OPERATIONS MANAGEMENT CUSTOM ACCESS
OPERATIONS MANAGEMENT CUSTOM ACCESS
11th Edition
ISBN: 9780135622438
Author: KRAJEWSKI
Publisher: PEARSON EDUCATION (COLLEGE)
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 11, Problem 24P

The following information is available for three MPS items:

Chapter 11, Problem 24P, The following information is available for three MPS items: Develop the material requirements plan , example  1

Develop the material requirements plan for the next 6 weeks for items D, E, and F. The BOMs are shown in Figure 11.43, and data from the inventory records are shown in Table 11.11. (Warning: A safety stock requirement applies to item F. Be sure to plan a receipt for any week in which the projected on-hand inventory becomes less than the safety stock.)

Chapter 11, Problem 24P, The following information is available for three MPS items: Develop the material requirements plan , example  2

Blurred answer
Students have asked these similar questions
Complete the following table. Lead time for the part is 2 weeks, and the order quantity is 50. What action should be taken?
Figure shows the BOMs for two products, A and B. Table 1 shows the MPS quantity start date for each one. Table 2 contains data from inventory records for items C, D, and E. There are no safety stock requirements for any of the items.a. Determine the material requirements plan for items C, D, and E for the next 8 weeks.b. What specific managerial actions are required in week 1?c. Suppose that a very important customer places an emergency order for a quantity of product A. To satisfy this order, a new MPS of 200 units of product A is now required in week 5. Determine the changes to the material requirements plan if this order is accepted and note any problems that you detect. MPS Quantity Start Dates   Date Product 1 2 3 4 5 6 7 8 A   125   95   150   130 B     80     70       Inventory Record Data   Item Data Category C D E Lot-sizing rule L4L POQ 1P = 32 FOQ = 800 Lead time 3 weeks 2 weeks 1 weeks Scheduled receipts 200 (week 2) None 800 (week 1) Beginning…
The table given below shows a partially completed MPS record for product A. What is the remaining ATP inventory (discrete) for week 7 after the company receives a 20 units of customer order for week 6? Order policy: 60 units Lead time: 1 week Item: A Quantity on hand: 30 Week 3 30 7. 34 11 4. Forecast requirements Customer orders (booked) Projected on-hand inventory MPS quantity MPS start ATP inventory 22 24 18 27 36 28 26 12 24 O a 59 Ob. 29 OcO Od. 49 Oe. 39

Chapter 11 Solutions

OPERATIONS MANAGEMENT CUSTOM ACCESS

Ch. 11 - A forecast of 240 units in January, 320 units in...Ch. 11 - An end items demand forecasts for the next 6 weeks...Ch. 11 - An end items demand forecasts for the next 10...Ch. 11 - Consider the bill of materials (BOM) in Figure...Ch. 11 - Product A is made from components B, C, and D....Ch. 11 - What is the lead time (in weeks) to respond to a...Ch. 11 - Product A is made from components B and C. Item B,...Ch. 11 - Refer to Figure 11.23 and Solved Problem 1. If...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - Figure 11.38 shows a partially completed inventory...Ch. 11 - A partially completed inventory record for the...Ch. 11 - The BOM for product A is shown in Figure 11.40,...Ch. 11 - The BOMs for products A & B and data from the...Ch. 11 - Figure 11.42 illustrates the BOM for product A....Ch. 11 - The following information is available for three...Ch. 11 - Figure 11.44 shows the BOMs for two products, A...Ch. 11 - The BOM for product A is shown in Figure 11.45....Ch. 11 - Refer to Solved Problem 1 (Figure 11.23) for the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The McDuff Credit Union advertises their ability...Ch. 11 - Suppose that the POQ for item B is changed from 3...Ch. 11 - As the on-hand inventory for item C increases from...Ch. 11 - As the fixed order quantity (FOQ) for item D...Ch. 11 - As the lead time for item C changes, what happens...

Additional Business Textbook Solutions

Find more solutions based on key concepts
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY