A company is about to begin production of a new product. The manager of the department that will produce one of the components for the product wants to know how often the machine used to produce the item will be available for other work. The machine will produce the item at a rate of 200 units a day. Eighty units will be used daily in assembling the final product. Assembly will take place five days a week, 50 weeks a year. The manager estimates that it will take almost a full day to get the machine ready for a production nm, at a cost of $300. Inventory holding costs will be $10 a year.
a. What runs quantity should be used to minimize total annual costs?
b. How many days does it take to produce the optimal run quantity?
c. What is the average amount of inventory?
d. If the manager wants to run another job between runs of this item, and needs a minimum of 10 days per cycle for the other work, will there be enough time?
e. Given your answer to part d, the manager wants to explore options that will allow this other job to be performed using this equipment. Name three options the manager can consider.
f. Suppose the manager decides to increase the new size the new product. How many additional units would be needed to just accommodate the other job? How much will that increase the total annual cost?
a)
To determine: The run quantity to minimize the total cost.
Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.
Answer to Problem 11P
Explanation of Solution
Given information:
Formula:
Calculation of run quantity to minimize the total cost:
The optimal run size is calculated by dividing the product of 2 and 200,000 and 300 with 10 and taking square root which gives the resultant value as 1095 units and 200 is divided with the difference of 200 and 80 and square root is taken which gives 1.290, both values are multiplies which gives the optimal run size as 1414 units.
Hence, the run quantity to minimize the total cost is 1,414 units.
b)
To determine: The number of days to produce optimal run quantities.
Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.
Answer to Problem 11P
Explanation of Solution
Given information:
Formula:
Calculation of days to produce optimal run quantities:
The number of days to produce optimal run quantity is calculated by dividing 1,414 with 200 which gives 7.07 days.
Hence, the number of days to produce optimal run quantities is 7.70 days.
c)
To determine: The average inventory.
Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.
Answer to Problem 11P
Explanation of Solution
Given information:
Formula:
Calculation of average inventory:
The average inventory is calculated by dividing 848.4 by 2 which yields 424.2 units.
Hence, the average inventory is 424.2 units.
d)
To explain: Whether there is adequate time for another job between the run of items.
Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.
Answer to Problem 11P
Explanation of Solution
Given information:
Formula:
Calculation to check whether there is adequate time to do the job between the production batches:
The cycle time is calculated by dividing 1,414 with 80 which yields the resultant as 17.68 days.
The run time is calculated by dividing 1,414 by 200 and adding the resultant with setup time which yields 8.07 days.
Consumption time is calculated by subtracting cycle time of 17.68 with the consumption time of 8.07 which yields the resultant as 9.61 days which is not sufficient since other job requires 10 days.
Hence, there will not be adequate time for the other job.
e)
To explore: Three options for managers that will allow him to do other job.
Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.
Explanation of Solution
Given information:
Three options for managers that will allow him to do other job:
The three options for manager to explore the ways to do other jobs are,
- The setup time for other job can be shortened.
- Increase the run time of the new product which allows longer run time between runs which is there less need to run the component.
- Reducing the run time for other jobs.
f)
To determine: The addition units produced from the new product and the total annual cost.
Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.
Answer to Problem 11P
Explanation of Solution
Given information:
Formula:
Calculation of addition units produced from the new product and the total annual cost:
The additional units produced is computed by finding the value of Qp
Solving for Qp, we get the values as,
The additional units per run = 1,467 – 1,414 = 53 units per run.
The additional unit per run is calculated by subtracting 1,467 and 1,414 which gives 53 units per run.
Increase in total cost:
Difference in total cost:
The increase in total cost is calculated by calculating the difference between $8,490.98 and $8,485.28 which is $5.70 per year.
Hence, additional units produced and increase in cost is 53 units per run and $ 5.7 per year.
Want to see more full solutions like this?
Chapter 13 Solutions
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
- Quasi-Tech Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. Costs have been assigned to each activity using direct tracing and resource drivers as follows: Activity Expected Cost Activity Driver Activity Capacity Engineering $1,000,000 Engineering hours 5,000 hours Setups 900,000 Setups 200 setups Machining 2,000,000 Machine hours 25,000 machine hours Inspection 800,000 Inspection hours 2,500 inspection hours Quasi-Tech produces two models: Model C and Model D. The following table…arrow_forwardHP Computer's primary consumer business takes orders from customers for specific configurations of desktop and laptop computers. Customers must select from a certain model line of computer and choose from available parts, but within those constraints may customize the computer as they desire. Once the order is received, hp assembles the computer as ordered, and delivers it to the customer. What type of manufacturing process is described here?arrow_forwardPlease do not give solution in image formate thanku.arrow_forward
- what are the 4m's (manpower, machines, material, method) of manufacturingarrow_forwardWhat is the advantage of a simple segmentation that does not require loading all of the segments of a process by including the nonresident segments automatically when needed?arrow_forwardThe process train functions as a visual instrument that allows stakeholders to get a thorough comprehension of the production system and its dynamics. A process train has numerous advantages and may be applied in various ways. What are the important advantages and applications of employing a process trainarrow_forward
- Smooth Chin Device Company The Smooth Chin Device Company is a manufacturer of high--end electric razors. These razors are produced using a machine--paced process. For each razor, a tray with components enters the process at the beginning of a conveyor belt. The tray then passes through the six steps (consisting of various tasks) explained in the table below. Workers perform the assembly operations on the moving tray. The last step consists of an inspection of the then fully assembled razor. The activity times of the process are as follows: Station Tasks A Preparation 1. Lay out chassis [12 sec] 2. Lay out screws [15 sec] 3. Lay out all other components [17 sec] Total time for A: 44 sec B Assembly 4. Perform task AS1 [10 sec] 5. Perform task AS2 [10 sec] 6. Perform task AS3 [20 sec] Total time for B: 40 sec C Assembly 7. Perform task AS4 [14 sec] 8. Perform task AS5 [16 sec] 9. Perform task AS6 [20 sec] 10. Perform task AS7 [5 sec] Total time for C: 55 sec…arrow_forwardSmooth Chin Device Company The Smooth Chin Device Company is a manufacturer of high--end electric razors. These razors are produced using a machine--paced process. For each razor, a tray with components enters the process at the beginning of a conveyor belt. The tray then passes through the six steps (consisting of various tasks) explained in the table below. Workers perform the assembly operations on the moving tray. The last step consists of an inspection of the then fully assembled razor. The activity times of the process are as follows: Station Tasks A Preparation 1. Lay out chassis [12 sec] 2. Lay out screws [15 sec] 3. Lay out all other components [17 sec] Total time for A: 44 sec B Assembly 4. Perform task AS1 [10 sec] 5. Perform task AS2 [10 sec] 6. Perform task AS3 [20 sec] Total time for B: 40 sec C Assembly 7. Perform task AS4 [14 sec] 8. Perform task AS5 [16 sec] 9. Perform task AS6 [20 sec] 10. Perform task AS7 [5 sec] Total time for C: 55 sec…arrow_forwardThe term "plenty of processes" doesn't really explain what it means, does it? Is it feasible to say the same thing with less words yet still have the same meaning?arrow_forward
- 1. Goods assume the following characteristics, except a) customers do not help with their manufacturing b) their quality is easier to measure c) they are more likely to be unique d) they can be stored until needed manufacturing is easier to measure e) 2. An operations manager is not likely to be involved in a) the design of goods and services to satisfy customers' wants and needs b) the quality of goods and services to satisfy customers' wants and needs c) work scheduling to meet the due dates promised to customers d) maintenance schedules e) the identification of customers' wants and needs 3. The operations function is made up of many tasks including all of the following except a) Managing inventory b) Scheduling production c) Equipment acquisitions d) Designing jobs e) All of the abovearrow_forwardWhich of the following processes is ideal for automation? Select one: a. Auditing of supplier records b. Identifying preferred suppliers c. Matching supplier invoices to purchase orders and receiving reports d. Creation of a purchase orderarrow_forwardAnalyze a process flow with reworkarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.