To define: The relationship between aggregate planning and master production schedule
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Master production
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
What is the relationship between the aggregate plan andthe master production schedule?
Explain the various costs associated with aggregate planning?
Deb Bishop Health and Beauty Products has developed a new shampoo and you need to develop its aggregate schedule. The cost accounting department has supplied you the cost relevant to the aggregate plan and the marketing department has provided a four-quarter forecast.
the four-quarter forecast.
Quarter
Forecast
1
1,400
2
1,100
3
1,700
4
1,300
aggregate plan.
Costs
Previous quarter's output
1,600
units
Beginning inventory
0
units
Stockout cost for backorders
$55
per unit
Inventory holding cost
$11
per unit for every unit held at the end of the quarter
Hiring workers
$50
per unit
Layoff workers
$75
per unit
Unit cost
$35
per unit
Overtime
$20
extra per unit
Subcontracting
Not available
Your job is to develop an aggregate plan for the next four quarters.
Part 2
a) Try hiring and layoffs (to meet the forecast) as necessary (enter your responses as whole…
Chapter 13 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
Ch. 13 - Make the case for, and then against, this pricing...Ch. 13 - Prob. 1DQCh. 13 - Why are SOP teams typically cross-functional?Ch. 13 - Prob. 3DQCh. 13 - Prob. 4DQCh. 13 - Prob. 5DQCh. 13 - Prob. 6DQCh. 13 - Prob. 7DQCh. 13 - Prob. 8DQCh. 13 - Prob. 9DQ
Ch. 13 - Prob. 10DQCh. 13 - Prob. 11DQCh. 13 - Prob. 12DQCh. 13 - Prob. 13DQCh. 13 - Prob. 14DQCh. 13 - Prob. 1PCh. 13 - Prob. 2PCh. 13 - The president of Hill Enterprises, Terri Hill,...Ch. 13 - Prob. 4PCh. 13 - Prob. 5PCh. 13 - Prob. 6PCh. 13 - Consuelo Chua, Inc., is a disk drive manufacturer...Ch. 13 - Prob. 8PCh. 13 - Prob. 9PCh. 13 - Prob. 10PCh. 13 - Prob. 11PCh. 13 - Southeast Soda Pop, Inc., has a new fruit drink...Ch. 13 - Ram Roys firm has developed the following supply,...Ch. 13 - Jerusalem Medical Ltd., an Israeli producer of...Ch. 13 - Prob. 15PCh. 13 - Prob. 16PCh. 13 - Prob. 17PCh. 13 - Prob. 18PCh. 13 - Dwayne Cole, owner of a Florida firm that...Ch. 13 - Prob. 20PCh. 13 - Prob. 21PCh. 13 - Prob. 22PCh. 13 - Prob. 23PCh. 13 - Prob. 24PCh. 13 - Prob. 25PCh. 13 - Prob. 26PCh. 13 - Evaluate the various configurations of operating...Ch. 13 - Prob. 2CSCh. 13 - After researching revenue (yield) management in...Ch. 13 - The Magic used its original pricing systems of...Ch. 13 - Prob. 1.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Table below provides the demand forecast and production day information for an aggregate plan. Assume that no back orders are allowed in this case. Month January February March April May June Demand Forecast 3,000 4,500 3,400 2,500 4,000 3,200 Production Days 22 18 21 21 22 20 The costing information that is used to evaluate the total cost of each plan is as follows:• Inventory carrying cost: $4 per unit per month• Subcontracting cost per unit: $15 per unit• Working hours: 8 hours per day• Average pay rate: $12 per hour ($96 per day per worker)• Labour-hours to produce a unit: 2 hours per unit• Cost of increasing daily production rate (hiring and training): $300 per unit• Cost of decreasing daily production rate (layoffs): $700 per unitUse these information to formulate an aggregate plan. The firm would like to use level strategy: constant workforce for the aggregate planning. The firm chooses the average demand of the…arrow_forwardExplain how an aggregate production plan is made.arrow_forwardDeb Bishop Health and Beauty Products has developed a new shampoo and you need to develop its aggregate schedule. The cost accounting department has supplied you the cost relevant to the aggregate plan and the marketing department has provided a four-quarter forecast. the four-quarter forecast. Quarter Forecast 1 1,400 2 1,100 3 1,700 4 1,300 the costs relevant to the aggregate plan. Costs Previous quarter's output 1,600 units Beginning inventory 0 units Stockout cost for backorders $55 per unit Inventory holding cost $11 per unit for every unit held at the end of the quarter Hiring workers $50 per unit Layoff workers $75 per unit Unit cost $35 per unit Overtime $20 extra per unit Subcontracting Not available Your job is to develop an aggregate plan for the next four quarters. Part 2 a) Try hiring and layoffs (to meet the forecast) as necessary…arrow_forward
- In production plan 2, vary inventory if the ending inventory for March is -32, what will be the beginning inventory for the month of April?arrow_forwardWhat considerations are essential in determining the planning horizon period for aggregate planning?arrow_forwardAn X product is composed of A, B, C items. The aggregate plan for February and some of the information are provided as follows. Prepare the master production schedule.arrow_forward
- Describe in detail what are the aggregate planning goal's?arrow_forwardWhat is the BOM stock needed for the shoe department for April if the sales are planned at $64,000 and the stock to sales ratio is 18.3?arrow_forwardCreate a level plan with a zero ending inventory for the forecast shown in the table. There is no beginning inventory and regular production capacity is 300 units. Overtime costs K15 extra and is limited to 25 units per month and subcontracting is limited to 60 units per month and costs K10 per unit. Back orders cost KS0 per unit and there is a cost of KS per month to hold a unit in inventory. What is the total plan cost? |Month January February March Forecast 250 300 400 |April 350arrow_forward