support the priorities of cost and time.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Christine has three cars that must be overhauled by her ace mechanic, Megan. Given the following data about the cars, use least slack per remaining operation to determine Megan’s scheduling priority for each:Customer Pick-Up Remaining Overhaul Car Time (hours hence) Time (hours) Remaining Operation A 10 4 PaintingB 17 5 Wheel alignment, painting C 15 1 Chrome plating, painting, seat repair
Panini, a popular sandwich shop, offers 3 types of sandwiches: grilled vegetables, grilled chicken, and pastrami. The table below provides demand data:
Grilled Vegetables
Grilled Chicken
Pastrami
Demand per hour
25
9
12
There are up to five steps in the process of making sandwiches listed below with activity times (if no activity time, then than step is not done for that sandwich). Only 50% of customers want their sandwich toasted, no matter which sandwich is ordered.
Step
Grilled Vegetables(in minutes)
Grilled Chicken(in minutes)
Pastrami(in minutes)
Cut bread
1
1
1
Grill
1.2
1.2
Slice meat
2
Toast
1.2
1.2
1.2
Wrap
0.8
0.8
0.8
Suppose Panini employs 1 worker at each step.
a) Does Panini have enough capacity to fulfill the current demand for sandwiches?
(b) What is the current capacity cushion for Panini? (as a %)
c) If demand for Pastramis increase with the percentage indicated below, how much additional workers should Panini hire (if any), and where…
Jack's Refrigeration Repair Service repairs and reconditions commercial icemakers at restaurants. Jack has four jobs to complete. Below are their processing times and due dates:
Job
Processing time (hours)
Due date (hour)
A
20
50
B
10
40
C
15
35
D
55
75
What is the average inventory if jobs are processed using the earliest due date rule?
Chapter 14 Solutions
OM (with OM Online, 1 term (6 months) Printed Access Card)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Please do not give solution in image formate thanku.arrow_forwardNeed to solve with Critical Path methodarrow_forwardNew students who join the university, should visit cer-tain departments in their first day, as part of the registration and induction process. Students are usually allocated to groups of ten,and their visits and their timings are as follows:DEPARTMENT DURATION FOR EACHGROUP (MINUTE)Registration/Finance 60IT 45Library 90Social Club 30Sport Centre 30Student Support Service 45Medical Centre 45Campus Services (banks, restaurant, etc.) 30During the visit, at least one person from the university student support team should be with each team of students. The stu-dent support team has allocated the visit of every two depart-ments to one person as follows: Deborah (Registration and IT), Gemma (Library and Social Club), Frank (Sport Centreand Student support service), and Raj (Medical centre and Campus services). The visits of the departments can be done inany sequence. Based on the current arrangements,a) What is the cycle timeb) What is the throughput per hourc) Total idle time in each…arrow_forward
- 1.Explain the concepts of scheduling and sequencing 2.Describe staff scheduling and appointment system decisions 3.Describe how to solve two-resource sequencing problems.arrow_forwardSubject: Operations researcharrow_forwardThe following 5 overhaul jobs are waiting to be processed at Avianic's Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days. Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.) Job CR Job Due Date Duration (days) 103 103 214 10 205 205 223 309 309 217 11 412 219 412 517 216 15 517 Assume that all jobs arrived on day 180; today's date is 200.arrow_forward
- Station 1,2,3,4,5,6,7,or 8arrow_forwardThe following jobs are waiting to be processed at Rick Solano’s machine center. Solano’s machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241 (day 241 is a workday). Job names refer to names of clients and contract numbers. Job Date job received Productiondays needed Date job due BR-02 228 15 300 CX-01 225 25 270 DE-06 230 35 320 RG-05 235 40 360 SY-11 231 30 310 a. Complete the following table. (Show your supporting calculations.) b.Which dispatching rule has the best score for flow time? c. Which dispatching rule would you select? Support your decision.arrow_forwardThe mowry machine shop still has five jobs to be processed as of 8A.M today (day 29) at its bottleneck operation. The time since the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in order of arrival: Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 12 4 10 B 7 3 24 C 5 10 16 D 3 8 7 E 1 4 13 Develope serpate schedules by using the FCF and EDS rules. Using FCF, the order is Using EDS, the order is The average flow time and average days past due are. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forward
- What are the advantages to finite capacity scheduling?arrow_forwardDraw a schedule for a brief comparison in points between a convenience store and a supermarket in : Front, parking, checkout, shelvingarrow_forwardCategorize different scheduling procedures for various types of service operations, such as restaurants, hospitals, and airlinesarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY