
Concept explainers
a)
To evaluate: Plan D
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
a)

Answer to Problem 6P
Plan D has been evaluated. The total cost of plan D is $128,000.
Explanation of Solution
Given information:
The production for all the months is 1,600 units. Overtime cost is $50 per unit. The maximum allowable inventor in the warehouse is 400 units or less. The demand requirement from period 0 to 8 is as follows:
Period | Expected demand |
0 | 0 |
1 | 1,400 |
2 | 1,600 |
3 | 1,800 |
4 | 1,800 |
5 | 2,200 |
6 | 2,200 |
7 | 1,800 |
8 | 1,800 |
Evaluate the cost of the plan:
Plan D | ||||||
Period | Demand | Production | Overtime (units) | Ending inventory | Stock-outs (units) | Extra cost |
0 | 200 | |||||
1 | 1,400 | 1,600 | - | 400 | $8,000 | |
2 | 1,600 | 1,600 | - | 400 | $8,000 | |
3 | 1,800 | 1,600 | - | 200 | $4,000 | |
4 | 1,800 | 1,600 | - | - | $0 | |
5 | 2,200 | 1,600 | 320 | - | 280 | $44,000 |
6 | 2,200 | 1,600 | 320 | - | 280 | $44,000 |
7 | 1,800 | 1,600 | 200 | - | $10,000 | |
8 | 1,800 | 1,600 | 200 | - | $10,000 | |
Total | 14,600 | 1,040 | 1,000 | $128,000 |
Note: Production is given as 1,600 units. The ending inventory for December is given as 200 units. If the production is more than or equal to the demand, then there would be inventory. If the demand is more, then there would be stock out. Maximum overtime units allowed is 320 units (20% of production)
Calculate the ending inventory or stock-out for Period 1:
It is calculated by adding the production and ending inventory of the previous month and subtracting the result from the demand. The ending inventory for Period 1 is 400.
Calculate the ending inventory or stock-out for Period 2:
It is calculated by adding the production and ending inventory of the previous month and subtracting the result from the demand. The ending inventory for Period 2 is 400.
Calculate the ending inventory or stock-out for Period 3:
It is calculated by adding the production and ending inventory of the previous month and subtracting the result from the demand. The ending inventory for Period 3 is 200.
Calculate the ending inventory or stock-out for Period 4:
It is calculated by adding the production and ending inventory of the previous month and subtracting the result from the demand. The ending inventory for Period 4 is 0.
Calculate the ending inventory or stock-out for Period 5:
As the demand is more than the production, there would be a stock-out.
It is calculated by subtracting the production from the demand. The result should then be subtracted from the overtime units. Hence, the stock-out units for Period 5 is 280 units.
Calculate the ending inventory or stock-out for Period 6:
As the demand is more than the production, there would be a stock-out.
It is calculated by subtracting the production from the demand. The result should then be subtracted from the overtime units. Hence, the stock-out units for Period 6 is 280 units.
Calculate the ending inventory or stock-out for Period 7:
It is calculated by subtracting the production from the demand. The result should then be subtracted from the overtime units. Hence, the stock-out units for Period 7 is 0 units.
Note: Overtime units of 320 units would lead to a negative value. Hence, it was taken as 200 units.
Calculate the ending inventory or stock-out for Period 8:
It is calculated by subtracting the production from the demand. The result should then be subtracted from the overtime units. Hence, the stock-out units for Period 8 is 0 units.
Note: Overtime units of 320 units would lead to negative value. Hence, it was taken as 200 units.
Calculate the extra cost for Period 1:
It is calculated by multiplying the extra inventory units and inventory holding cost. The inventory holding cost is given as $20 per unit. Hence, the extra cost for period 1 is $8,000
Calculate the extra cost for Period 2:
It is calculated by multiplying the extra inventory units and inventory holding cost. Inventory holding cost is given as $20 per unit. Hence, the extra cost for period 2 is $8,000
Calculate the extra cost for Period 3:
It is calculated by multiplying the extra inventory units and inventory holding cost. Inventory holding cost is given as $20 per unit. Hence, the extra cost for period 3 is $4,000
Calculate the extra cost for Period 4:
As there are no overtime units, ending inventory units, or stock-out units, there would not be any extra costs.
Calculate the extra cost for Period 5:
It is calculated by adding the product of overtime units and inventory holding overtime cost per unit, and the product of stock-out units and stock-out cost per unit. Stock-out cost is given as $100 per unit and overtime cost is given as $50 per unit. Hence, the extra cost for period 5 is $44,000
Calculate the extra cost for Period 6:
It is calculated by adding the product of overtime units and inventory holding overtime cost per unit, and the product of stock-out units and stock-out cost per unit. Stock-out cost is given as $100 per unit and overtime cost is given as $50 per unit. Hence, the extra cost for period 6 is $44,000
Calculate the extra cost for Period 7:
It is calculated by adding the product of overtime units and inventory holding overtime cost per unit, and the product of stock-out units and stock-out cost per unit. Stock-out cost is given as $100 per unit and overtime cost is given as $50 per unit. Hence, the extra cost for period 7 is $10,000
Calculate the extra cost for Period 8:
It is calculated by adding the product of overtime units and inventory holding overtime cost per unit, and the product of stock-out units and stock-out cost per unit. Stock-out cost is given as $100 per unit and overtime cost is given as $50 per unit. Hence, the extra cost for period 8 is $10,000
Calculate the total cost of Plan D:
It is calculated by adding the extra costs of all the periods.
Hence, the total cost for Plan D is $128,000.
b)
To determine: Plan E
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
b)

Answer to Problem 6P
Plan E has been evaluated. The total cost of Plan E is $140,000.
Explanation of Solution
Given information:
Production for all the months is 1,600 units. Overtime cost is $50 per unit. Maximum allowable inventor in the warehouse is 400 units or less. Demand requirement from period 0 to 8 is as follows:
Period | Expected demand |
0 | 0 |
1 | 1,400 |
2 | 1,600 |
3 | 1,800 |
4 | 1,800 |
5 | 2,200 |
6 | 2,200 |
7 | 1,800 |
8 | 1,800 |
Evaluate the cost of the plan:
Plan E | |||||
Period | Demand | Production | Subcontract (units) | Ending inventory | Extra cost |
0 | 200 | ||||
1 | 1,400 | 1,600 | - | 400 | $8,000 |
2 | 1,600 | 1,600 | - | 400 | $8,000 |
3 | 1,800 | 1,600 | - | 200 | $4,000 |
4 | 1,800 | 1,600 | - | - | $0 |
5 | 2,200 | 1,600 | 600 | - | $45,000 |
6 | 2,200 | 1,600 | 600 | - | $45,000 |
7 | 1,800 | 1,600 | 200 | - | $15,000 |
8 | 1,800 | 1,600 | 200 | - | $15,000 |
Total | 14,600 | 1,600 | 1,000 | $140,000 |
Note: Production is given as 1,600 units. The ending inventory for December is given as 200 units. If the production is more than or equal to the demand, then there would be inventory. If the demand is more, then there would be subcontract.
Calculate the ending inventory or subcontract for Period 1:
It is calculated by adding the production and ending inventory of previous month and subtracting the demand from the result. The ending inventory for Period 1 is 400.
Calculate the ending inventory or subcontract for Period 2:
It is calculated by adding the production and ending inventory of previous month and subtracting the demand from the result. The ending inventory for Period 2 is 400.
Calculate the ending inventory or subcontract for Period 3:
It is calculated by adding the production and ending inventory of previous month and subtracting the demand from the result. The ending inventory for Period 3 is 200.
Calculate the ending inventory or subcontract for Period 4:
It is calculated by adding the production and ending inventory of previous month and subtracting the demand from the result. The ending inventory for Period 4 is 0.
Calculate the ending inventory or subcontract for Period 5:
As the demand is more than the production, there would be a subcontract.
It is calculated by subtracting the production from the demand. Hence, the subcontract units for Period 5 is 600 units.
Calculate the ending inventory or subcontract for Period 6:
As the demand is more than the production, there would be a subcontract.
It is calculated by subtracting the production from the demand. Hence, the subcontract units for Period 6 is 600 units.
Calculate the ending inventory or subcontract for Period 7:
It is calculated by subtracting the production from the demand. The result should then be subtracted from the overtime units. Hence, the subcontract units for Period 7 is 200 units.
Calculate the ending inventory or subcontract for Period 8:
It is calculated by subtracting the production from the demand. The result should then be subtracted from the overtime units. Hence, the subcontract units for Period 8 is 0 units.
Calculate the extra cost for Period 1:
It is calculated by multiplying the extra inventory units and inventory holding cost. Inventory holding cost is given as $20 per unit. Hence, the extra cost for period 1 is $8,000
Calculate the extra cost for Period 2:
It is calculated by multiplying the extra inventory units and inventory holding cost. Inventory holding cost is given as $20 per unit. Hence, the extra cost for period 2 is $8,000
Calculate the extra cost for Period 3:
It is calculated by multiplying the extra inventory units and inventory holding cost. Inventory holding cost is given as $20 per unit. Hence, the extra cost for period 3 is $4,000
Calculate the extra cost for Period 4:
As there are no overtime units, ending inventory units, and subcontract units, there would not be extra costs.
Calculate the extra cost for Period 5:
It is calculated by multiplying the subcontract units and subcontract cost per unit. Subcontract cost is given as $75 per unit. Hence, the extra cost for period 5 is $45,000
Calculate the extra cost for Period 6:
It is calculated by multiplying the subcontract units and subcontract cost per unit. Subcontract cost is given as $75 per unit. Hence, the extra cost for period 6 is $45,000
Calculate the extra cost for Period 7:
It is calculated by multiplying the subcontract units and subcontract cost per unit. Subcontract cost is given as $75 per unit. Hence, the extra cost for period 7 is $15,000
Calculate the extra cost for Period 8:
It is calculated by multiplying the subcontract units and subcontract cost per unit. Subcontract cost is given as $75 per unit. Hence, the extra cost for period 8 is $15,000
Calculate the total cost of Plan E:
It is calculated by adding the extra costs of all the periods.
Hence, the total cost for Plan E is $140,000.
The total cost for Plan D is preferable when compared with Plan E. However, Plan C, with the total cost of $86,000 is preferable over other plans.
Want to see more full solutions like this?
Chapter 13 Solutions
Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)
- Which of the following statements concerning the evaluation of training programs is true? Most companies thoroughly evaluate the return on investment of their training programs It is relatively easy to establish a control group and a treatment group for evaluation Results level of evaluation measures how well participants liked the program Behavior level criteria measure whether skills learned in training result in behavior changes back on the jobarrow_forwardEligibility testing is an disparate impact validation method none of the above a method to validate promotions and progressive discipline activity a test an employee administers to ensure that the potential employee is capable and qualified to perform the requirements of the positionarrow_forwardA no-strike pledge by a union in a collective bargaining agreement is given in return for management’s agreement to: a grievance procedure a union shop a wage increase a fringe benefit increase binding arbitration of grievancesarrow_forward
- Which is the major OD technique that is used for increasing the communication, cooperation, and cohesiveness of work units? Leadership analysis Developing objectives Groupthink Strategic Planning team Buildingarrow_forwardAn American multinational firm usually is less than fully successful in adapting itself to local practices in each country because: American managers are often ignorant of local conditions None of the above management direction may be centralized in the home office All of the above Foreign subsidiaries often have American managersarrow_forwardWhen salary increases are based on inputs, or performance, companies are following: agency theory equality theory equity theory compliance theory need theoryarrow_forward
- The most frequently used techniques for measuring job satisfaction involves Direct observation Questionnaires Interviews Psychological testsarrow_forwardWhich of the following is not an advantage of on-the-job training? Transfer is less difficult Transfer is less difficult The training is inexpensive Any organizational member can be the trainer without preparation It is relatively easy to use this methodarrow_forwardDiversimilarity is characterized by A systematic and dual emphasis and appreciation of both the differences and the similarities that members of an organization have Everyone is either the same or different Attempting to change the values of minority groups to make them conform with the views of the dominant group Emotional intelligence of everyone involvedarrow_forward
- Cultural environment includes all of the following components except: religious beliefs values/ideologies corporate structure education/human capitalarrow_forwardSearch firms _____________. All of the above place consultants onsite for their clients are outsourced to search and place full-time employees for their clients place contract employees for the clientsarrow_forwardWhich of the following accurately describe the functions of the NLRB: most cases are settled before they reach the board the five member board is required to make a ruling in all cases the board rules only in cases involving interpretation of the Constitution the five member board is required to make a ruling in most casesarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning
- Foundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning


