Using the accompanying diagram, do the following:
a. Draw a tree diagram for the scissors.
b. Prepare an MRP plan for scissors. Lead times are one day for each component and final scissor assembly, but two days for the plastic grips. Six hundred pairs of scissors are needed on day 6. Note: There are 200 straight blades and 350 bent blades on hand, and 40 top blade assemblies on hand.
Use lot-for-lot ordering for all items.
a)

To prepare: Tree diagram for the scissors.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
Lead-time is one day for all the components except plastic grips, which has the lead-time of 2 days. 600 pairs of scissors are needed on day 6. There are 350 bent blades, 200 straight blades, and 40 top blade assemblies on hand. Lot size is lot-for-lot ordering for all items.
In addition to that, following diagram is given:
Prepare tree diagram for the scissors using given diagram:
b)

To prepare: A Material requirement planning for scissors.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
Lead-time is one day for all the components except plastic grips, which has the lead-time of 2 days. 600 pairs of scissors are needed on day 6. There are 350 bent blades, 200 straight blades, and 40 top blade assemblies on hand. Lot size is lot-for-lot ordering for all items.
In addition to that, following diagram is given:
Develop material requirement planning for scissors:
- It is given that 600 pairs of scissors are needed on day 6.
- Beginning inventory is 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 600 units in week 6 (600-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 600 units in the beginning of Week 6. Hence, they need to order for 600 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 5.
Develop material requirement planning for bottom blade assembly:
- Scissor is the parent for bottom blade assembly. Hence, the planned order release of the scissor would be the gross requirement of the bottom blade assembly. As number of units required is 1 for bottom blade assembly, the planned order release row of scissor should be multiplied with 1 to attain the gross requirement column of bottom blade assembly.
- Beginning inventory is 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 600 units in week 5(600-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 600 units in the beginning of Week 5. Hence, they need to order for 600 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop material requirement planning for top blade assembly:
- Scissor is the parent for top blade assembly. Hence, the planned order release of the scissor would be the gross requirement of the top blade assembly. As number of units required is 1 for top blade assembly, the planned order release row of scissor should be multiplied with 1 to attain the gross requirement column of top blade assembly.
- Beginning inventory is 40 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 560 units in week 5 (600-40).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 560 units in the beginning of Week 5. Hence, they need to order for 560 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
- Projected on hand inventory for week 6 is 0 units. Calculation is as follows:
Develop material requirement planning for screw:
- Scissor is the parent for screw. Hence, the planned order release of the scissor would be the gross requirement of the screw. As number of units required is 1 for screw, the planned order release row of scissor should be multiplied with 1 to attain the gross requirement column of screw.
- Beginning inventory is 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 600 units in week 5 (600-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 600 units in the beginning of Week 5. Hence, they need to order for 600 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop material requirement planning for straight blade:
- Bottom blade assembly is the parent for straight blade. Hence, the planned order release of the bottom blade assembly would be the gross requirement of the straight blade. As number of units required is 1 for straight blade, the planned order release row of bottom blade assembly should be multiplied with 1 to attain the gross requirement column of straight blade.
- Beginning inventory is 200 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 400 units in week 4(600-200).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 400 units in the beginning of Week 4. Hence, they need to order for 400 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop material requirement planning for straight plastic grip:
- Bottom blade assembly is the parent for straight blade. Hence, the planned order release of the bottom blade assembly would be the gross requirement of the straight blade. As number of units required is 1 for straight blade, the planned order release row of bottom blade assembly should be multiplied with 1 to attain the gross requirement column of straight blade.
- Beginning inventory is 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 600 units in week 4 (600-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. Company requires 600 units in the beginning of Week 4. Hence, they need to order for 600 units (as the lot size is lot-for-lot) before two weeks (as the lead-time is 2 weeks). Thus, company need to order the required units in week 3.
Develop material requirement planning for bent blade:
- Top blade assembly is the parent for bent blade. Hence, the planned order release of the top blade assembly would be the gross requirement of the bent blade. As number of units required is 1 for bent blade, the planned order release row of top blade assembly should be multiplied with 1 to attain the gross requirement column of bent blade.
- Beginning inventory is 350 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 210 units in week 4 (560-350).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 210 units in the beginning of Week 4. Hence, they need to order for 210 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop material requirement planning for bent plastic grip:
- Top blade assembly is the parent for bent plastic grip. Hence, the planned order release of the top blade assembly would be the gross requirement of the bent plastic grip. As number of units required is 1 for bent plastic grip, the planned order release row of top blade assembly should be multiplied with 1 to attain the gross requirement column of bent plastic grip.
- Beginning inventory is 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 560 units in week 4 (560-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 560 units in the beginning of Week 4. Hence, they need to order for 560 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3
Want to see more full solutions like this?
Chapter 12 Solutions
EBK OPERATIONS MANAGEMENT
Additional Business Textbook Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Gitman: Principl Manageri Finance_15 (15th Edition) (What's New in Finance)
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Principles Of Taxation For Business And Investment Planning 2020 Edition
FUNDAMENTALS OF CORPORATE FINANCE
Financial Accounting, Student Value Edition (5th Edition)
- How can businesses integrate Petri Net modeling with Little's Law to enhance supply chain resilience, especially in unexpected disruptions such as supplier delays or demand fluctuations?arrow_forwardLearning Activity 5: Expansion in Global Markets Discussion Questions: Bubble (or “boba”) tea is a milky tea containing chewy tapioca balls. It is has gained huge popularity in markets across Asia and is now also in North America and Europe. In your view will the recent exponential growth continue, and will it be at the expense of other drinks such as traditional black or green tea or coffee? Can global markets continue to support its growth, and what age group is mainly targeted?arrow_forwardDyson, a high-tech home appliance maker, has cut ties with Malaysian supplier ATA IMS Bhd following an audit of the company's labour practices and allegations by a whistleblower. ATA is already under US investigation over forced labour allegations. Dyson has terminated its contracts and is in talks with its customer over the audit findings. ATA, which produces parts for Dyson's vacuum cleaners and air purifiers, tumbled 30% to its lowest since April 2020. The termination is a significant blow for Malaysia, a major electronics manufacturing hub, which has faced scrutiny this year over claims of abusive working and living conditions. Dyson terminated the relationship with six months' contractual notice, hoping it would give ATA the impetus to improve and enable an orderly withdrawal in the interests of the workers they employ. Former ATA worker Dhan Kumar Limbu was beaten by police in Malaysia after sharing information about conditions at the factory with activists. ATA denied all…arrow_forward
- Question content area Part 1 Oakwood Hospital is considering using ABC analysis to classify laboratory SKUs into three categories: those that will be delivered daily from their supplier (Class A items), those that will be controlled using a continuous review system (B items), and those that will be held in a two bin system (C items). The following table shows the annual dollar usage for a sample of eight SKUs. Fill in the blanks for annual dollar usage below. (Enter your responses rounded to the nearest whole number.) Part 2 Rank the SKUs in descending order on the basis of their annual dollar usage and fill in the table with the ranked SKU's percentage of dollar usage. (Enter your responses rounded to two decimal places.)arrow_forwardSam's Pet Hotel operates 51 weeks per year, 6 days per week, and uses a continuous review inventory system. It purchases kitty litter for $13.00 per bag. The following information is available about these bags: > Demand 70 bags/week > Order cost $58.00/order > Annual holding cost 30 percent of cost > Desired cycle-service level = 80 percent >Lead time 4 weeks (24 working days) > Standard deviation of weekly demand = 15 bags > Current on-hand inventory is 320 bags, with no open orders or backorders. a. Suppose that the weekly demand forecast of 70 bags is incorrect and actual demand averages only 45 bags per week. How much higher will total costs be, owing to the distorted EOQ caused by this forecast error? The costs will be $ higher owing to the error in EOQ. (Enter your response rounded to two decimal places.)arrow_forwarda. The average aggregate inventory value of the product if Ruby-Star used vendor 1 exclusively is $enter your response here. (Enter your response as a whole number.) b. The aggregate inventory value of the product if Ruby-Star used vendor 2 exclusively is shown below. c. How would your analysis change if average weekly demand increased to 160 units per week? The aggregate inventory values are shown below.arrow_forward
- a. What order quantity should be used? lures. (Enter your response rounded to the nearest whole number.) b. What reorder point should be used? (Enter your response rounded to the nearest whole number.) c. What is the total annual cost for this inventory system? (Enter your response rounded to two decimal places)arrow_forwardOakwood Hospital is considering using ABC analysis to classify laboratory SKUS into three categories: those that will be delivered daily from their supplier (Class A items), those that will be controlled using a continuous review system (B items), and those that will be held in a two bin system (C items). The following table shows the annual dollar usage for a sample of eight SKUS. Fill in the blanks for annual dollar usage below. (Enter your responses rounded to the nearest whole number.) SKU Unit Value Demand (units) Annual Dollar Usage 1 $1.10 30,000 $ 2 $0.02 125,000 $ 3 $0.20 65,000 S 4 $0.02 1,100 SA 5 $1.40 150 SA 678 $4.10 900 $ $0.80 350 $ $0.55 80 EA $arrow_forwardDyson, a high-tech home appliance maker, has cut ties with Malaysian supplier ATA IMS Bhd following an audit of the company's labour practices and allegations by a whistleblower. ATA is already under US investigation over forced labour allegations. Dyson has terminated its contracts and is in talks with its customer over the audit findings. ATA, which produces parts for Dyson's vacuum cleaners and air purifiers, tumbled 30% to its lowest since April 2020. The termination is a significant blow for Malaysia, a major electronics manufacturing hub, which has faced scrutiny this year over claims of abusive working and living conditions. Dyson terminated the relationship with six months' contractual notice, hoping it would give ATA the impetus to improve and enable an orderly withdrawal in the interests of the workers they employ. Former ATA worker Dhan Kumar Limbu was beaten by police in Malaysia after sharing information about conditions at the factory with activists. ATA denied all…arrow_forward
- Question 4 (25 Marks) Discuss how developing internal performance measures to track the performance of supplier development, can create efficiency for Pick n Pay.arrow_forwardLeadership and people Earlier this year, Pick n Pay actioned the first priority of the plan: the introduction of a new, simplified and seasoned leadership team with proven track records. The team has already implemented strengthened structures, including establishing regional trading areas with local decision-making, with clear sight of strong long-term succession Each operating region now has a regional buying team and store management team in place to meet specific customer needs particular to that region, while also increasing staff training and productivity for an overall improved store experience. Reset the store estate To create a more sustainable supermarket business, the Group is resetting its store estate to minimise losses by creating a smaller but more profitable Pick n Pay store estate. The plan is to leverage the strength of its multi-format model with strategic conversions to lift store profitability: selected Pick n Pay stores will be converted to Boxer, where customer…arrow_forwardQuestion 3 (25 Marks) Elaborate on how Pick n Pay could use information technology and ERP systems across the company and their suppliers to improve their operating model? Question 4 (25 Marks)arrow_forward
- Contemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage LearningPractical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning