Interpretation: The order in which the jobs have arrived, the average flow time, tardiness and lateness are to be calculated and compared.
Concept Introduction:The process of planning the ordering of the activities involves based on the elements such as, priority, set up time and such other is referred to as sequencing.
A

Answer to Problem 10PA
After necessary calculations, it can be seen that the average flow time is 25, lateness is 9.5, and tardiness is 11.25.
Explanation of Solution
Under the given order rule:
Job | Processing Time | Flow Time | Due Date | Lateness | Tardiness |
1 | 7 | 7 | 21 | -14 | 0 |
2 | 3 | 10 | 7 | 3 | 3 |
3 | 5 | 15 | 8 | 7 | 7 |
4 | 2 | 17 | 5 | 12 | 12 |
5 | 6 | 23 | 17 | 6 | 6 |
6 | 9 | 32 | 16 | 16 | 16 |
7 | 14 | 46 | 38 | 8 | 8 |
8 | 4 | 50 | 12 | 38 | 38 |
Average | 25.00 | 9.50 | 11.25 |
Average Flow Time will be;
The average lateness will be;
The average tardiness will be;
B
Interpretation: the shortest processing time is to be calculated.
Concept Introduction: The process of planning the ordering of the activities involves based on the elements such as, priority, set up time and such other is referred to as sequencing.
The process of
B

Explanation of Solution
Job | 4 | 2 | 8 | 3 | 5 | 1 | 6 | 7 |
Job | Processing Time | Flow Time | Due Date | Lateness | Tardiness |
4 | 2 | 2 | 5 | -3 | 0 |
2 | 3 | 5 | 7 | -2 | 0 |
8 | 4 | 9 | 12 | -3 | 0 |
3 | 5 | 14 | 8 | 6 | 6 |
5 | 6 | 20 | 17 | 3 | 3 |
1 | 7 | 27 | 21 | 6 | 6 |
6 | 9 | 36 | 16 | 20 | 20 |
7 | 14 | 50 | 38 | 12 | 12 |
Average | 20.38 | 4.88 | 5.88 |
C
Interpretation: The earliest due date is to be derived.
Concept Introduction: The process of planning the ordering of the activities involves based on the elements such as, priority, set up time and such other is referred to as sequencing.
C

Explanation of Solution
Job | 4 | 2 | 3 | 8 | 6 | 5 | 1 | 7 |
Job | Processing Time | Flow Time | Due Date | Lateness | Tardiness |
4 | 2 | 2 | 5 | -3 | 0 |
2 | 3 | 5 | 7 | -2 | 0 |
3 | 5 | 10 | 8 | 2 | 2 |
8 | 4 | 14 | 12 | 2 | 2 |
6 | 9 | 23 | 16 | 7 | 7 |
5 | 6 | 29 | 17 | 12 | 12 |
1 | 7 | 36 | 21 | 15 | 15 |
7 | 14 | 50 | 38 | 12 | 12 |
Average | 21.13 | 5.63 | 6.25 |
Below is the required comparison of the derived solutions:
Average Flow Time | Average Lateness | Average Tardiness | |
FCFS | 25.00 | 9.50 | 11.25 |
SPT | 20.38 | 4.88 | 5.88 |
EDD | 21.13 | 5.63 | 6.25 |
Want to see more full solutions like this?
Chapter 14 Solutions
OM (with OM Online, 1 term (6 months) Printed Access Card)
- How does wellness reflect and impact the past and the future of our health as a workout routine? What are the obstacles during the workout routine, and how do you overcome the obstacles? What are the best solutions to plan and accomplish the wellness?arrow_forwardMy last question! Thank you all for helping me better understand how OM works. If you can assist me for this one I'd be very thankful. Can you explain it step by step?I know now that LS is late start, and ES is early start. - •Activities on the critical path are? •The total project completion time for Rafay Ishfaq's software firm is how many weeks?•Determine the slack time for each of the activities for A-F •What is the total slack for the non critical paths in Rafays project?arrow_forwardThank you so much! I was able to answer C without help! Can you assist me with slack time for A-F? I believe A=0arrow_forward
- There's 8 parts, but I need some help with them. I always get confused on which is most critical of a patharrow_forwardMenu Item Sales and Cost Data Taco Salad: Number Sold: 127; Item Cost: $0.71; Selling Price: $3.25 Lasagna: Number Sold: 48; Item Cost: $0.92; Selling Price: $4.67 Chicken: Number Sold: 31; Item Cost: $1.20; Selling Price: $3.00 Green Beans: Number Sold: 14; Item Cost: $0.20; Selling Price: $1.00 Corn: Number Sold: 13; Item Cost: $0.24; Selling Price: $1.00 Rice: Number Sold: 9;Item Cost: $0.13; Selling Price: $1.00 Menu Item Classification: Low contribution margin, low menu mix % DOG High contribution margin, low menu mix % PUZZLE Low contribution margin, high menu mix % PLOWHORSE High contribution margin, high menu mix o/o STAR QUESTION 1 Complete the menu analyses worksheet below. Calculations will be done using the information above. Restaurant: Date: MealPeriod: (A) ☐ (B) (C) (D) (E) (F) (G) (H) (1) (J) Menu Mix Popularity % Item Item Sold/(Menu Mix Menu Menu Item Food Menu Contribution Contribution Contribution Category Item Mix %): (B/K) Cost Selling Margin Price Margin (E-D)…arrow_forward1) Around the Clock Production of Fire Nozzles View the videos Around the Clock Production of Fire Nozzles 1 https://media.gaspar.mheducation.com/GASPARPlayer/play.html?id=132KoZwS0yMEgsToDUsZjJe (9.44 minutes, Ctrl+Click on the link) and Around the Clock Production of Fire Nozzles 2 https://media.gaspar.mheducation.com/GASPARPlayer/play.html?id=44JM0cKtFLqHP5bad6KOHAm (7.43 minutes, Ctrl+Click on the link); what are your key takeaways (tie to one or more of the topics discussed in Chapters 12 and/or 13) after watching these videos. Note: As a rough guideline, please try to keep the written submission to one or two paragraphs. 2) Cyberdyne Systems stocks and sells Cyberdyne glucose meters. The firm gathered the following information from its South Pasadena office: Demand = 19,500 units per year Ordering cost = $25 per order Holding cost = $4 per unit per year The firm’s operations manager wants to calculate the: a) EOQ for the glucose meters. b) Annual holding costs for the…arrow_forward
- In the following problems assume, unless otherwise stated, that S = $40, σ = 30%, r =8%,and δ =0. 13.1 Suppose you sell a 45-strike call with 91 days to expiration. What is delta? If the option is on 100 shares, what investment is required for a delta-hedged portfolio? What is your overnight profit if the stock tomorrow is $39? What if the stock price is $40.50?arrow_forwardQuestion 1 M&H company ltd. sells television sets and has collected monthly sales data (in units) for the past 12 months as shown in table 1below: TABLE 1 Month Sales (Units) 1 120 2 135 3 150 4 165 5 180 6 200 7 195 8 210 9 225 10 240 11 255 12 270 Using the data provided, answer the following questions: a. Using a 3-month weighted moving average with weights 0.5, 0.3, and 0.2 (most recent month having the highest weight), calculate the forecast for month 13. [2 marks] b. If the company applies an exponential smoothing method with a smoothing constant (a) = 02, and assumes an initial forecast of 120 units for Month 1, calculate the forecast for month 13. [6 marks] c. Calculate the Mean Absolute Deviation (MAD) for the exponential smoothing method and weighted moving average method using the actual sales data for Months 4 to 12 and determine which method is more accurate. [8 marks] d. Compute the values of a (intercept) and b (slope) using the least squares method. [7 marks] e. Use the…arrow_forwardQuestion 4 MGM12026 Production and Operations Management semester il 2024 A company operates a manufacturing plant that produces two products, A and B. The plant has the following capacity data: . . Design Capacity: 15,000 machine hours per month Effective Capacity: 12,000 machine hours per month Actual Output (Utilized Capacity): 10,000 machine hours per month Additionally, the plant produces Product A and Product B, with the following production data: Product Demand (Units) Processing Time Contribution Margin ($ (hours per unit) per unit) A 3,000 2.5 40 B 4,000 1.5 30 a. Calculate the plant's i. Capacity Utilization [3 marks] ii. Effective Capacity Utilization [3 marks] iii. Efficiency. Interpret the results. [3 marks] b. Compute the total machine hours required to meet full demand for both products. [5 marks] c. Determine whether the plant has sufficient capacity to meet full demand. If not, calculate the shortfall in machine hours. [3 marks] d. Using the contribution margin per…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing