Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
12th Edition
ISBN: 9781259580093
Author: William J Stevenson
Publisher: McGraw-Hill Education
bartleby

Videos

Textbook Question
Book Icon
Chapter 13, Problem 11P

A company is about to begin production of a new product. The manager of the department that will produce one of the components for the product wants to know how often the machine used to produce the item will be available for other work. The machine will produce the item at a rate of 200 units a day. Eighty units will be used daily in assembling the final product. Assembly will take place five days a week, 50 weeks a year. The manager estimates that it will take almost a full day to get the machine ready for a production nm, at a cost of $300. Inventory holding costs will be $10 a year.

a. What runs quantity should be used to minimize total annual costs?

b. How many days does it take to produce the optimal run quantity?

c. What is the average amount of inventory?

d. If the manager wants to run another job between runs of this item, and needs a minimum of 10 days per cycle for the other work, will there be enough time?

e. Given your answer to part d, the manager wants to explore options that will allow this other job to be performed using this equipment. Name three options the manager can consider.

f. Suppose the manager decides to increase the new size the new product. How many additional units would be needed to just accommodate the other job? How much will that increase the total annual cost?

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The run quantity to minimize the total cost.

Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.

Answer to Problem 11P

The run quantity to minimize the total cost is 1,414 units.

Explanation of Solution

Given information:

D=250days×80/day=20,000u=80/dayp=200/day

H=$10S=$300

Formula:

Qo=2DSH

Calculation of run quantity to minimize the total cost:

Qo=2×20,000×3001020020080=1,414units

The optimal run size is calculated by dividing the product of 2 and 200,000 and 300 with 10 and taking square root which gives the resultant value as 1095 units and 200 is divided with the difference of 200 and 80 and square root is taken which gives 1.290, both values are multiplies which gives the optimal run size as 1414 units.

Hence, the run quantity to minimize the total cost is 1,414 units.

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The number of days to produce optimal run quantities.

Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.

Answer to Problem 11P

The number of days to produce optimal run quantities are 7.70 days.

Explanation of Solution

Given information:

D=250days×80/day=20,000u=80/dayp=200/day

H=$10S=$300

Formula:

Daystoproduceoptimalrunquantity=Qpp

Calculation of days to produce optimal run quantities:

=1,414200=7.07days

The number of days to produce optimal run quantity is calculated by dividing 1,414 with 200 which gives 7.07 days.

Hence, the number of days to produce optimal run quantities is 7.70 days.

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The average inventory.

Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.

Answer to Problem 11P

The average inventory is 625 units.

Explanation of Solution

Given information:

D=250days×80/day=20,000u=80/dayp=200/day

H=$10S=$300

Formula:

Averageinventory=Imax2

Calculation of average inventory:

Imax=Qpp(pu)=1,414200(20080)= 848.4units

Averageinventory=848.42=424.2units

The average inventory is calculated by dividing 848.4 by 2 which yields 424.2 units.

Hence, the average inventory is 424.2 units.

d)

Expert Solution
Check Mark
Summary Introduction

To explain: Whether there is adequate time for another job between the run of items.

Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.

Answer to Problem 11P

There will not be adequate time for the other job.

Explanation of Solution

Given information:

D=250days×80/day=20,000u=80/dayp=200/day

H=$10S=$300

Formula:

Cycletime=Runtime+Consumptiontime

Calculation to check whether there is adequate time to do the job between the production batches:

Cycletime=Qpu=1,41480=17.68days

The cycle time is calculated by dividing 1,414 with 80 which yields the resultant as 17.68 days.

Runtime=Qpp+Setuptime=1,414200+1=8.07days

The run time is calculated by dividing 1,414 by 200 and adding the resultant with setup time which yields 8.07 days.

Cycletime=Runtime+consumptiontimeConsumptiontime=17.688.07=9.61days

Consumption time is calculated by subtracting cycle time of 17.68 with the consumption time of 8.07 which yields the resultant as 9.61 days which is not sufficient since other job requires 10 days.

Hence, there will not be adequate time for the other job.

e)

Expert Solution
Check Mark
Summary Introduction

To explore: Three options for managers that will allow him to do other job.

Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.

Explanation of Solution

Given information:

D=250days×80/day=20,000u=80/dayp=200/day

H=$10S=$300

Three options for managers that will allow him to do other job:

The three options for manager to explore the ways to do other jobs are,

  • The setup time for other job can be shortened.
  • Increase the run time of the new product which allows longer run time between runs which is there less need to run the component.
  • Reducing the run time for other jobs.

f)

Expert Solution
Check Mark
Summary Introduction

To determine: The addition units produced from the new product and the total annual cost.

Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.

Answer to Problem 11P

Additional units produced and increase in cost is 53 units per run and $5.7 per year.

Explanation of Solution

Given information:

D=250days×80/day=20,000u=80/dayp=200/day

H=$10S=$300

Formula:

Cycletime=Runtime+Consumptiontime

Calculation of addition units produced from the new product and the total annual cost:

The additional units produced is computed by finding the value of Qp

Cycletime=Runtime+ConsumptiontimeQp80=[Qp200+1]+10

Solving for Qp, we get the values as,

Qp=1467units

The additional units per run = 1,467 – 1,414 = 53 units per run.

The additional unit per run is calculated by subtracting 1,467 and 1,414 which gives 53 units per run.

Increase in total cost:

Imax=Qpp(pu)=1,467200(20080)= 880.2units

TC1,467=(Imax2)H+(DQ)S=(880.22)10+(20,0001,467)300=$4,401+$4,089.98=$8,485.28

TC1,414=(Imax2)H+(DQ)S=(848.22)10+(20,0001,414)300=$4,242+$4,243.28=$5.70/year

Difference in total cost:

Increase=$8,490.98$8,485.28=$5.70/year

The increase in total cost is calculated by calculating the difference between $8,490.98 and $8,485.28 which is $5.70 per year.

Hence, additional units produced and increase in cost is 53 units per run and $ 5.7 per year.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
A company is about to begin production of a new product. The manager of the department that will produce one of the components for the product wants to know how often the machine used to produce the item will be available for other work. The machine will produce the item at a rate of 200 units a day. Eighty units will be used daily in assembling the final product. Assembly will take place five days a week, 50 weeks a year. The manager estimates that it will take almost a full day to get the machine ready for a production run, at a cost of 300. Inventory holding costs will be a 10 a year. how many days does it take to produce the optimal run quanity?
Rapid Product Development (RPD) How would you improve the production rate of RPD? What are the advantages and disadvantages of RPD when compared to other traditional forming operations e.g casting, forging, extrusion etc.?
Suppose a final assembly is produced by assembling two components. THE The first component, A, is produced internally and goes through three process steps, which are stamping, forging and machining, with scrap estimates of 10%, 15% and 25%, respectively. For every three produced units of component A, two are used in the final assembly and one is separate to meet spare parts needs. The second component, B, which is used exclusively in final assembly, is purchased from a supplier external and inspected on arrival; 2% do not pass inspection. A unit of the component purchased is required for each final assembly. The final assembly process produces 5% of scraps. Spare parts demands for component A and final Su assembly match to 1,000 and 5,000 units, respectively. How many input units are needed for produce component A, and how many units of component B should the firm buy?

Chapter 13 Solutions

Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)

Ch. 13 - What is meant by the term service level? Generally...Ch. 13 - Describe briefly the A-B-C approach to inventory...Ch. 13 - The purchasing agent for a company that assembles...Ch. 13 - Explain how a decrease in setup time can lead to a...Ch. 13 - What is the single-period model, and under what...Ch. 13 - Can the optimal stocking level in the...Ch. 13 - Prob. 17DRQCh. 13 - What trade-offs are involved in each of these...Ch. 13 - Who needs to be involved in inventory decisions...Ch. 13 - How has technology aided inventory management? How...Ch. 13 - To be competitive, many fast-food chains began to...Ch. 13 - As a supermarket manager, how would you go about...Ch. 13 - Sam is at the post office to mail a package. After...Ch. 13 - Give two examples of unethical conduct involving...Ch. 13 - Prob. 1PCh. 13 - a. The following table contains figures on the...Ch. 13 - A bakery buys flours in 25-pound bags. The bakery...Ch. 13 - A large law firm uses an average of 40 boxes of...Ch. 13 - Garden Variety Flower Shop uses 750 clay pots a...Ch. 13 - A produce distributor uses 800 packing crates a...Ch. 13 - A manager receives a forecast for next year....Ch. 13 - A food processor uses approximately 27,000 glass...Ch. 13 - The Friendly Sausage Factory (FSF) can produce hot...Ch. 13 - A chemical firm produces sodium bisulfate in...Ch. 13 - A company is about to begin production of a new...Ch. 13 - Prob. 12PCh. 13 - A mail-order house uses 18,000 boxes a year....Ch. 13 - A jewelry firm buys semiprecious stones to make...Ch. 13 - A manufacturer of exercise equipment purchases the...Ch. 13 - A company will begin stocking remote control...Ch. 13 - A manager just received a new price list from a...Ch. 13 - A newspaper publisher uses roughly 800 feet of...Ch. 13 - Given this information: Expected demand during...Ch. 13 - Given this information: Lead-time demand = 600...Ch. 13 - Demand for walnut fudge ice cream at the Sweet...Ch. 13 - The injection molding department of a company uses...Ch. 13 - A company uses 85 circuit boards a day in a...Ch. 13 - One item a computer store sells is supplied by a...Ch. 13 - The manager of a car wash received a revised price...Ch. 13 - A small copy center uses five 500-sheet boxes of...Ch. 13 - Ned's Natural Foods sells unshelled peanuts by the...Ch. 13 - Regional Supermarket is open 360 days per year....Ch. 13 - A service station uses 1,200 cases of oil a year....Ch. 13 - Caring Hospital's dispensary reorders doses of a...Ch. 13 - A drugstore uses fixed-order cycles for many of...Ch. 13 - Prob. 32PCh. 13 - Prob. 33PCh. 13 - Demand for jelly doughnuts on Saturdays at Don's...Ch. 13 - A public utility intends to buy a turbine as part...Ch. 13 - Skinner's Fish Market buys fresh Boston bluefish...Ch. 13 - A small grocery store sells fresh produce, which...Ch. 13 - Demand for devil's food whipped-cream layer cake...Ch. 13 - Prob. 39PCh. 13 - Demand for rug-cleaning machines at Clyde's...Ch. 13 - A manager is going to purchase new processing...Ch. 13 - A Las Vegas supermarket bakery must decide how...Ch. 13 - Offwego Airlines has a daily flight from Chicago...Ch. 13 - UPD Manufacturing produces a range of health care...Ch. 13 - Prob. 1.2CQCh. 13 - Prob. 2.1CQCh. 13 - Grill Rite is an old-line company that started out...Ch. 13 - SARAH LUBBERS AND CHRIS RUSCHE, GRAND VALLEY STATE...Ch. 13 - SARAH LUBBERS AND CHRIS RUSCHE, GRAND VALLEY STATE...Ch. 13 - Prob. 4.3CQCh. 13 - SARAH LUBBERS AND CHRIS RUSCHE, GRAND VALLEY STATE...Ch. 13 - Prob. 4.5CQCh. 13 - Prob. 1OTQCh. 13 - Prob. 2OTQCh. 13 - Prob. 3OTQCh. 13 - Prob. 4OTQ
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Process selection and facility layout; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=wjxS79880MM;License: Standard YouTube License, CC-BY