UPD Manufacturing produces a range of health care appliances for hospital as well as for home use. The company has experienced a steady demand for its products, which are highly regarded in the health care field. Recently the company has undertaken a review of its inventory ordering procedures as part of a larger effort to reduce costs.
One of the company's products is a blood pressure testing kit. UPD manufactures all of the components for the kit in house except for the digital display unit. The display units are ordered at six-week intervals from the supplier. This ordering system began about five years ago, because the supplier insisted on it. However, that supplier was bought out by another supplier about a year ago, and the six-week ordering requirement is no longer in place. Nonetheless, UPD has continued to use the six-week ordering policy. According to purchasing manager Tom Chambers, "Unless somebody can give me a reason for changing, I'm going to stick with what we've been doing. I don't have time to reinvent the wheel."
Further discussions with Tom revealed a cost of $32 to order and receive a shipment of display units from the supplier. The company assembles 89 kits a week. Also, information from Sara James, in Accounting, indicated a weekly carrying cost of $.08 for each display unit.
The supplier has been quite reliable with deliveries; orders are received five working days after they are faxed to the supplier. Tom indicated that as far as he was concerned, lead-time variability is virtually nonexistent.
Would using an order interval other than every six weeks reduce costs? If so, what order interval would be best, and what order size would that involve?
Want to see the full answer?
Check out a sample textbook solutionChapter 13 Solutions
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
- Scenario 3 Ben Gibson, the purchasing manager at Coastal Products, was reviewing purchasing expenditures for packaging materials with Jeff Joyner. Ben was particularly disturbed about the amount spent on corrugated boxes purchased from Southeastern Corrugated. Ben said, I dont like the salesman from that company. He comes around here acting like he owns the place. He loves to tell us about his fancy car, house, and vacations. It seems to me he must be making too much money off of us! Jeff responded that he heard Southeastern Corrugated was going to ask for a price increase to cover the rising costs of raw material paper stock. Jeff further stated that Southeastern would probably ask for more than what was justified simply from rising paper stock costs. After the meeting, Ben decided he had heard enough. After all, he prided himself on being a results-oriented manager. There was no way he was going to allow that salesman to keep taking advantage of Coastal Products. Ben called Jeff and told him it was time to rebid the corrugated contract before Southeastern came in with a price increase request. Who did Jeff know that might be interested in the business? Jeff replied he had several companies in mind to include in the bidding process. These companies would surely come in at a lower price, partly because they used lower-grade boxes that would probably work well enough in Coastal Products process. Jeff also explained that these suppliers were not serious contenders for the business. Their purpose was to create competition with the bids. Ben told Jeff to make sure that Southeastern was well aware that these new suppliers were bidding on the contract. He also said to make sure the suppliers knew that price was going to be the determining factor in this quote, because he considered corrugated boxes to be a standard industry item. As the Marketing Manager for Southeastern Corrugated, what would you do upon receiving the request for quotation from Coastal Products?arrow_forwardSitka Industries uses a cost system that carries direct materials inventory at a standard cost. The controller has established these standards for one ladder (unit): StandardQuantity x StandardPrice = StandardCost Direct materials 3 pounds $4.50 per pound $13.50 Direct labor 2.00 hours 12.00 per hour 24.00 Total cost $37.50 Sitka Industries made 2,900 ladders in July and used 8,500 pounds of material to make these units. Sitka Industries bought 15,400 pounds of material in the current period. There was a $300 unfavorable direct materials price variance. Enter all amounts as positive numbers. A. How much in total did Sitka pay for the 15,400 pounds? B. What is the direct materials quantity variance? C. What is the total direct materials cost variance? D. What if 9,200 pounds were used to make these ladders, what would be the direct materials quantity variance? E. If there was a $340 favorable direct materials price variance, how much did Sitka pay…arrow_forwardThe sales department receives all orders from the customers. While receiving the order, the sales team authorizes the payment and check line items. If authorization is failed, a cancelation message is sent to the customer. On the other hand, each line item is checked with the stock. If it is in stock, assigned to the order otherwise the item is removed from the list. If stocks are available for all products and payment is authorized, the sales team dispatched the order.Shipping teams ship the order to the customer. The method of delivery is decided conditionally. Depending on the condition either the Urgent Delivery activity or the Regular Delivery activity is performed. The delivery procedure is finished when the customer receives it and signs in. Draw an Activity diagram based on the above scenario.arrow_forward
- As the engineering manager of air conditioning units for Acme Bus Company, you receive a notice that there might be some flaw in the units because a virus-like upper respiratory infection has spread through the school children who were bussed a long way for a special summer session. The suspicion is reinforced early in the fall school year when only a few of the 80 students showed up at the pick-up points two weeks after the bus runs started. These are new buses put into service at the beginning of the summer, thus there is no previous experience with them. You go to your boss to advise an immediate withdrawal of the buses but he refuses on the grounds that there is no evidence. How should you proceed? What steps should you take to resolve the issues? Write briefly analyzing this case and explaining your answer.arrow_forward“oh fada” receives supplies from a wide range of suppliers directly and adds value by breaking down bulk, customising certain items, and holding stocks until customers require them. The number of inflows of various ranges of goods serving the same purpose has begun to increase with several large amounts laying ideal in warehouse and threatening to become obsolete and also adding up unnecessary cost. The coding system does not allow for ease of identification of the products and wrong item are often picked as the difference between the right and wrong item can be just one digit. Orders are received by telephone and there is no provision for electronic ordering. The stock coding system is a sequential one and has contributed to several issues including inaccurate order entry as it is not possible to find the product details from the codes in use. The products for the orders are manually picked by a team, stock records is done manually with a lot of errors and does not update stock…arrow_forwardDevelop a measure of risk to go along with the ordering policy. This measure should be quantifiable.arrow_forward
- Identify CVP analysis assumptions and restrictions.arrow_forwardDiscount-Mart (see Problem 16.8), as part of its newLean program, has signed a long-term contract with SpecialtyLighting and will place orders electronically for its halogen lamps.Ordering costs will drop to $.50 per order, but Discount-Mart alsoreassessed its carrying costs and raised them to $20 per lamp.a) What is the new economic order quantity?b) How many orders will now be placed?c) What is the total annual cost of managing the inventory withthis policy?arrow_forwardJustin is a carpenter and makes furniture which he sells via the internet. He needs a new machine with steel attachments to speed up the drilling process for his work. He contacts Fixing and Building Machines Ltd who recommends a machine which they claim is more than 10 times quicker and stronger than his old machine. Justin goes into Fixing and Building Machines Ltd. Before paying for the machine, he sees a sign on the wall behind the counter that has the words “Important Information: READ BEFORE PURCHASE! Fixing and Building Machines Ltd accepts no liability.....” in bold, red print at the top. However, the sign is falling down from the wall and the rest of the words are obscured by a large plant. Had Justin been able to read the rest of the sign, he would have read “....for loss howsoever caused.” Justin signs a document, buys this machine and takes it with him. When he tried it he found it to be no quicker than his old one and the attachments broke. He also found that it started…arrow_forward
- Demand for portable music players for joggers has caused Nancy Industries (Nancy) to grow almost 50 percent over the past year. The number of joggers continues to expand, so Nancy expects demand for music player to also expand, because, as yet, no safety laws have been passed to prevent joggers from wearing them. Demands for the players for last year was as follows : Month Demand (units) Jan 4200 Feb 4300 Mar 4000 Apr 4400 May 5000 Jun 4700 Jul 5300 Aug 4900 Sep 5400 Oct 5700 Nov 6300 Dec 6000 Question : From the choice of simple moving average, weighted moving average, exponential smoothing, and linear regression analysis, which forecasting technique would you consider the most accurate to Nancy Industries? Why?arrow_forwardWhich item would be considered an order winner in an automobile developed for high-end users? Voice-activated music system Compact disc players Full-sized spare tire Air bagsarrow_forwardCycle counting is conducted more frequently for C items since they are less costly and easy to count > true or false?arrow_forward
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning