Dwayne Cole, owner of a Florida firm that manufactures display cabinets, develops an 8-month aggregate plan. Demand and capacity (in units) are
The cost of producing each unit is $1,000 on regular time, $1,300 on overtime, and $1,800 on a subcontract. Inventory carrying cost is $200 per unit per month. There is no beginning or ending inventory in stock, and no backorders are permitted from period to period.
Let the production (workforce) vary by using regular time first, then overtime, and then subcontracting.
a) Set up a production plan that minimizes cost by producing exactly what the demand is each month. This plan allows no backorders or inventory. What is this plan’s cost?
b) Through better planning, regular time production can be set at exactly the same amount, 275 units, per month. If demand cannot be met there is no cost assigned to shortages and they will not be filled. Does this alter the solution?
c) If overtime costs per unit rise from $1,300 to $1,400, will your answer to (a) change? What if overtime costs then fall to $1,200?
a)
To determine: The total cost of the plan.
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Answer to Problem 19P
The total cost of the plan is $2,608,300.
Explanation of Solution
Given information:
Regular time cost per unit is given as $1,000, overtime cost is $1,300, and subcontract cost is $1,800 per unit. The capacity and demand are given as follows:
Month | Demand | Regular time capacity | Overtime capacity | Subcontract capacity |
Initial | 0 | 0 | 0 | 0 |
January | 255 | 235 | 20 | 12 |
February | 294 | 255 | 24 | 16 |
March | 321 | 290 | 26 | 15 |
April | 301 | 300 | 24 | 17 |
May | 330 | 300 | 30 | 17 |
June | 320 | 290 | 28 | 19 |
July | 345 | 300 | 30 | 19 |
August | 340 | 290 | 30 | 20 |
Calculate the total cost:
Table 1
Working note:
Demand, regular time capacity, overtime capacity, and subcontract capacity are given.
Determine regular time, overtime, and subcontract units for the month of January:
It is given that the demand for the month of January is 255 units. 235 units would be produced in the regular time (as the regular time capacity is 235). Remaining 20 units would be produced in the overtime (as the overtime capacity is 20). Hence, regular time unit is 235 units and overtime unit is 20 units.
Determine regular time, overtime, and subcontract units for the month of February:
It is given that the demand for the month of February is 294 units. 255 units would be produced in the regular time (as the regular time capacity is 255). From the remaining 39 units, 24 units would be produced in the overtime (as the overtime capacity is 24) and 15 units would be produced using subcontract (as the subcontract capacity is 16). Hence, regular time unit is 255 units, overtime unit is 24 units, and subcontract unit is 15 units.
Determine regular time, overtime, and subcontract units for the month of March:
It is given that the demand for the month of March is 321 units. 290 units would be produced in the regular time (as the regular time capacity is 290). From the remaining 31 units, 26 units would be produced in the overtime (as the overtime capacity is 26) and 5 units would be produced using subcontract (as the subcontract capacity is 15). Hence, regular time unit is 290 units, overtime unit is 26 units, and subcontract unit is 5 units.
Note: The procedure continues for all months.
Increase or decrease for the month of January:
There would be no increase or decrease for the month of January as there is no period compare.
Increase or decrease for the month of February:
Production in the month of January is 235 units and production in the month of February is 255 units. There is an increase of 20 units. Hence, there would be 20 units increase in February.
Increase or decrease for the month of March:
Production in the month of February is 255 units and production in the month of March is 290 units. There is an increase of 35 units. Hence, there would be 35 units increase in March.
Increase or decrease for the month of April:
Production in the month of March is 290 units and production in the month of April is 300 units. There is an increase of 10 units. Hence, there would be 10 units increase in April.
Increase or decrease for the month of May:
Production in the month of April is 300 units and production in the month of May is 300 units. As there is no change in the production units, there would not be any increase or decrease.
Increase or decrease for the month of June:
Production in the month of May is 300 units and production in the month of June is 290 units. There is a decrease of 10 units. Hence, there would be 10 units decrease in June.
Increase or decrease for the month of July:
Production in the month of June is 290 units and production in the month of July is 300 units. There is an increase of 10 units. Hence, there would be 10 units increase in July.
Increase or decrease for the month of August:
Production in the month of July is 300 units and production in the month of August is 290 units. There is a decrease of 10 units. Hence, there would be 10 units decrease in August.
Summary of the table:
Type | Units | Cost |
Regular time | 2,260 | $2,260,000 |
Overtime | 189 | $245,700 |
Subcontract | 57 | $102,600 |
Holding | 0 | 0 |
Shortage | 0 | 0 |
Increase | 75 | 0 |
Decrease | 20 | 0 |
$2,608,300 |
Table 2
Working note:
Total units of regular time, overtime, subcontract, shortage, holding, increase, and decrease were calculated in theTable 1.
Calculate the regular time cost:
Regular time cost is calculated by multiplying regular time unit and the given regular time cost per unit. Hence, the regular time cost is $2,260,000.
Calculate the overtime cost:
Overtime cost is calculated by multiplying overtime unit and the given overtime cost per unit. Hence, the overtime cost is $245,700.
Calculate the subcontract cost:
Subcontract cost is calculated by multiplying subcontract unit and the given subcontract cost per unit. Hence, the subcontract cost is $102,600.
Calculate the increase and decrease cost:
As there is no increase or decrease cost per unit, it would remain 0.
Calculate the total cost:
Total cost is calculated by adding regular time cost, overtime cost, subcontract cost, holding cost, shortage cost, increase cost, and decrease cost.
Hence, the total cost of the plan is $2,608,300.
b)
To determine: The total cost of the plan.
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Answer to Problem 19P
The total cost of the plan is $2,585,100.
Explanation of Solution
Given information:
Regular time cost per unit is given as $1,000, overtime cost is $1,300, and subcontract cost is $1,800 per unit. The capacity and demand are given as follows:
Month | Demand | Regular time capacity | Overtime capacity | Subcontract capacity |
Initial | 0 | 0 | 0 | 0 |
January | 255 | 275 | 20 | 12 |
February | 294 | 275 | 24 | 16 |
March | 321 | 275 | 26 | 15 |
April | 301 | 275 | 24 | 17 |
May | 330 | 275 | 30 | 17 |
June | 320 | 275 | 28 | 19 |
July | 345 | 275 | 30 | 19 |
August | 340 | 275 | 30 | 20 |
Calculate the total cost:
Table 3
Working note:
Demand, regular time capacity, overtime capacity, and subcontract capacity are given.
Determine regular time, overtime, and subcontract units for the month of January:
It is given that the demand for the month of January is 255 units. Whole 255 units would be produced in the regular time (as the regular time capacity is 275). Hence, regular time unit is 255 units.
Determine regular time, overtime, and subcontract units for the month of February:
It is given that the demand for the month of February is 294 units. 275 units would be produced in the regular time (as the regular time capacity is 275). Remaining 19 units would be produced in the overtime (as the overtime capacity is 24). Hence, regular time unit is 275 units and overtime unit is 19 units.
Determine regular time, overtime, and subcontract units for the month of March:
It is given that the demand for the month of March is 321 units. 275 units would be produced in the regular time (as the regular time capacity is 290). From the remaining 46 units, 26 units would be produced in the overtime (as the overtime capacity is 26) and 15 units would be produced using subcontract (as the subcontract capacity is 15). Hence, regular time unit is 275 units, overtime unit is 26 units, and subcontract unit is 15 units. Remaining 5 units is a shortage.
Note: The procedure continues for all months.
Increase or decrease for the month of January:
There would be no increase or decrease for the month of January as there is no period compare.
Increase or decrease for the month of February:
Production in the month of January is 255 units and production in the month of February is 275 units. There is an increase of 20 units. Hence, there would be 20 units increase in February.
Increase or decrease from the month of March to August:
As the production for regular time remains the same, there would be no increase or decrease from the month of March to August.
Summary of the table:
Type | Units | Cost |
Regular time | 2,180 | $2,180,000 |
Overtime | 187 | $243,100 |
Subcontract | 90 | $162,000 |
Holding | 0 | 0 |
Shortage | 49 | 0 |
Increase | 20 | 0 |
Decrease | 0 | |
$2,585,100 |
Table 4
Working note:
Total units of regular time, overtime, subcontract, shortage, holding, increase, and decrease were calculated in theTable 3.
Calculate the regular time cost:
Regular time cost is calculated by multiplying regular time unit and the given regular time cost per unit. Hence, the regular time cost is $2,180,000.
Calculate the overtime cost:
Overtime cost is calculated by multiplying overtime unit and the given overtime cost per unit. Hence, the overtime cost is $243,100.
Calculate the subcontract cost:
Subcontract cost is calculated by multiplying subcontract unit and the given subcontract cost per unit. Hence, the subcontract cost is $162,000.
Calculate the increase and decrease cost:
As there is no increase or decrease cost per unit, it would remain 0.
Calculate the total cost:
Total cost is calculated by adding regular time cost, overtime cost, subcontract cost, holding cost, shortage cost, increase cost, and decrease cost.
Hence, the total cost of the plan is $2,585,100.
c)
To determine: The total cost of the plan, if the overtime increased to $1,400.
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Answer to Problem 19P
The total cost of the plan is $2,627,200.
Explanation of Solution
Given information:
Regular time cost per unit is given as $1,000, overtime cost is $1,400, and subcontract cost is $1,800 per unit. The capacity and demand are given as follows:
Month | Demand | Regular time capacity | Overtime capacity | Subcontract capacity |
Initial | 0 | 0 | 0 | 0 |
January | 255 | 235 | 20 | 12 |
February | 294 | 255 | 24 | 16 |
March | 321 | 290 | 26 | 15 |
April | 301 | 300 | 24 | 17 |
May | 330 | 300 | 30 | 17 |
June | 320 | 290 | 28 | 19 |
July | 345 | 300 | 30 | 19 |
August | 340 | 290 | 30 | 20 |
Calculate the total cost:
Table 5
Working note:
Demand, regular time capacity, overtime capacity, and subcontract capacity are given.
Determine regular time, overtime, and subcontract units for the month of January:
It is given that the demand for the month of January is 255 units. 235 units would be produced in the regular time (as the regular time capacity is 235). Remaining 20 units would be produced in the overtime (as the overtime capacity is 20). Hence, regular time unit is 235 units and overtime unit is 20 units.
Determine regular time, overtime, and subcontract units for the month of February:
It is given that the demand for the month of February is 294 units. 255 units would be produced in the regular time (as the regular time capacity is 255). From the remaining 39 units, 24 units would be produced in the overtime (as the overtime capacity is 24) and 15 units would be produced using subcontract (as the subcontract capacity is 16). Hence, regular time unit is 255 units, overtime unit is 24 units, and subcontract unit is 15 units.
Determine regular time, overtime, and subcontract units for the month of March:
It is given that the demand for the month of March is 321 units. 290 units would be produced in the regular time (as the regular time capacity is 290). From the remaining 31 units, 26 units would be produced in the overtime (as the overtime capacity is 26) and 5 units would be produced using subcontract (as the subcontract capacity is 15). Hence, regular time unit is 290 units, overtime unit is 26 units, and subcontract unit is 5 units.
Note: The procedure continues for all months.
Increase or decrease for the month of January:
There would be no increase or decrease for the month of January as there is no period compare.
Increase or decrease for the month of February:
Production in the month of January is 235 units and production in the month of February is 255 units. There is an increase of 20 units. Hence, there would be 20 units increase in February.
Increase or decrease for the month of March:
Production in the month of February is 255 units and production in the month of March is 290 units. There is an increase of 35 units. Hence, there would be 35 units increase in March.
Increase or decrease for the month of April:
Production in the month of March is 290 units and production in the month of April is 300 units. There is an increase of 10 units. Hence, there would be 10 units increase in April.
Increase or decrease for the month of May:
Production in the month of April is 300 units and production in the month of May is 300 units. As there is no change in the production units, there would not be any increase or decrease.
Increase or decrease for the month of June:
Production in the month of May is 300 units and production in the month of June is 290 units. There is a decrease of 10 units. Hence, there would be 10 units decrease in June.
Increase or decrease for the month of July:
Production in the month of June is 290 units and production in the month of July is 300 units. There is an increase of 10 units. Hence, there would be 10 units increase in July.
Increase or decrease for the month of August:
Production in the month of July is 300 units and production in the month of August is 290 units. There is a decrease of 10 units. Hence, there would be 10 units decrease in August.
Calculate the total cost if the overtime cost per unit increased to $1,400:
Type | Units | Cost |
Regular time | 2,260 | $2,260,000 |
Overtime | 189 | $264,600 |
Subcontract | 57 | $102,600 |
Holding | 0 | 0 |
Shortage | 0 | 0 |
Increase | 75 | 0 |
Decrease | 20 | 0 |
$2,627,200 |
Table 6
Working note:
Total units of regular time, overtime, subcontract, shortage, holding, increase, and decrease were calculated in theTable 5.
Calculate the regular time cost:
Regular time cost is calculated by multiplying regular time unit and the given regular time cost per unit. Hence, the regular time cost is $2,260,000.
Calculate the overtime cost:
Overtime cost is calculated by multiplying overtime unit and the given overtime cost per unit. Hence, the overtime cost is $264,600.
Calculate the subcontract cost:
Subcontract cost is calculated by multiplying subcontract unit and the given subcontract cost per unit. Hence, the subcontract cost is $102,600.
Calculate the increase and decrease cost:
As there is no increase or decrease cost per unit, it would remain 0.
Calculate the total cost:
Total cost is calculated by adding regular time cost, overtime cost, subcontract cost, holding cost, shortage cost, increase cost, and decrease cost.
Hence, the total cost of the plan is $2,627,200.
Calculate the total cost if the overtime cost per unit increased to $1,200:
Type | Units | Cost |
Regular time | 2,260 | $2,260,000 |
Overtime | 189 | $226,800 |
Subcontract | 57 | $102,600 |
Holding | 0 | 0 |
Shortage | 0 | 0 |
Increase | 75 | 0 |
Decrease | 20 | 0 |
$2,589,400 |
Table 7
Working note:
Total units of regular time, overtime, subcontract, shortage, holding, increase, and decrease were calculated in theTable 6.
Calculate the regular time cost:
Regular time cost is calculated by multiplying regular time unit and the given regular time cost per unit. Hence, the regular time cost is $2,260,000.
Calculate the overtime cost:
Overtime cost is calculated by multiplying overtime unit and the given overtime cost per unit. Hence, the overtime cost is $264,600.
Calculate the subcontract cost:
Subcontract cost is calculated by multiplying subcontract unit and the given subcontract cost per unit. Hence, the subcontract cost is $102,600.
Calculate the increase and decrease cost:
As there is no increase or decrease cost per unit, it would remain 0.
Calculate the total cost:
Total cost is calculated by adding regular time cost, overtime cost, subcontract cost, holding cost, shortage cost, increase cost, and decrease cost.
Hence, the total cost of the plan is $2,589,400.
Want to see more full solutions like this?
Chapter 13 Solutions
Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)
- Scenario 3 Ben Gibson, the purchasing manager at Coastal Products, was reviewing purchasing expenditures for packaging materials with Jeff Joyner. Ben was particularly disturbed about the amount spent on corrugated boxes purchased from Southeastern Corrugated. Ben said, I dont like the salesman from that company. He comes around here acting like he owns the place. He loves to tell us about his fancy car, house, and vacations. It seems to me he must be making too much money off of us! Jeff responded that he heard Southeastern Corrugated was going to ask for a price increase to cover the rising costs of raw material paper stock. Jeff further stated that Southeastern would probably ask for more than what was justified simply from rising paper stock costs. After the meeting, Ben decided he had heard enough. After all, he prided himself on being a results-oriented manager. There was no way he was going to allow that salesman to keep taking advantage of Coastal Products. Ben called Jeff and told him it was time to rebid the corrugated contract before Southeastern came in with a price increase request. Who did Jeff know that might be interested in the business? Jeff replied he had several companies in mind to include in the bidding process. These companies would surely come in at a lower price, partly because they used lower-grade boxes that would probably work well enough in Coastal Products process. Jeff also explained that these suppliers were not serious contenders for the business. Their purpose was to create competition with the bids. Ben told Jeff to make sure that Southeastern was well aware that these new suppliers were bidding on the contract. He also said to make sure the suppliers knew that price was going to be the determining factor in this quote, because he considered corrugated boxes to be a standard industry item. Is Ben Gibson acting legally? Is he acting ethically? Why or why not?arrow_forwardScenario 3 Ben Gibson, the purchasing manager at Coastal Products, was reviewing purchasing expenditures for packaging materials with Jeff Joyner. Ben was particularly disturbed about the amount spent on corrugated boxes purchased from Southeastern Corrugated. Ben said, I dont like the salesman from that company. He comes around here acting like he owns the place. He loves to tell us about his fancy car, house, and vacations. It seems to me he must be making too much money off of us! Jeff responded that he heard Southeastern Corrugated was going to ask for a price increase to cover the rising costs of raw material paper stock. Jeff further stated that Southeastern would probably ask for more than what was justified simply from rising paper stock costs. After the meeting, Ben decided he had heard enough. After all, he prided himself on being a results-oriented manager. There was no way he was going to allow that salesman to keep taking advantage of Coastal Products. Ben called Jeff and told him it was time to rebid the corrugated contract before Southeastern came in with a price increase request. Who did Jeff know that might be interested in the business? Jeff replied he had several companies in mind to include in the bidding process. These companies would surely come in at a lower price, partly because they used lower-grade boxes that would probably work well enough in Coastal Products process. Jeff also explained that these suppliers were not serious contenders for the business. Their purpose was to create competition with the bids. Ben told Jeff to make sure that Southeastern was well aware that these new suppliers were bidding on the contract. He also said to make sure the suppliers knew that price was going to be the determining factor in this quote, because he considered corrugated boxes to be a standard industry item. As the Marketing Manager for Southeastern Corrugated, what would you do upon receiving the request for quotation from Coastal Products?arrow_forwardThe president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: January 1,400 May 2,200 February 1,500 June 2,100 March 1,800 July 1,700 April 1,700 August 1,700 Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $125 per unit. Inventory holding cost is $25 per unit per month. Ignore any idle-time costs. The plan is called plan A. Plan A: Vary the workforce level to execute a strategy that produces the quantity demanded in the prior month. The December demand and rate of production are both 1,600 units per month. The cost of hiring additional workers is $55 per unit. The cost of laying off workers is $75 per unit. Evaluate this plan. (Enter all responses as whole питbers.) Note: Both hiring and layoff costs are incurred in the month of the change. For example, going from 1,600 in January to 1,400 in February incurs a cost of…arrow_forward
- The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: January 1,400 May 2,200 February 1,600 June 2,200 March 1,800 July 1,800 April 1,800 August 1,400 Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $100 per unit. Inventory holding cost is $20 per unit per month. Ignore any idle-time costs. The plan is called plan C. Plan C: Keep a stable workforce by maintaining a constant production rate equal to the average gross requirements excluding initial inventory and allow varying inventory levels. Conduct your analysis for January through August. Part 2 The average monthly demand requirement=17751775 units. (Enter your response as a whole number.) Part 3 In order to arrive at the costs, first compute the ending inventory and stockout units for each month…arrow_forwardThe president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: January 1,400 May 2,200 February 1,600 June 2,200 March 1,800 July 1,800 April 1,800 August 1,400 Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $100 per unit. Inventory holding cost is $20 per unit per month. Ignore any idle-time costs. The plan is called plan C. Plan C: Keep a stable workforce by maintaining a constant production rate equal to the average gross requirements excluding initial inventory and allow varying inventory levels. Conduct your analysis for January through August. Part 2 The average monthly demand requirement=1775 units. (Enter your response as a whole number.) Part 3 In order to arrive at the costs, first compute the ending inventory and stockout units for each month by…arrow_forwardThe president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: January 1,400 May 2,100 February 1,700 June 2,100 March April 1,800 1,900 July August 1,800 1,800 Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $125 per unit. Inventory holding cost is $25 per unit per month. Ignore any idle-time costs. The plan is called plan A. Plan A: Vary the workforce level to execute a strategy that produces the quantity demanded in the prior month. The December demand and rate of production are both 1,600 units per month. The cost of hiring additional workers is $50 per unit. The cost of laying off workers is $75 per unit. Evaluate this plan. (Enter all responses as whole numbers.) Note: Both hiring and layoff costs are incurred in the month of the change. For example, going from 1,600 in January to 1,400 in February incurs a cost of…arrow_forward
- The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: January 1,200 May 2,100 February 1,500 June 2,300 March April 1,600 1,900 July August 1,700 1,300 Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $100 per unit. Inventory holding cost is $20 per unit per month. Ignore any idle-time costs. The plan is called plan C. Plan C: Keep a stable workforce by maintaining a constant production rate equal to the average gross requirements excluding initial inventory and allow varying inventory levels. Conduct your analysis for January through August. The average monthly demand requirement = 1700 units. (Enter your response as a whole number.) In order to arrive at the costs, first compute the ending inventory and stockout units for each month by filling in the table below (enter your responses as whole numbers). Ending Period…arrow_forwardThe president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: January February March 1,600 1,700 1,800 April 1,700 Month 0 December 1 January 2 February 3 March Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $70 per unit. Inventory holding cost is $25 per unit per month. Ignore any idle-time costs. Evaluate the following plans D and E. 4 April 6 May 6 June Plan D: Keep the current workforce stable at producing 1,600 units per month. In addition to the regular production, another 20% of the normal production units can be produced in overtime at an additional cost of $55 per unit. A warehouse now constrains the maximum allowable inventory on hand to 600 units or less. Note: Do not produce in overtime if production or inventory are adequate to cover demand. 7 July 8 August Demand 1,500 1,700 1,800 1,700 2,100 2,100 1,800 1,500…arrow_forwardThe president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: May 1,500 1,700 1,700 June 1,700 January February March April Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $100 per unit. Inventory holding cost is $20 per unit per month. Ignore any idle-time costs. The plan is called plan C. Plan C: Keep a stable workforce by maintaining a constant production rate equal to the average gross requirements excluding initial inventory and allow varying inventory levels. Conduct your analysis for January through August. The average monthly demand requirement = 1800 units. (Enter your response as a whole number.) In order to arrive at the costs, first compute the ending inventory and stockout units for each month by filling in the table below (enter your responses as whole numbers). D₂₁ 0 December 1 January 2 February 3 March 4…arrow_forward
- The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: January 1,400 May 2,300 February 1,700 June 2,100 March 1,600 July 1,900 April 1,700 August 1,300 Her operations manager is considering a new plan, which begins in January with 200units on hand and ends with zero inventory. Stockout cost of lost sales is $125per unit. Inventory holding cost is $25per unit per month. Ignore any idle-time costs. The plan is called plan B. Plan B: Produce at a constant rate of 1,300units per month, which will meet minimum demands. Then use subcontracting, with additional units at a premium price of $75per unit. Subcontracting capacity is limited to 1,000units per month. Evaluate this plan by computing the costs for January through August. Part 2 In order to arrive at the costs, first compute the ending inventory and subcontracting units for each month by…arrow_forwardThe president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: 2,100 2,200 January February March April 5 6 Her operations manager is considering a new plan, which begins in January with 200 units on hand and ends with zero inventory Stockout cost of lost sales is $100 per unit. Inventory holding cost is $20 per unit per month. Ignore any idle-time costs. The plan is called plan B. Period Month Demand 0 December January 1 2 February 3 March 4 April May June 7 Plan B: Produce at a constant rate of 1,400 units per month, which will meet minimum demands. Then use subcontracting, with additional units at a premium price of $75 per unit. Subcontracting capacity is limited to 800 units per month. Evaluate this plan by computing the costs for January through August in order to arrive at the costs, first compute the ending inventory and subcontracting units for each month by filling in the table below (enter your responses as…arrow_forwardThe president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: Month 0 December 1 January 2 February 3 March 4 April 5 May 6 June January February March April 7 July 8 August Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $60 per unit. Inventory holding cost is $20 per unit per month. Ignore any idle-time costs. Evaluate the following plan. This exercise contains only Plan D. Plan D: Keep the current workforce stable at producing 1,600 units per month. In addition to the regular production, another 20% of the normal production units can be produced in overtime at an additional cost of $50 per unit. A warehouse now constrains the maximum allowable inventory on hand to 600 units or less. Note: Do not produce in overtime if production or inventory are adequate to cover demand. Demand 1,450 1,600 1,600 1,700 1,450 1,600 1,600…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning