Question
Chapter 12, Problem 3P
a)
Summary Introduction
To determine: The required units of Item B, if 40 units of end items are to be assembled.
Introduction: Materials requirement planning (MRP) is the planning or
b)
Summary Introduction
To determine: The latest week that the order can be started and still be ready to ship on time.
Introduction: Materials requirement planning (MRP) is the planning or scheduling system used in manufacturing process. It is used to manage the process efficiently.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Note:-
Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism.
Answer completely.
14.) A part structure, lead time (weeks), and on-hand quantities for product A are shown in Figure 14. From the information shown, generate:
a) An indented bell of material for product A.
b) Net requirements for each part to produce 10 As in week 8 using lot-for-lot.
Figure 14:
In each of the following, name the term defined or answer the question. Answers are listed at the bottom.
1. A term used for a computer system that integrates application programs for the different functions in a firm.
2. The logic used to calculate the needed parts, components, and other materials needed to produce an end item.3. This drives the MRP calculations and is a detailed plan for how we expect to meet demand.
4. Period of time during which a customer has a specified level of opportunity to make changes.
5. This identifies the specific materials used to make each item and the correct quantities of each.6. If an item is used in two places in a bill-of-materials, say level 3 and level 4, what low-level code would be assigned to the item?
Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The
lead time for B is three weeks. Sixty units of A are needed at the start of week 8. There are currently 15 units of B on hand and 130 of E
on hand, and 50 units of Hare in production and will be completed by the start of week 2. (Leave no cells blank - be certain to enter
"O" wherever required.)
B2)
D(2)
E(4)
HO
H3)
Master Schedule
Week
Quantity
Chapter 12 Solutions
EBK OPERATIONS MANAGEMENT
Ch. 12.11 - What is ERP?Ch. 12.11 - What are the three main reasons firms adopt ERP?Ch. 12.11 - What are some hidden costs of ERP?Ch. 12.11 - How does ERP fit with e-commerce and supply chain...Ch. 12 - Contrast independent and dependent demand.Ch. 12 - When is MRP appropriate?Ch. 12 - Briefly define or explain each of these terms: a....Ch. 12 - Prob. 4DRQCh. 12 - Prob. 5DRQCh. 12 - What is meant by the term safety time?
Ch. 12 - Prob. 7DRQCh. 12 - Briefly discuss the requirements for effective...Ch. 12 - Prob. 9DRQCh. 12 - How can the use of MRP contribute to productivity?Ch. 12 - Prob. 11DRQCh. 12 - What is lot sizing. what is its goal, and why is...Ch. 12 - Contrast planned-order receipts and scheduled...Ch. 12 - If seasonal variations are present, is their...Ch. 12 - Prob. 15DRQCh. 12 - What are some unforeseen costs of ERP?Ch. 12 - What trade-offs are involved in the decision to...Ch. 12 - Who in the organization needs to be involved in...Ch. 12 - Prob. 3TSCh. 12 - Prob. 1CTECh. 12 - Give one example of unethical behavior involving...Ch. 12 - a. Given the following diagram for a product,...Ch. 12 - Prob. 2PCh. 12 - Prob. 3PCh. 12 - Eighty units of end item E are needed at the...Ch. 12 - a. One hundred twenty units of end item Z are...Ch. 12 - A table is assembled using three components, as...Ch. 12 - Eighty units of end item X are needed at the...Ch. 12 - Oh No!, Inc., sells three models of radar detector...Ch. 12 - Assume that you are the manager of a shop that...Ch. 12 - Assume that you are the manager of Assembly, Inc....Ch. 12 - Determine material requirements plans for pans N...Ch. 12 - A firm that produces electric golf carts has just...Ch. 12 - Refer to Problem 12. Assume that unusually mild...Ch. 12 - Using the accompanying diagram, do the following:...Ch. 12 - A company that manufactures paving material for...Ch. 12 - Prob. 16PCh. 12 - The MRP Department has a problem. Its computer...Ch. 12 - Develop a material requirements plan for component...Ch. 12 - How many wheels sets should the manager order?Ch. 12 - When should the wheel sets be ordered?Ch. 12 - Prob. 2.1CQCh. 12 - Prob. 1OTQCh. 12 - Prob. 2OTQCh. 12 - Suppose the company has just received an order for...Ch. 12 - Prob. 4OTQCh. 12 - Prob. 5OTQ
Knowledge Booster
Similar questions
- Please do not give solution in image formate thanku.arrow_forwardThe following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount Direct Components on Hand End 1 0 L(2), C(1), K(3) L 1 10 B(2), J(3) C 2 14 G(2), B(2) K 2 19 H(4), B(2) B 1 34 J 2 25 G 2 7 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are needed? b. An order for the end item is scheduled to be shipped at the start of week 9. What is the latest week that the order can be started and still be ready to ship on time?arrow_forwardhelp please I need it to be done in excelarrow_forward
- In the following MRP planning schedule for Item J, indicate the correct net requirements, planned-order receipts, and planned-order releases to meet the gross requirements. Lead time is one week. Note: Leave the cells blank, whenever zero (0) is required. ITEM J Gross requirements On-hand Net requirements Planned-order receipt Planned-order release Item: J OH: 47 LT: 1 SS: 0 Q: L4L Period WEEK NUMBER 0 1 2 3 4 5 77 52 75 47 Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases 2 5 77 52 75arrow_forwardThe following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 11 B(2), J(3) C 3 15 G(2), B(2) K 3 20 H(4), B(2) B 2 25 J 3 34 G 3 3 H 2 0 Click here for the Excel Data File a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don’t need to develop an MRP plan.) b. An order for the end item is scheduled to be shipped at the start of week 11. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don’t need to develop an MRP plan.)arrow_forwardhello I need help with number 13 please and I need it only in excelarrow_forward
- The BOM for product A is given below:Assume the master schedule calls for 200 units of product A in week 5 and 250 units in week 6. a. Develop a materials plan for this product. b. What actions should be taken immediately? c. Project the inventory ahead for each part. d. If you were suddenly notified that part D will take three weeks to get instead of two weeks, what actions would you take?arrow_forwardIn the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank-be certain to enter "0" wherever required.) ITEM 3 Gross requirements On-hand Net requirements Planned order receipt Planned order release Period Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases WEEK NUMBER 2 3 76 4 48 76 5 72 48 72arrow_forwardPlease, I need a solution within 15 minutes.arrow_forward
- Your boss at Xiangling Hu Products, Inc., has just provided you with the schedule and lead times for the bracket. The unit is to be prepared in week 10. The lead times for the components a re bracket (I week), base (1 week), spring ( I week), clamp (I week), housing (2 weeks), handle (I week), casting (3 weeks), bearing (I week), and shaft (1 week).a) Prepare the time-phased product structure for the bracket.b) In what week do you need to start the castings?arrow_forwardDetermine the correct planned order release of Scissors. Determine the correct planned order release of Scissors. a. Day 5 600 b. Day 3 300 c. Day 3 600 d. Day 2 600 e. Day 4 300arrow_forwardPlease Simply fill out the chart answering the questionarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.