Summary Introduction

Interpretation: Under the given scenario, the sequence that promises a minimized average lateness is to be derived.

Concept Introduction: The process of planning the ordering of the activities involves based on the elements such as, priority, set up time and such other is referred to as sequencing.

A

Expert Solution
Check Mark

Explanation of Solution

Under the given order rule:

    Job12345678
    JobProcessing TimeFlow TimeDue DateLatenessTardiness
    17721-140
    2310733
    3515877
    421751212
    56231766
    6932161616
    714463888
    8450123838
    Average25.009.5011.25

Average Flow Time will be;

  =7+10+15+17+23+32+46+508=2008=25.00

The average lateness will be;

  =14+3+7+12+6+16+8+388=768=9.50

The average tardiness will be;

  =0+3+7+12+6+16+8+388=908=11.25

Under the SPT rule:

    Job42835167
    JobProcessing TimeFlow TimeDue DateLatenessTardiness
    4225-30
    2357-20
    84912-30
    3514866
    56201733
    17272166
    6936162020
    71450381212
    Average20.384.885.88

Under the EDD rule:

    Job42386517
    JobProcessing TimeFlow TimeDue DateLatenessTardiness
    4225-30
    2357-20
    3510822
    84141222
    69231677
    5629171212
    1736211515
    71450381212
    Average21.135.636.25

The comparisons will be as follows:

    AFTALAT
    FCFS25.009.5011.25
    SPT20.384.885.88
    EDD21.135.636.25

Upon observing the above derived observations, it can be concluded that the sequence that minimizes the AL is EDD:

    42386517

B

Summary Introduction

Interpretation: Under the given scenario, the sequence that promises a minimized average tardiness is to be calculated.

Concept Introduction: The process of planning the ordering of the activities involves based on the elements such as, priority, set up time and such other is referred to as sequencing.

B

Expert Solution
Check Mark

Explanation of Solution

Upon observing the above derived observations, it can be concluded that the sequence that minimizes the AT is SPT:

    42835167

C

Summary Introduction

Interpretation: In a generalized manner, the logic is to be placed into a procedure that aids in accomplishing these objects for most of the time.

Concept Introduction: The process of planning the ordering of the activities involves based on the elements such as, priority, set up time and such other is referred to as sequencing.

C

Expert Solution
Check Mark

Explanation of Solution

The logic here is so simple. Supposing that the flow time need to be minimized then the SPT need to be implemented. The advantage of the SPT here is that it minimizes the average job flow time and WIP inventory and also thereby maximizes the resource allocation.

On the other hand, the EDD rule minimizes the average tardiness and lateness and in that it does the best job.

Once the data of processing time, the due date of the single machine are accomplished and the tardiness can easily be minimized, the firm does the best.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
her psychological test and interview while Ms. Domingo got a good score and good psychological result. Ms. Sabado’s father is your godfather and a good friend of yours. Ms. Sabado asked you a favor to consider her daughter and if possible she will be hired. He also added that every job can be learned through training and mentoring. The situation bothers you since it’s your duty to recommend to the higher authority whom to hire.Questions:1. As a supervisor how will you diced on this situation?2. It’s time to decide, who among the two (2) will be hired? Why?
Help me solve part C.
Boreki Enterprise has the following 10 items in inventory. Theodore Boreki asks you, a recent OM graduate, to divide these items into ABC classifications. Fill in the blanks and then answer the following questions. (Round dollar volume to the nearest whole number and percentage of dollar volume to two decimal places.) Dollar Item Annual Demand Cost/Unit Volume % of Total Dollar Volume A2 10 120 B8 4000 12 48,000 5.65 C7 1500 45 67,500 7.94 D1 2000 44 E9 1000 20 20,000 2.35 F3 25 40 G2 200 1500 300,000 35.29 H2 600 20 12,000 1.41 15 1000 300 J8 2500 5 12,500 1.47
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,