Demand for walnut fudge ice cream at the Sweet Cream Dairy can be approximated by a
a. If an ROP model is used, what ROP would be consistent with the desired service level? How many days of supply are on hand at the ROP, assuming average demand?
b. If a fixed-interval model is used instead of an ROP model, what order size would be needed for the 90 percent service level with an order interval of 10 days and a supply of 8 gallons on hand at the order time? What is the probability of experiencing a stockout before this order arrives?
c. Suppose the manager is using the ROP model described in part a. One day after placing an order with the supplier, the manager receives a call from the supplier that the order will be delayed because of problems at the supplier's plant. The supplier promises to have the order there in two days. After hanging up, the manager checks the supply of walnut fudge ice cream and finds that 2 gallons have been sold since the order was placed. Assuming the supplier's promise is valid, what is the probability that the dairy will run out of this flavor before the shipment arrives?
a)
To determine: The reorder point and days of supply on hand.
Introduction: Reorder point is the point at which the firm has to replenish its inventory in order to avoid shortages or any lag in production.
Answer to Problem 21P
Explanation of Solution
Given information:
Formula:
Calculation of Reorder point and number of days of supply:
Using z-factor table, the z value corresponds to 0.90. The closest value of probability is 0.8997 which corresponds to z = 1.28.
Reorder point is calculated by multiplying 21 with
Number of days of supply is calculated by dividing 9 with the ratio of 21 and 7 which yields 3 days of supply on hand at ROP.
Hence, the reorder point and days of supply on hand is 9 gallons and 3days.
b)
To determine: The probability of experiencing stock out before the order arrives.
Introduction: Safety stock refers to the quantity of additional or extra stock which are maintained to mitigate the risks and uncertainty which arises due to fluctuation in supply and demand.
Answer to Problem 21P
Explanation of Solution
Given information:
Formula:
Calculation to determine the probability of stock out before arriving of the order:
Using z-factor table, the lead service level is 0.8577.
The risk of stock out is calculated by finding the z-factor from using the ROP of 8, mean demand of 21 and standard deviation of 3.5 and lead time of
For z=1.07, the corresponding value from z-factor table is 0.8577. The probability to find the risk of stock out is difference between 1 and 0.8577 which gives 14.23%.
Hence, the probability of experiencing stock out before the order arrives is 14.23%.
c)
To determine: The probability of stock out situation.
Introduction: Safety stock refers to the quantity of additional or extra stock which are maintained to mitigate the risks and uncertainty which arises due to fluctuation in supply and demand.
Answer to Problem 21P
Explanation of Solution
Given information:
Calculation to determine the probability of stock out situation:
The ROP is 9 gallons (refer equation (1)) and 2 gallons had been sold after placing order. Stock after day 1 of placing order is the difference between 9 and 2 which is 7 gallons.
Using z-factor table, the lead service level is 0.7019.
The risk of stock out is calculated by finding the z-factor from using the ROP of 7, mean demand of 21 and standard deviation of 3.5 and lead time of
For z = 0.53, the corresponding value from z-factor table is 0.7019. The probability to find the risk of stock out is difference between 1 and 0.7019 which gives 29.81%.
Hence, the probability of experiencing stock out is 29.81%.
Want to see more full solutions like this?
Chapter 13 Solutions
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
- 1) View the video Service Processing at BuyCostumes (10.41 minutes, Ctrl+Click on the link); what are your key takeaways (tie to one or more of the topics discussed in Chapter 3) after watching this video. (viddler.com/embed/a6b7054c) Note: As a rough guideline, please try to keep the written submission to one or two paragraphs. 2) Orkhon Foods makes hand-held pies (among other products). The firm’s weekly sales of hand-held pies over the past seven weeks are given in the table. The firm’s operations manager, Amarjargal, wants to forecast sales for week 8. Weeks Sales of hand-held pies(000s) 1 19 2 18 3 17 4 20 5 18 6 22 7 20 Forecast the week 8 sales using the following approaches: a) Naïve approach b) 5-month moving average c) 3-month weighted moving average using the following weights: 0.50 for week 7, 0.30 for week 6, and 0.20 for week 5. d) Exponential smoothing using a smoothing constant of 0.30, assume a…arrow_forwardAnswer all parts to question 4 and show all workingarrow_forward1) View the video Service Processing at BuyCostumes (10.41 minutes, Ctrl+Click on the link); what are your key takeaways (tie to one or more of the topics discussed in Chapter 3) after watching this video. (viddler.com/embed/a6b7054c) Note: As a rough guideline, please try to keep the written submission to one or two paragraphs. 2) Orkhon Foods makes hand-held pies (among other products). The firm’s weekly sales of hand-held pies over the past seven weeks are given in the table. The firm’s operations manager, Amarjargal, wants to forecast sales for week 8. Weeks Sales of hand-held pies(000s) 1 19 2 18 3 17 4 20 5 18 6 22 7 20 Forecast the week 8 sales using the following approaches: a) Naïve approach b) 5-month moving average c) 3-month weighted moving average using the following weights: 0.50 for week 7, 0.30 for week 6, and 0.20 for week 5. d) Exponential smoothing using a smoothing constant of 0.30, assume a week 2…arrow_forward
- What area of emotional intelligence refers to the ability to manage your emotions, particularly in stressful situations, and maintain a positive outlook despite setbacks? relationship management self awareness social awareness self managementarrow_forwardWhat area of emotional intelligence refers to the ability to manage your emotions, particularly in stressful situations, and maintain a positive outlook despite setbacks? relationship management self awareness social awareness self managementarrow_forwardThis area of emotional intelligence describes your ability to not only understand your strengths and weaknesses but to recognize your emotions and their effect on you and your team’s performance self management self awareness relationship management social awarenessarrow_forward
- Emotional intelligence is defined as the ability to understand and manage your emotions, as well as recognize and influence the emotions of those around you. True Falsearrow_forwardAt the Ford automobile Highland plant, assume the one-millionth vehicle was produced in 1916 at a cost of $8084 (in 2013 US$), by how much did the Ford company reduce his cost with each doubling of cumulative output from 1916 to 1927?arrow_forwardAt the Ford automobile Highland plant,in 1913, how long did the average worker stay with the plant and what was the average tenure of a worker?arrow_forward
- Community Federal Bank in Dothan, Alabama, recently increased its fees to customers who use employees as tellers. Management is interested in whether its new tee policy has increased the number of customers now using its automatic teller machines to that point that more machines are required. The following table provides the number of automatic teller transactions by week. Use trend projection with regression to forecast usage for weeks 13-16.arrow_forwardDavison Electronics manufactures three LED television monitors, identified as Model A, Model B, and Model C. Davison Electronics four manufacturing plants. Each model has its lowest possible production cost when produced at Plant 1. However, Plant 1 does not have the capacity to handle the total production of all three models. As a result, at least some of the production must be routed to the other manufacturing plants. The following table shows the minimum production requirements for next month, the plant capacities in units per month, and the production cost per unit at each plant: Model Production Cost per Unit Minimum Production Requirements Plant 1 Plant 2 Plant 3 Plant 4 A $25 $28 $37 $34 48,000 B $26 $35 $36 $41 75,000 C $20 $31 $26 $23 60,000 Production Capacity 65,000 50,000 32,000 43,000 Davison’s objective is to determine the cost-minimizing production planarrow_forwardAnecdotally, entrepreneurs frequently encounter two critical dilemmas in managing human resources: the timing of hiring and the decision regarding hiring a generalist versus a specialist for their growing venture. Deciding when to expand a team is crucial, as premature hiring (i.e., hiring too soon) can strain resources, while delayed hiring (i.e., hiring too late) might hinder growth opportunities. Moreover, the choice between hiring a generalist or a specialist depends on the specific needs and stage of the venture, with each option presenting distinct advantages and challenges. To address these issues, a management scholar seeks to identify the factors shaping the hiring cycle throughout the entrepreneurial journey and to understand the criteria for choosing between generalists and specialists at various stages of a venture. The scholar has assembled a sample of 20 experienced South African entrepreneurs who have encountered both failure and success in the financial technology…arrow_forward
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningPractical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
- MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing