Concept explainers
a)
To evaluate: Plan D
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
a)
Answer to Problem 6P
Plan D has been evaluated. The total cost of plan D is $128,000.
Explanation of Solution
Given information:
The production for all the months is 1,600 units. Overtime cost is $50 per unit. The maximum allowable inventor in the warehouse is 400 units or less. The demand requirement from period 0 to 8 is as follows:
Period | Expected demand |
0 | 0 |
1 | 1,400 |
2 | 1,600 |
3 | 1,800 |
4 | 1,800 |
5 | 2,200 |
6 | 2,200 |
7 | 1,800 |
8 | 1,800 |
Evaluate the cost of the plan:
Plan D | ||||||
Period | Demand | Production | Overtime (units) | Ending inventory | Stock-outs (units) | Extra cost |
0 | 200 | |||||
1 | 1,400 | 1,600 | - | 400 | $8,000 | |
2 | 1,600 | 1,600 | - | 400 | $8,000 | |
3 | 1,800 | 1,600 | - | 200 | $4,000 | |
4 | 1,800 | 1,600 | - | - | $0 | |
5 | 2,200 | 1,600 | 320 | - | 280 | $44,000 |
6 | 2,200 | 1,600 | 320 | - | 280 | $44,000 |
7 | 1,800 | 1,600 | 200 | - | $10,000 | |
8 | 1,800 | 1,600 | 200 | - | $10,000 | |
Total | 14,600 | 1,040 | 1,000 | $128,000 |
Note: Production is given as 1,600 units. The ending inventory for December is given as 200 units. If the production is more than or equal to the demand, then there would be inventory. If the demand is more, then there would be stock out. Maximum overtime units allowed is 320 units (20% of production)
Calculate the ending inventory or stock-out for Period 1:
It is calculated by adding the production and ending inventory of the previous month and subtracting the result from the demand. The ending inventory for Period 1 is 400.
Calculate the ending inventory or stock-out for Period 2:
It is calculated by adding the production and ending inventory of the previous month and subtracting the result from the demand. The ending inventory for Period 2 is 400.
Calculate the ending inventory or stock-out for Period 3:
It is calculated by adding the production and ending inventory of the previous month and subtracting the result from the demand. The ending inventory for Period 3 is 200.
Calculate the ending inventory or stock-out for Period 4:
It is calculated by adding the production and ending inventory of the previous month and subtracting the result from the demand. The ending inventory for Period 4 is 0.
Calculate the ending inventory or stock-out for Period 5:
As the demand is more than the production, there would be a stock-out.
It is calculated by subtracting the production from the demand. The result should then be subtracted from the overtime units. Hence, the stock-out units for Period 5 is 280 units.
Calculate the ending inventory or stock-out for Period 6:
As the demand is more than the production, there would be a stock-out.
It is calculated by subtracting the production from the demand. The result should then be subtracted from the overtime units. Hence, the stock-out units for Period 6 is 280 units.
Calculate the ending inventory or stock-out for Period 7:
It is calculated by subtracting the production from the demand. The result should then be subtracted from the overtime units. Hence, the stock-out units for Period 7 is 0 units.
Note: Overtime units of 320 units would lead to a negative value. Hence, it was taken as 200 units.
Calculate the ending inventory or stock-out for Period 8:
It is calculated by subtracting the production from the demand. The result should then be subtracted from the overtime units. Hence, the stock-out units for Period 8 is 0 units.
Note: Overtime units of 320 units would lead to negative value. Hence, it was taken as 200 units.
Calculate the extra cost for Period 1:
It is calculated by multiplying the extra inventory units and inventory holding cost. The inventory holding cost is given as $20 per unit. Hence, the extra cost for period 1 is $8,000
Calculate the extra cost for Period 2:
It is calculated by multiplying the extra inventory units and inventory holding cost. Inventory holding cost is given as $20 per unit. Hence, the extra cost for period 2 is $8,000
Calculate the extra cost for Period 3:
It is calculated by multiplying the extra inventory units and inventory holding cost. Inventory holding cost is given as $20 per unit. Hence, the extra cost for period 3 is $4,000
Calculate the extra cost for Period 4:
As there are no overtime units, ending inventory units, or stock-out units, there would not be any extra costs.
Calculate the extra cost for Period 5:
It is calculated by adding the product of overtime units and inventory holding overtime cost per unit, and the product of stock-out units and stock-out cost per unit. Stock-out cost is given as $100 per unit and overtime cost is given as $50 per unit. Hence, the extra cost for period 5 is $44,000
Calculate the extra cost for Period 6:
It is calculated by adding the product of overtime units and inventory holding overtime cost per unit, and the product of stock-out units and stock-out cost per unit. Stock-out cost is given as $100 per unit and overtime cost is given as $50 per unit. Hence, the extra cost for period 6 is $44,000
Calculate the extra cost for Period 7:
It is calculated by adding the product of overtime units and inventory holding overtime cost per unit, and the product of stock-out units and stock-out cost per unit. Stock-out cost is given as $100 per unit and overtime cost is given as $50 per unit. Hence, the extra cost for period 7 is $10,000
Calculate the extra cost for Period 8:
It is calculated by adding the product of overtime units and inventory holding overtime cost per unit, and the product of stock-out units and stock-out cost per unit. Stock-out cost is given as $100 per unit and overtime cost is given as $50 per unit. Hence, the extra cost for period 8 is $10,000
Calculate the total cost of Plan D:
It is calculated by adding the extra costs of all the periods.
Hence, the total cost for Plan D is $128,000.
b)
To determine: Plan E
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
b)
Answer to Problem 6P
Plan E has been evaluated. The total cost of Plan E is $140,000.
Explanation of Solution
Given information:
Production for all the months is 1,600 units. Overtime cost is $50 per unit. Maximum allowable inventor in the warehouse is 400 units or less. Demand requirement from period 0 to 8 is as follows:
Period | Expected demand |
0 | 0 |
1 | 1,400 |
2 | 1,600 |
3 | 1,800 |
4 | 1,800 |
5 | 2,200 |
6 | 2,200 |
7 | 1,800 |
8 | 1,800 |
Evaluate the cost of the plan:
Plan E | |||||
Period | Demand | Production | Subcontract (units) | Ending inventory | Extra cost |
0 | 200 | ||||
1 | 1,400 | 1,600 | - | 400 | $8,000 |
2 | 1,600 | 1,600 | - | 400 | $8,000 |
3 | 1,800 | 1,600 | - | 200 | $4,000 |
4 | 1,800 | 1,600 | - | - | $0 |
5 | 2,200 | 1,600 | 600 | - | $45,000 |
6 | 2,200 | 1,600 | 600 | - | $45,000 |
7 | 1,800 | 1,600 | 200 | - | $15,000 |
8 | 1,800 | 1,600 | 200 | - | $15,000 |
Total | 14,600 | 1,600 | 1,000 | $140,000 |
Note: Production is given as 1,600 units. The ending inventory for December is given as 200 units. If the production is more than or equal to the demand, then there would be inventory. If the demand is more, then there would be subcontract.
Calculate the ending inventory or subcontract for Period 1:
It is calculated by adding the production and ending inventory of previous month and subtracting the demand from the result. The ending inventory for Period 1 is 400.
Calculate the ending inventory or subcontract for Period 2:
It is calculated by adding the production and ending inventory of previous month and subtracting the demand from the result. The ending inventory for Period 2 is 400.
Calculate the ending inventory or subcontract for Period 3:
It is calculated by adding the production and ending inventory of previous month and subtracting the demand from the result. The ending inventory for Period 3 is 200.
Calculate the ending inventory or subcontract for Period 4:
It is calculated by adding the production and ending inventory of previous month and subtracting the demand from the result. The ending inventory for Period 4 is 0.
Calculate the ending inventory or subcontract for Period 5:
As the demand is more than the production, there would be a subcontract.
It is calculated by subtracting the production from the demand. Hence, the subcontract units for Period 5 is 600 units.
Calculate the ending inventory or subcontract for Period 6:
As the demand is more than the production, there would be a subcontract.
It is calculated by subtracting the production from the demand. Hence, the subcontract units for Period 6 is 600 units.
Calculate the ending inventory or subcontract for Period 7:
It is calculated by subtracting the production from the demand. The result should then be subtracted from the overtime units. Hence, the subcontract units for Period 7 is 200 units.
Calculate the ending inventory or subcontract for Period 8:
It is calculated by subtracting the production from the demand. The result should then be subtracted from the overtime units. Hence, the subcontract units for Period 8 is 0 units.
Calculate the extra cost for Period 1:
It is calculated by multiplying the extra inventory units and inventory holding cost. Inventory holding cost is given as $20 per unit. Hence, the extra cost for period 1 is $8,000
Calculate the extra cost for Period 2:
It is calculated by multiplying the extra inventory units and inventory holding cost. Inventory holding cost is given as $20 per unit. Hence, the extra cost for period 2 is $8,000
Calculate the extra cost for Period 3:
It is calculated by multiplying the extra inventory units and inventory holding cost. Inventory holding cost is given as $20 per unit. Hence, the extra cost for period 3 is $4,000
Calculate the extra cost for Period 4:
As there are no overtime units, ending inventory units, and subcontract units, there would not be extra costs.
Calculate the extra cost for Period 5:
It is calculated by multiplying the subcontract units and subcontract cost per unit. Subcontract cost is given as $75 per unit. Hence, the extra cost for period 5 is $45,000
Calculate the extra cost for Period 6:
It is calculated by multiplying the subcontract units and subcontract cost per unit. Subcontract cost is given as $75 per unit. Hence, the extra cost for period 6 is $45,000
Calculate the extra cost for Period 7:
It is calculated by multiplying the subcontract units and subcontract cost per unit. Subcontract cost is given as $75 per unit. Hence, the extra cost for period 7 is $15,000
Calculate the extra cost for Period 8:
It is calculated by multiplying the subcontract units and subcontract cost per unit. Subcontract cost is given as $75 per unit. Hence, the extra cost for period 8 is $15,000
Calculate the total cost of Plan E:
It is calculated by adding the extra costs of all the periods.
Hence, the total cost for Plan E is $140,000.
The total cost for Plan D is preferable when compared with Plan E. However, Plan C, with the total cost of $86,000 is preferable over other plans.
Want to see more full solutions like this?
Chapter 13 Solutions
Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)
- PP.63 Jupiter, a large candy company, is having great success with its "Swan" family of candy bars. Due to a number of factors they like to plan their production at least six months into the future. The table below contains their demand projections (in tons) for April through September: Supply/Demand Info Beginning Apr May Jun Jul Aug Sep Predicted Sales 45,500 45,100 51,900 52,800 47,900 47,200 Regular production Overtime production Subcontract production Ending inventory 14,400 Hired employees Fired employees Total employees 423 Cost variables are as follows: Cost Variables Labor cost/hour $13 Overtime cost/ton $30 Subcontracting cost/ton $28 Holding cost/ton/month $14 Hiring cost/employee $3,700 Firing cost/employee $5,800 Here is some additional…arrow_forwardWhat are the responsibilities and duties of a consultant for a local company who is considering expanding its operations to international markets? How can a local Agriculture and Food Processing company successfully enter international markets?arrow_forwardWhat is an example of how someone would explain how their past personal and professional experience makes you a quality candidate for a teaching position at an Elementary School as a K-6 Teacher?arrow_forward
- I need answer typing clear urjent no chatgpt used pls i will give 5 Upvotes.arrow_forwardHow can a local tourism and hospitality company successfully enter international markets?arrow_forwardHow was Circuit City Company collapsed? And what was the sequence of time and events or problems? How to solve the issues, and could you help identify positions or titles. Sanitize all names and use only fictitious data. What is synthesize the qualitative research methodology of Case Study research? Please give some examples. How to use the practical of Lean Six Sigma to develop a business-facing DMAIC-based case studyarrow_forward
- BUSINESS MODEL CANVAS: U.S ARMY key partners: Key activities: Key Resources: Value Propositions: Buy-in & Support: Deployment: Benficiaries: Mission budget/cost: Mission Achievement/ Impact factors: Please at least 4 for each categoryarrow_forwardhow you would best conduct a performance evaluation meeting with a subordinate (where an employee would receive their performance evaluation from their supervisor). Importantly, detail how a supervisor can best gain the concurrence from an employee on the evaluation itself, and to ensure that the employee’s performance will be modified as a result of appraisal meeting.arrow_forwardI need answer typing clear urjent no chatgpt used pls i will give 5 Upvotes.arrow_forward
- assume that you are police commander which leads and supervises the department’s internal affairs division. Your goal is to reduce civilian complainants against personnel in the department. Using what you have learned and at least three scholarly sources, document two changes you see the department can implement, whether it be training, planning, mitigating, and resolving, to improve police/community relations.arrow_forwardNess Engineering is a private limited company mainly engaged in the continuous production and assembly of domestic products. The annual turnover is $900,000,000. The largest area of expenditure is raw materials and components where the annual spend is approximately $450,000,000. The Managing Director, Bill, considers that profit margins are too small and has asked you to suggest how profitability might be increased. Bill suggests that this might be done by appointing additional sales staff and by an advertising campaign, which would, hopefully, increase turnover and thereby reduce overhead cost per item. You find that purchasing is little more than a post-office function. Specifications are received from the design or user departments and sent either to supplies designated by the directors or to the supplier providing the cheapest quotation. The company does, in fact, deal with many suppliers and issues many orders for low-cost items. All purchasing is done by manual means. None of the…arrow_forwardThe oasis outpost of Abu Ilan, in the heart of the Negev desert, has a population of 20 Bedouin tribesmen and 20 Farima tribesmen. El Kamin, a nearby oasis, has a population of 32 Bedouins and 8 Farima. A lost Israeli soldier, accidentally separated from his army unit, is wandering through the desert and arrives at the edge of one of the oases. The soldier has no idea which oasis he has found, but the first person he spots at a distance is a Bedouin. 1. What is the probability that he wandered into Abu Ilan? 2. What is the probability that he is in El Kamin?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning
- Foundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning