Figure 11.32 shows a partially completed MPS record for 2-inch pneumatic control valves. Suppose that you receive the following orders at right for the valves (shown in the order of their arrival). As they arrive, you must decide whether to accept or reject them. Which orders would you accept for shipment?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
At the Lebanese factory "DELCO", John is using a system to produce the bar codes attached on the product bulks for identification. Each bulk contains 100 units of a certain product, and all the information related to the products inside the bulk are then represented by the barcode. Once prepared, the bulks are transferred to a very large warehouse and the location of each one is entered on the system. At a later stage, John uses the barcode in the warehouse to identify the right bulks for delivery, after being scanned using a special wireless barcode scanner. This way, John can decide in a better way how and when to make the shipments. This system helps John to save time and minimize the errors, and to perform his daily work in the most efficient way. On the other side, "DELCO" is facing a problem of late delivery to customers. In fact, dealing with hundreds of suppliers, wholesalers, and agents around the world makes this process very complicated. Most of the times, the shipments from…
Table B shows a partially completed MPS record for ball
Develop the MPS for ball
Four customer orders arrived in the following sequences (Table B).
Table A
Order
Quantity
Week desired
1
500
4
2
400
5
3
300
1
4
300
7
Assume that you must commit to the orders in the sequence of arrival and cannot change the desired shipping dates or your MPS. Which orders should you accept?
Table B
Item: Ball bearings
Quantity on hand: 400
Order policy: 500 units Lead time: 1 week
Week
1
2
3
4
5
6
7
8
9
10
Forecast
550
300
400
450
300
350
200
300
450
400
Customer order
booked
300
350
250
250
200
150
100
100
100
100
Projected on-hand
inventory
MPS
quantity
500
MPS start
Available to promise
(ATP)
snip
Chapter 11 Solutions
OPERATIONS MANAGEMENT CUSTOM ACCESS
Ch. 11 - Consider the master flight schedule of a major...Ch. 11 - For an organization of your choice, such as where...Ch. 11 - Consider a service provider that is in the...Ch. 11 - Complete the MPS record in Figure 11.29 for a...Ch. 11 - Complete the MPS record in Figure 11.30 for a...Ch. 11 - Prob. 3PCh. 11 - Figure 11.31 shows a partially completed MPS...Ch. 11 - Tabard Industries forecasted the following demand...Ch. 11 - Figure 11.32 shows a partially completed MPS...Ch. 11 - The forecasted requirements for an electric hand...
Ch. 11 - A forecast of 240 units in January, 320 units in...Ch. 11 - An end items demand forecasts for the next 6 weeks...Ch. 11 - An end items demand forecasts for the next 10...Ch. 11 - Consider the bill of materials (BOM) in Figure...Ch. 11 - Product A is made from components B, C, and D....Ch. 11 - What is the lead time (in weeks) to respond to a...Ch. 11 - Product A is made from components B and C. Item B,...Ch. 11 - Refer to Figure 11.23 and Solved Problem 1. If...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - Figure 11.38 shows a partially completed inventory...Ch. 11 - A partially completed inventory record for the...Ch. 11 - The BOM for product A is shown in Figure 11.40,...Ch. 11 - The BOMs for products A & B and data from the...Ch. 11 - Figure 11.42 illustrates the BOM for product A....Ch. 11 - The following information is available for three...Ch. 11 - Figure 11.44 shows the BOMs for two products, A...Ch. 11 - The BOM for product A is shown in Figure 11.45....Ch. 11 - Refer to Solved Problem 1 (Figure 11.23) for the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The McDuff Credit Union advertises their ability...Ch. 11 - Suppose that the POQ for item B is changed from 3...Ch. 11 - As the on-hand inventory for item C increases from...Ch. 11 - As the fixed order quantity (FOQ) for item D...Ch. 11 - As the lead time for item C changes, what happens...
Additional Business Textbook Solutions
Find more solutions based on key concepts
What is precedent, and how does it affect common law?
Business in Action (8th Edition)
What are the three major business functions, and how are they related to one another? Give specific examples.
Operations Management, Binder Ready Version: An Integrated Approach
The flowchart for the process at the local car wash. Introduction: Flowchart: A flowchart is a visualrepresenta...
Principles Of Operations Management
2. In what circumstances might a market-pull approach or a technology-push approach to new-product design be th...
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Many companies including Company OM tried to implement dynamic pricing in their ticketing system. The dynamic p...
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- These are orders that have already been released and are to arrive in the future.arrow_forwardFigure shows a partially completed MPS record for 2 inch pneumatic control valves. Suppose that you receive the following orders at right for the valves (shown in the order of their arrival). As they arrive, you must decide whether to accept or reject them. Which orders would you accept for shipment?Order Amount (Units) Week Requested1 15 22 30 53 25 34 75 7arrow_forwardRead the email and write a short paragraph as a resale (around 50 - 70 words). Specify if it would be 1st, 2nd, 3rd or 4th paragraph. Write a number before the paragraph. For example: "1st As I fully understand..." Subject: Late Delivery and Damaged/Missing Products Dear SuperSonic Customer Support Team, I am writing to express my deep dissatisfaction with the recent order I placed through your Kuwait website. Unfortunately, I have encountered multiple issues, including a significant delay in delivery, a damaged product, and a missing item. On October 12th, I made a purchase for a tablet pc and a charger both of which were expected to be delivered promptly. However, I have yet to receive the tracking number email, even though the items have already been delivered. Furthermore, the delivery itself was delayed by two weeks, causing inconvenience and frustration. To my dismay, upon receiving the package, I discovered that the tablet pc had a visible crack running down the middle (refer to…arrow_forward
- q3arrow_forwardCan you assist me with Problem 7 errors. Thank you greatlyarrow_forwardAssume that Product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. B is made of three units of E. If 50 units of Z is required to make, then how many units of D do they need? Group of answer choices 250 400 300 150 550arrow_forward
- Heather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 8. Subscripts indicate quantity required for each parent. Assume lot-for-lot ordering. b. Choose correct time phased-structures c. Develop a net material requirements plan for F (enter your responses as whole numbers).arrow_forwardEach Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level 0 kits. Complete the MRP records, using the following information: • Production plans for complete kits are as follows: Start assembling 4,500 kits in week 2 Start assembling 1,000 kits in weeks 3, 4, and 5 Start assembling 8,000 kits in week 6 • The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements. • All scheduled receipts, lead times, and beginning inventory levels are shown. Click the icon to view the MRP records. Construct the material requirements plan for item System unit (enter your responses as whole numbers). System unit: Lead Time = 1 week; Minimum order quantity = 3,500 Week 1 2 3 Gross requirements 4,500 1,000…arrow_forwardPlease resolve within 15 minutes or 25 minutes. Please, pleasearrow_forward
- The sales department receives all orders from the customers. While receiving the order, the sales team authorizes the payment and check line items. If authorization is failed, a cancelation message is sent to the customer. On the other hand, each line item is checked with the stock. If it is in stock, assigned to the order otherwise the item is removed from the list. If stocks are available for all products and payment is authorized, the sales team dispatched the order.Shipping teams ship the order to the customer. The method of delivery is decided conditionally. Depending on the condition either the Urgent Delivery activity or the Regular Delivery activity is performed. The delivery procedure is finished when the customer receives it and signs in. Draw an Activity diagram based on the above scenario.arrow_forwardWhat is the best approach to ERP system testing?arrow_forward1.1 discuss the four benefits of an MRP system in relation to apple benefits: expediting is eliminated outstanding orders are decreased closer relationship with suppliers and other departments are formed the production schedules are based on actual demand and forecast 1.2 discuss how the just in time inventory system could benefit apple explain the benefits first benefits: it reduces lot sizes required in production and purchasing It decreases setup times it reduces lead times it encourages preventative maintenance of the inventory control systemarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY