EBK PRINCIPLES OF OPERATIONS MANAGEMENT
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
11th Edition
ISBN: 9780135175644
Author: Munson
Publisher: VST
bartleby

Concept explainers

Question
Book Icon
Chapter 13, Problem 10P

a)

Summary Introduction

To evaluate: Plan C for the given information

Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.

a)

Expert Solution
Check Mark

Answer to Problem 10P

The Plan C has been evaluated. The total cost of Plan C is $104,000.

Explanation of Solution

Given information:

Production for all the months is 1,300 units. Ending inventory in June is 300 units. Overtime cost is $50 per unit. Demand requirement from July to December is given as follows:

Period Demand Production (units)
June
July 1,000 1,300
August 1,200 1,300
September 1,400 1,300
October 1,800 1,300
November 1,800 1,300
December 1,800 1,300

Evaluate the cost of the plan:

Plan C
Period Demand Production (units) Subcontract (units) Ending inventory Extra cost
June 300
July 1,000 1,300 600 $15,000
August 1,200 1,300 700 $17,500
September 1,400 1,300 600 $15,000
October 1,800 1,300 100 $2,500
November 1,800 1,300 400 0 $24,000
December 1,800 1,300 500 0 $30,000
Total $104,000

Note: Production is given as 1,300 units. Ending inventory for June is given as 300 units. If the production is more than or equal to the demand, then there would be inventory. If the demand is more, then there would be stock out.

Calculate ending inventory or subcontract for July:

It is calculated by adding the production and ending inventory of previous month and subtract the result from the demand. Ending inventory for July is 600.

Ending inventory=(Production+Ending inventory of previous month)Demand=(1,300+300)1,000=1,6001,000=600

Calculate ending inventory or subcontract for August:

It is calculated by adding the production and ending inventory of previous month and subtract the result from the demand. Ending inventory for August is 700.

Ending inventory=(Production+Ending inventory)Demand=(1,300+600)1,200=1,9001,200=700

Calculate ending inventory or subcontract for September:

It is calculated by adding the production and ending inventory of previous month and subtract the result from the demand. Ending inventory for September is 600.

Ending inventory=(Production+Ending inventory)Demand=(1,300+700)1,400=2,0001,400=600

Even though the demand is high, as there is enough ending inventory in previous month, there would be inventory rather than subcontract.

Calculate the ending inventory or subcontract for October:

It is calculated by adding the production and ending inventory of previous month and subtract the result from the demand. Ending inventory for October is 100.

Ending inventory=(Production+Ending inventory)Demand=(1,300+600)1,800=1,9001,800=100

Even though the demand is high, as there is enough ending inventory in previous month, there would be inventory rather than subcontract.

Calculate ending inventory or subcontract for November:

As the demand is more than the production and there is no enough ending inventory, there would be subcontract.

It is calculated by adding production and ending inventory and the result should be subtracted with the demand. Hence, the subcontract units for November is 400 units.

Ending inventory=(Production+Ending inventory)Demand=(1,300+100)1,800=1,4001,800=400

As the value is in negative, it would be subcontract.

Calculate ending inventory or subcontract for December:

As the demand is more than the production and there is no enough ending inventory, there would be subcontract.

It is calculated by adding production and ending inventory and the result should be subtracted with the demand. Hence, the subcontract units for December is 500 units.

Ending inventory=(Production+Ending inventory)Demand=(1,300+0)1,800=1,3001,800=500

As the value is in negative, it would be subcontract.

Calculate extra cost for July:

It is calculated by multiplying ending inventory units and inventory holding cost. Inventory holding cost is given as $25 per unit. Hence, extra cost for July is $15,000

Extra cost=Ending inventory×Inventory holding cost per unit=600×$25=$15,000

Calculate extra cost for August:

It is calculated by multiplying ending inventory units and inventory holding cost. Inventory holding cost is given as $25 per unit. Hence, extra cost for August is $17,500

Extra cost=Ending inventory×Inventory holding cost per unit=700×$25=$17,500

Calculate extra cost for September:

It is calculated by multiplying ending inventory units and inventory holding cost. Inventory holding cost is given as $25 per unit. Hence, extra cost for September is $15,000

Extra cost=Ending inventory×Inventory holding cost per unit=600×$25=$15,000

Calculate extra cost for October:

It is calculated by multiplying ending inventory units and inventory holding cost. Inventory holding cost is given as $25 per unit. Hence, extra cost for October is $2,500

Extra cost=Ending inventory×Inventory holding cost per unit=100×$25=$2,500

Calculate extra cost for November:

It is calculated by multiplying ending inventory units and inventory holding cost. Inventory holding cost is given as $60 per unit. Hence, extra cost for November is $24,000

Extra cost=Subcontract×Subcontract cost per unit=400×$60=$24,000

Calculate extra cost for December:

It is calculated by multiplying ending inventory units and inventory holding cost. Inventory holding cost is given as $60 per unit. Hence, extra cost for December is $30,000

Extra cost=Subcontract×Subcontract cost per unit=500×$60=$30,000

Calculate total cost of Plan C:

It is calculated by adding the extra costs of all the periods.

Total cost=Extra costs of all periods=$15,000+$17,500+$15,000+$2,500+$24,000+$30,000=$104,000

Hence, the total cost for Plan C is $104,000.

b)

Summary Introduction

To determine: Evaluate plan D for the given information

Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.

b)

Expert Solution
Check Mark

Answer to Problem 10P

The Plan D has been evaluated. The total cost of Plan D is $93,800.

Explanation of Solution

Given information:

Production for all the months is 1,300 units. Ending inventory in June is 300 units. Overtime cost is $50 per unit. Demand requirement from July to December is given as follows:

Period Demand Production (units)
June
July 1,000 1,300
August 1,200 1,300
September 1,400 1,300
October 1,800 1,300
November 1,800 1,300
December 1,800 1,300

Evaluate the cost of the plan:

Plan D
Period Demand Regular production (units) Overtime production (units) Ending inventory Sub-contract (units) Idle time (units) Extra cost
June
July 1,000 1,300 180 120 $11,700
August 1,200 1,300 180 100 $10,500
September 1,400 1,300 80 $2,000
October 1,800 1,300 260 0 160 $20,000
November 1,800 1,300 260 0 240 $24,800
December 1,800 1,300 260 0 240 $24,800
Total $93,800

Note: Production is given as 1,300 units. If the production is more than or equal to the demand, then there would be inventory. If the demand is more, then there would be stock out. Maximum overtime units allowed is 260 units (20% of production)

Calculate ending inventory or subcontract for July:

It is calculated by adding the production and ending inventory of previous month and subtract the result from the demand. Ending inventory for July is 180.

Ending inventory=ProductionDemand=1,3001,000=300

It is given that the ending inventory should not exceed 180 units. Hence, the ending inventory would be 180 units and remaining units of 300 (120 units) would be in idle time.

Calculate ending inventory or subcontract for August:

It is calculated by adding the production and ending inventory of previous month and subtract the result from the demand. Ending inventory for August is 180.

Ending inventory=(Production+Ending inventory)Demand=(1,300+180)1,200=1,4801,200=280

It is given that the ending inventory should not exceed 180 units. Hence, the ending inventory would be 180 units and remaining units of 280 (100 units) would be in idle time.

Calculate ending inventory or subcontract for September:

It is calculated by adding the production and ending inventory of previous month and subtract the result from the demand. Ending inventory for September is 80.

Ending inventory=(Production+Ending inventory)Demand=(1,300+180)1,400=1,4801,400=80

Calculate the ending inventory or subcontract for October:

It is calculated by adding the production and ending inventory of previous month and subtract the result from the demand. Subcontract for October is 160.

Ending inventory=(Production+Ending inventory)Demand=(1,300+80)1,800=1,3801,800=420

As the value is in negative, it would be subcontract. Overtime production should not exceed 260 units. Hence, 260 units would be production in overtime production and 160 units (remaining from 420) would be produced in subcontract.

Calculate the ending inventory or subcontract for November:

It is calculated by adding the production and ending inventory of previous month and subtract the result from the demand. Subcontract for November is 240.

Ending inventory=(Production+Ending inventory)Demand=(1,300+0)1,800=1,3001,800=500

As the value is in negative, it would be subcontract. Overtime production should not exceed 260 units. Hence, 260 units would be production in overtime production and 240 units (remaining from 500) would be produced in subcontract.

Calculate the ending inventory or subcontract for December:

It is calculated by adding the production and ending inventory of previous month and subtract the result from the demand. Subcontract for December is 240.

Ending inventory=(Production+Ending inventory)Demand=(1,300+0)1,800=1,3001,800=500

As the value is in negative, it would be subcontract. Overtime production should not exceed 260 units. Hence, 260 units would be production in overtime production and 240 units (remaining from 500) would be produced in subcontract.

Calculate extra cost for July:

It is calculated by adding the multiple of ending inventory units and inventory holding cost and the multiple of idle time and idle time cost. Inventory holding cost is given as $25 per unit and idle time per unit is $60. Hence, extra cost for July is $11,700.

Extra cost=(Ending inventory×Inventory holding cost per unit)+(Idle time×Idle time cost)=(180×$25)+(120×$60)=$11,700

Calculate extra cost for August:

It is calculated by adding the multiple of ending inventory units and inventory holding cost and the multiple of idle time and idle time cost. Inventory holding cost is given as $25 per unit and idle time per unit is $60. Hence, extra cost for August is $10,500.

Extra cost=(Ending inventory×Inventory holding cost per unit)+(Idle time×Idle time cost)=(180×$25)+(100×$60)=$10,500

Calculate extra cost for September:

It is calculated by adding the multiple of ending inventory units and inventory holding cost and the multiple of idle time and idle time cost. Inventory holding cost is given as $25 per unit and idle time per unit is $60. Hence, extra cost for September is $2,000.

Extra cost=(Ending inventory×Inventory holding cost per unit)+(Idle time×Idle time cost)=(80×$25)+(0)=$2,000

Calculate extra cost for October:

It is calculated by adding the multiple of overtime units and overtime cost per unit and subcontract units and subcontract cost per unit. Overtime cost per unit is $40 per unit and subcontract cost is $60 per unit. Hence, extra cost for October is $20,000.

Extra cost=(Overtime units×Overtime cost per unit)+(Subcontract units×Subcontract cost per unit)=(260×$40)+(160×$60)=$20,000

Calculate extra cost for November:

It is calculated by adding the multiple of overtime units and overtime cost per unit and subcontract units and subcontract cost per unit. Overtime cost per unit is $40 per unit and subcontract cost is $60 per unit. Hence, extra cost for November is $24,800.

Extra cost=(Overtime units×Overtime cost per unit)+(Subcontract units×Subcontract cost per unit)=(260×$40)+(240×$60)=$24,800

Calculate extra cost for December:

It is calculated by adding the multiple of overtime units and overtime cost per unit and subcontract units and subcontract cost per unit. Overtime cost per unit is $40 per unit and subcontract cost is $60 per unit. Hence, extra cost for December is $24,800.

Extra cost=(Overtime units×Overtime cost per unit)+(Subcontract units×Subcontract cost per unit)=(260×$40)+(240×$60)=$24,800

Calculate total cost of Plan D:

It is calculated by adding the extra costs of all the periods.

Total cost=Extra costs of all periods=$11,700+$10,500+$2,000+$20,000+$24,800+$24,800=$93,800

Hence, the total cost for Plan D is $93,800.

Conclusion

Total cost for Plan D is preferable when compare with Plan C. However, Plan D with the total cost of $93,800 is preferable than other plans.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The planner at a company that makes garden tractors is about to prepare an aggregate production plan that will cover the next 6 months. She has collected the following information: Month Demand Forecast Above the available capacity through permanent workforce 1 1,000 2 1,000 3 2,000 4 3,000 5 4,000 6 1,000 Total: 12,000 Production per month = 20 units per worker Initial inventory = 500 units Desired ending inventory (at the end of month 6) = 0 units Cost:               Hire cost = $500 per temporary worker               Inventory = $10 per tractor per month               Backorder = $150 per tractor per month The optimum aggregate plan is: Month 1 2 3 4 5 6 Total Forecast Demand above regular capacity 1,000 1,000 2,000 3,000 4,000 1,000 12,000 # of temporary workers required 50 50 100 150 200 50   Temp. Workers hired 25 25 50 75 0 0   Temp. workers laid off 0…
Jose Martinez of El Paso had developed a polished stainless-steel tortilla machine that makes it a “showpiece” for display in Mexican restaurants.  He needs to develop a 5-month aggregate plan.  His forecast of capacity and demand follows:   Month   1 2 3 4 5 Demand 150 160 130 200 210 Regular capacity 150 150 150 150 150 Overtime capacity 20 20 10 10 10 Subcontracting: 100 units available over the 5-month period (NOT 100 units each month) Beginning inventory: 0 units Ending inventory required at the last month (i.e. month 5): 20 units. Costs   Regular-time cost per unit $100 Overtime cost per unit $125 Subcontracting cost per unit $135 Inventory holding cost per unit per month $3 Assume that backorders are not permitted. a) Find an aggregate production plan using the intuitive lowest cost approach. (i.e. Develop an aggregate plan using the transportation method). b) State the corresponding…
3) AGGREGATE PLANNING Mark Tuan, Operations Manager at GOT7 Furniture, has received the following estimates of demand requirements: January 1,100 February 1,200 March 1,400 April 1,800 May 1,800 June 1,600 Assuming stockout costs for lost sales of RM100 per unit, inventory carrying costs of RM25 per unit per month, and a zero beginning and ending inventory. Analyze the extra cost if the company vary the workforce, which performs at a current production level of 1,300 units per month. The cost of hiring additional workers is RM3,000 per 100 units produced. The cost of layoffs is RM6,000 per 100 units cut back.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing