Concept explainers
A
Interpretation: The order in which the jobs have arrived, the average flow time, tardiness and lateness are to be calculated and compared.
Concept Introduction:The process of planning the ordering of the activities involves based on the elements such as, priority, set up time and such other is referred to as sequencing.
A
Answer to Problem 10PA
After necessary calculations, it can be seen that the average flow time is 25, lateness is 9.5, and tardiness is 11.25.
Explanation of Solution
Under the given order rule:
Job | Processing Time | Flow Time | Due Date | Lateness | Tardiness |
1 | 7 | 7 | 21 | -14 | 0 |
2 | 3 | 10 | 7 | 3 | 3 |
3 | 5 | 15 | 8 | 7 | 7 |
4 | 2 | 17 | 5 | 12 | 12 |
5 | 6 | 23 | 17 | 6 | 6 |
6 | 9 | 32 | 16 | 16 | 16 |
7 | 14 | 46 | 38 | 8 | 8 |
8 | 4 | 50 | 12 | 38 | 38 |
Average | 25.00 | 9.50 | 11.25 |
Average Flow Time will be;
The average lateness will be;
The average tardiness will be;
B
Interpretation: the shortest processing time is to be calculated.
Concept Introduction: The process of planning the ordering of the activities involves based on the elements such as, priority, set up time and such other is referred to as sequencing.
The process of
B
Explanation of Solution
Job | 4 | 2 | 8 | 3 | 5 | 1 | 6 | 7 |
Job | Processing Time | Flow Time | Due Date | Lateness | Tardiness |
4 | 2 | 2 | 5 | -3 | 0 |
2 | 3 | 5 | 7 | -2 | 0 |
8 | 4 | 9 | 12 | -3 | 0 |
3 | 5 | 14 | 8 | 6 | 6 |
5 | 6 | 20 | 17 | 3 | 3 |
1 | 7 | 27 | 21 | 6 | 6 |
6 | 9 | 36 | 16 | 20 | 20 |
7 | 14 | 50 | 38 | 12 | 12 |
Average | 20.38 | 4.88 | 5.88 |
C
Interpretation: The earliest due date is to be derived.
Concept Introduction: The process of planning the ordering of the activities involves based on the elements such as, priority, set up time and such other is referred to as sequencing.
C
Explanation of Solution
Job | 4 | 2 | 3 | 8 | 6 | 5 | 1 | 7 |
Job | Processing Time | Flow Time | Due Date | Lateness | Tardiness |
4 | 2 | 2 | 5 | -3 | 0 |
2 | 3 | 5 | 7 | -2 | 0 |
3 | 5 | 10 | 8 | 2 | 2 |
8 | 4 | 14 | 12 | 2 | 2 |
6 | 9 | 23 | 16 | 7 | 7 |
5 | 6 | 29 | 17 | 12 | 12 |
1 | 7 | 36 | 21 | 15 | 15 |
7 | 14 | 50 | 38 | 12 | 12 |
Average | 21.13 | 5.63 | 6.25 |
Below is the required comparison of the derived solutions:
Average Flow Time | Average Lateness | Average Tardiness | |
FCFS | 25.00 | 9.50 | 11.25 |
SPT | 20.38 | 4.88 | 5.88 |
EDD | 21.13 | 5.63 | 6.25 |
Want to see more full solutions like this?
- Consider the following process at a pharmacy.Customers drop off their prescriptions either in the drive-through counter or in the front counter of the pharmacy. Customers can request that their prescription be filled immediately. In this case, they have to wait between 15 minutes and one hour depending on the current workload. Most customers are not willing to wait that long, so they opt to nominate a pickup time at a later point during the day. Generally, customers drop their prescriptions in the morning before going to work (or at lunchtime) and they come back to pick up the drugs after work, typically between 5pm and 6pm. When dropping their prescription, a technician asks the customer for the pick-up time and puts the prescription in a box labelled with the hour preceding the pick-up time. For example, if the customer asks to have the prescription be ready at 5pm, the technician will drop it in the box with the label 4pm (there is one box for each hour of the day). Every hour, one…arrow_forwardConsider the following process at a pharmacy. Customers drop off their prescriptions either in the drive-through counter or in the front counter of the pharmacy. Customers can request that their prescription be filled immediately. In this case, they have to wait between 15 minutes and one hour depending on the current workload. Most customers are not willing to wait that long, so they opt to nominate a pickup time at a later point during the day. Generally, customers drop their prescriptions in the morning before going to work (or at lunchtime) and they come back to pick up the drugs after work, typically between 5pm and 6pm. When dropping their prescription, a technician asks the customer for the pick-up time and puts the prescription in a box labelled with the hour preceding the pick-up time. For example, if the customer asks to have the prescription be ready at 5pm, the technician will drop it in the box with the label 4pm (there is one box for each hour of the day). Every hour, one…arrow_forwardApply the four popular sequencing rules to the five jobs shown in the table below. For each sequence determine: The average completion time (sum of total flow time/number of jobs) Utilisation measure (Total job work time/Sum of total flow time) Average number of jobs in system (Sum of total flow time/Total job work time) Average job lateness (Total late days/Number of jobs) Job Due Job Work (Processing) Time Date (Days) (Days) 8 6 18 15 23 Job ABCDE 6 W ∞ NO 6 2 8 3 9arrow_forward
- The first five columns of the following table contain information about a set of four jobs that just arrived (end of Hour 0 or beginning of Hour 1) at an engine lathe. They are the only ones now waiting to be processed. Several operations, including the one at the engine lathe, remain to be done on each job. Determine the schedule by using (a) the CR rule and (b) the S/RO rule. Compare these schedules to those generated by FCFS, SPT, and EDD. Job ProcessingTime at EngineLathe (hours) TimeRemainingUntil Due Date(days) Number ofOperationsRemaining Shop TimeRemaining(days) CR S/RO 1 2 3 4 2.3 10.5 6.2 15.6 15 10 20 8 10 2 12 5 6.1 7.8 14.5 10.2 2.46 1.28 1.38 0.78 0.89 1.10 0.46 -0.44arrow_forwardAn insurance claims work area has five claims waiting for processing as follows: Job Processing Time Due Date (Di ) 1 18 31 2 14 25 3 12 23 4 19 24 5 10 37 Use the Excel Sequencing template to find the average flowtime, average and maximum tardiness, and average lateness for the following sequences: SPT sequence, EDD sequence, and the sequence 4-3-2-1-5. Round your answers for the average values to two decimal places. The SPT sequence is - - - - . Average Flow Time Average Tardiness Maximum Tardiness Average Lateness The EDD sequence is - - - - . Average Flow Time Average Tardiness Maximum Tardiness Average Lateness 4-3-2-1-5 sequence: Average Flow Time Average Tardiness Maximum Tardiness Average Lateness What sequencing rule do you recommend? The ___________ is recommended as it minimizes average flow time and number of jobs in system.arrow_forwardThe data for five tax analysis jobs waiting to be processed by Martha at T. R. Accounting Service has been collected in the Microsoft Excel Online file below. Open the spreadsheet and perform the required analysis to answer the questions below. Questions 1. Use the shortest-processing-time (SPT) sequencing rules to sequence the jobs. Compute the flow time, tardiness, and lateness for each job, and the average flow time, average tardiness, and average lateness for all jobs. Use minus sign to enter negative lateness values, if any. Round the average values to two decimal places. Sequence Job Processing Time Due Date Flow Time Lateness Tardiness 1 2 3 4 5 Average 2. Use the earliest-due-date (EDD) sequencing rules to sequence the jobs. Compute the flow time, tardiness, and lateness for each job, and the average flow time, average tardiness, and average lateness for all jobs. Use minus…arrow_forward
- The following jobs are waiting to be processed at Rick Solano’s machine center. Solano’s machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241 (day 241 is a workday). Job names refer to names of clients and contract numbers. Job Date job received Productiondays needed Date job due BR-02 228 15 300 CX-01 225 25 270 DE-06 230 35 320 RG-05 235 40 360 SY-11 231 30 310 a. Complete the following table. (Show your supporting calculations.) b.Which dispatching rule has the best score for flow time? c. Which dispatching rule would you select? Support your decision.arrow_forwardThe owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: Job processing time hrs due from now W 4 4 X 3 5 Y 2 2 Z 1 1 If he uses the earliest due date first priority rule to schedule these jobs, what will be the average job tardiness?arrow_forwardEight jobs have arrived in the following order: Job Processing Time Due Date 1 7 23 2 3 9 3 5 8 4 2 11 5 6 16 6 9 18 7 14 40 8 4 31 Find and compare the performance measures for the following sequencing rules using the Excel Sequencing template. Round your answers to two decimal places. Process in the order they have arrived Flow Time Lateness Tardiness Averagearrow_forward
- Consider the following process at a pharmacy. Customers drop off their prescriptions either in the drive-through counter or in the front counter of the pharmacy. Customers can request that their prescription be filled immediately. In this case, they must wait between 15 minutes and one hour depending on the current workload. Most customers are not willing to wait that long, so they opt to nominate a pick-up time at a later point during the day. Generally, customers drop their prescriptions in the morning before going to work (or at lunchtime) and they come back to pick up the drugs after work, typically between 5pm and 6pm. When dropping their prescription, a technician asks the customer for the pick-up time and puts the prescription in a box labelled with the hour preceding the pick-up time. For example, if the customer asks to have the prescription be ready at 5pm, the technician will drop it in the box with the label 4pm (there is one box for each hour of the day). Every hour, one…arrow_forwardConsider the following process at a pharmacy. Customers drop off their prescriptions either in the drive-through counter or in the front counter of the pharmacy. Customers can request that their prescription be filled immediately. In this case, they must wait between 15 minutes and one hour depending on the current workload. Most customers are not willing to wait that long, so they opt to nominate a pick-up time at a later point during the day. Generally, customers drop their prescriptions in the morning before going to work (or at lunchtime) and they come back to pick up the drugs after work, typically between 5pm and 6pm. When dropping their prescription, a technician asks the customer for the pick-up time and puts the prescription in a box labelled with the hour preceding the pick-up time. For example, if the customer asks to have the prescription be ready at 5pm, the technician will drop it in the box with the label 4pm (there is one box for each hour of the day). Every hour, one…arrow_forwardConsider the following process at a pharmacy. Customers drop off their prescriptions either in the drive-through counter or in the front counter of the pharmacy. Customers can request that their prescription be filled immediately. In this case, they must wait between 15 minutes and one hour depending on the current workload. Most customers are not willing to wait that long, so they opt to nominate a pick-up time at a later point during the day. Generally, customers drop their prescriptions in the morning before going to work (or at lunchtime) and they come back to pick up the drugs after work, typically between 5pm and 6pm. When dropping their prescription, a technician asks the customer for the pick-up time and puts the prescription in a box labelled with the hour preceding the pick-up time. For example, if the customer asks to have the prescription be ready at 5pm, the technician will drop it in the box with the label 4pm (there is one box for each hour of the day). Every hour, one…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.