Question
Chapter 14, Problem 12PA
Summary Introduction
Interpretation:A minimum make span scheduleis to be developed by applying the J’s rule.
Concept Introduction:The time required to process a given set of jobs is referred to as the makespan.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The following 5 overhaul jobs are waiting to be processed at Avianic's Engine Repair Inc. These jobs were logged
as they arrived. All dates are specified as planning calendar days.
Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.)
Job
CR
Job
Due Date
Duration (days)
103
103
214
10
205
205
223
309
309
217
11
412
219
412
517
216
15
517
Assume that all jobs arrived on day 180; today's date is 200.
The following jobs are waiting to be processed atJeremy LaMontagne’s machine center. Today is day 250.
Using the critical ratio scheduling rule, in what sequencewould the jobs be processed?
Five customers brought in computers to be repaired to a small shop. Estimated repair times (in days) and dates promised are given below. Due dates were set based on available technicians; however, one technician had a medical emergency and will be
unavailable for at least two weeks so processing times were adjusted.
Customer job 1
Processing time
(days)
Due date (days)
6
Use the EDD rule and compute the start time, flow time, lateness, and tardiness for each job. Use minus sign to enter negative lateness values, if any. If your answer is zero, enter "0".
Sequence Start Time, days Flow Time, days Lateness, days
Tardiness, days
-Select-
-Select-
-Sclect.
-Select-
-Select-
UI
5
LI
TE
10
MA
Chapter 14 Solutions
OM (with OM Online, 1 term (6 months) Printed Access Card)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The following jobs are waiting to be processed at Jeremy LaMontagne's machine center. Today is day 250. Using the critical ratio scheduling rule, in what sequence would the jobs be processed?arrow_forwardThe Security Life Insurance Company processes all new life insurance policies through three departments: incoming mail (I), underwriting (U), and policy control (P). Theincoming mail department receives applications and customer payments and then routes the files to the underwriting department. After checking on the applicants’qualifications for life insurance, the underwriting department forwards the file to policy control for the issue of the policy. At the present time, the company has five new policy applications waiting to be processed. The time required for processing in each department is shown below. Policy Department/Hours 1 I/3, U/6, P/8 2 I/2, P/10 3 I/1, U/3, P/4 4 I/2, U/8, P/6 5 I/1, P/6a. Prepare a Gantt chart schedule for these policies.arrow_forwardJack's Refrigeration Repair Service repairs and reconditions commercial icemakers at restaurants. Jack has four jobs to complete. Below are their processing times and due dates: Job Processing time (hours) Due date (hour) A 20 50 B 10 40 C 15 35 D 55 75 What is the average inventory if jobs are processed using the earliest due date rule?arrow_forward
- The following jobs are waiting to be processed atJulie Morel’s machine center: In what sequence would the jobs be ranked according to thefollowing rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT?All dates are according to shop calendar days. Today on theplanning calendar is day 130, and none of the jobs have beenstarted or scheduled. Which rule is best?arrow_forwardThe first five columns of the following table contain information about a set of four jobs that just arrived (end of Hour 0 or beginning of Hour 1) at an engine lathe. They are the only ones now waiting to be processed. Several operations, including the one at the engine lathe, remain to be done on each job. Determine the schedule by using (a) the CR rule and (b) the S/RO rule. Compare these schedules to those generated by FCFS, SPT, and EDD. Job ProcessingTime at EngineLathe (hours) TimeRemainingUntil Due Date(days) Number ofOperationsRemaining Shop TimeRemaining(days) CR S/RO 1 2 3 4 2.3 10.5 6.2 15.6 15 10 20 8 10 2 12 5 6.1 7.8 14.5 10.2 2.46 1.28 1.38 0.78 0.89 1.10 0.46 -0.44arrow_forwardThe following jobs are waiting to be processed at Rick Solano’s machine center. Solano’s machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241 (day 241 is a workday). Job names refer to names of clients and contract numbers. Job Date job received Productiondays needed Date job due BR-02 228 15 300 CX-01 225 25 270 DE-06 230 35 320 RG-05 235 40 360 SY-11 231 30 310 a. Complete the following table. (Show your supporting calculations.) b.Which dispatching rule has the best score for flow time? c. Which dispatching rule would you select? Support your decision.arrow_forward
- Hi, I need help solving this Operations Mgmt. problem. Thanks!arrow_forwardThe following jobs are waiting to be processed at JulieMorel’s machine center:JOB DATE ORDER RECEIVED PRODUCTIONDAYS NEEDED DATE ORDER DUEA 110 20 180B 120 30 200C 122 10 175D 125 16 230E 130 18 210 In what sequence would the jobs be ranked according to the fol-lowing rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT? All dates are according to shop calendar days. Today on the planning cal-endar is day 130, and none of the jobs have been started or sched-uled. Which rule is best?arrow_forwardThe following jobs are waiting to be processed at thesame machine center. Jobs are logged as they arrive:JOB DUE DATE DURATION (DAYS)A 313 8B 312 16C 325 40D 314 5E 314 3 In what sequence would the jobs be ranked according to the follow-ing decision rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT? All dates are specified as manufacturing planning calendar days. Assumethat all jobs arrive on day 275. Which decision is best and why?arrow_forward
- where the consulting company has five jobs in its backlog. Create a schedule usingthe EDD rule, calculating the average days past due and flow time. In this case, does EDD outperformthe FCFS rule?arrow_forwardThe following jobs are waiting to be processed at a small machine center: DUE DATE 250 242 250 260 265 JOB 10 20 30 40 50 DURATION (DAYS) 20 10 16 34 6 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 (yesterday) in the order shown but are not scheduled to begin until day 201 (today). a) Sequence the jobs according to LPT. According to the LPT rulle, the sequence of jobs should be b) What is the average completion (flow) time? The average completion (flow) time is c) What is the average job lateness? The average job lateness is d) What is the average number of jobs in the system? The average number of jobs in the system is jobs (round your response to one decimal place). days (round your response to one decimal place). days (round your response to ane decimal place).arrow_forwardChristine has three cars that must be overhauled by her ace mechanic, Megan. Given the following data about the cars, use least slack per remaining operation to determine Megan’s scheduling priority for each:Customer Pick-Up Remaining Overhaul Car Time (hours hence) Time (hours) Remaining Operation A 10 4 PaintingB 17 5 Wheel alignment, painting C 15 1 Chrome plating, painting, seat repairarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY