MyLab Operations Management with Pearson eText -- Access Card -- for Operations Management: Processes and Supply Chains
12th Edition
ISBN: 9780134742366
Author: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 11, Problem 19P
Figure 11.38 shows a partially completed inventory record for the rear wheel subassembly. Gross requirements,
- Complete the last three rows of the record for an FOQ of 200 units.
- Complete the last three rows of the record by using an FOQ of 100 units.
- Complete the last three rows of the record by using the L4L rule.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Table B shows a partially completed MPS record for ball
Develop the MPS for ball
Four customer orders arrived in the following sequences (Table B).
Table A
Order
Quantity
Week desired
1
500
4
2
400
5
3
300
1
4
300
7
Assume that you must commit to the orders in the sequence of arrival and cannot change the desired shipping dates or your MPS. Which orders should you accept?
Table B
Item: Ball bearings
Quantity on hand: 400
Order policy: 500 units Lead time: 1 week
Week
1
2
3
4
5
6
7
8
9
10
Forecast
550
300
400
450
300
350
200
300
450
400
Customer order
booked
300
350
250
250
200
150
100
100
100
100
Projected on-hand
inventory
MPS
quantity
500
MPS start
Available to promise
(ATP)
Heather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 8. Subscripts indicate quantity required for each parent. Assume lot-for-lot ordering.
b. Choose correct time phased-structures
c. Develop a net material requirements plan for F (enter your responses as whole numbers).
MRP Logic
13. Item A has a gross requirement for 1,000 in week 5. There are currently 300 of the
item on hand, with a scheduled receipt of 100 items in week 2. The order quantity is
lot for lot, and there is a two-week lead time. Complete the MRP record for item A.
Chapter 11 Solutions
MyLab Operations Management with Pearson eText -- Access Card -- for Operations Management: Processes and Supply Chains
Ch. 11 - Consider the master flight schedule of a major...Ch. 11 - For an organization of your choice, such as where...Ch. 11 - Consider a service provider that is in the...Ch. 11 - Complete the MPS record in Figure 11.29 for a...Ch. 11 - Complete the MPS record in Figure 11.30 for a...Ch. 11 - Prob. 3PCh. 11 - Figure 11.31 shows a partially completed MPS...Ch. 11 - Tabard Industries forecasted the following demand...Ch. 11 - Figure 11.32 shows a partially completed MPS...Ch. 11 - The forecasted requirements for an electric hand...
Ch. 11 - A forecast of 240 units in January, 320 units in...Ch. 11 - An end items demand forecasts for the next 6 weeks...Ch. 11 - An end items demand forecasts for the next 10...Ch. 11 - Consider the bill of materials (BOM) in Figure...Ch. 11 - Product A is made from components B, C, and D....Ch. 11 - What is the lead time (in weeks) to respond to a...Ch. 11 - Product A is made from components B and C. Item B,...Ch. 11 - Refer to Figure 11.23 and Solved Problem 1. If...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - Figure 11.38 shows a partially completed inventory...Ch. 11 - A partially completed inventory record for the...Ch. 11 - The BOM for product A is shown in Figure 11.40,...Ch. 11 - The BOMs for products A & B and data from the...Ch. 11 - Figure 11.42 illustrates the BOM for product A....Ch. 11 - The following information is available for three...Ch. 11 - Figure 11.44 shows the BOMs for two products, A...Ch. 11 - The BOM for product A is shown in Figure 11.45....Ch. 11 - Refer to Solved Problem 1 (Figure 11.23) for the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The McDuff Credit Union advertises their ability...Ch. 11 - Suppose that the POQ for item B is changed from 3...Ch. 11 - As the on-hand inventory for item C increases from...Ch. 11 - As the fixed order quantity (FOQ) for item D...Ch. 11 - As the lead time for item C changes, what happens...
Additional Business Textbook Solutions
Find more solutions based on key concepts
What are the three major business functions, and how are they related to one another? Give specific examples.
Operations Management, Binder Ready Version: An Integrated Approach
2. Identify four people who have contributed to the theory and techniques of operations management.
Operations Management: Sustainability and Supply Chain Management (12th Edition)
2. Identify four people who have contributed to the theory and techniques of operations management.
Operations Management
2. In what circumstances might a market-pull approach or a technology-push approach to new-product design be th...
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Feeding America Each year, the Feeding America network helps provide food to more than 46 million people facing...
Operations and Supply Chain Management 9th edition
What is precedent, and how does it affect common law?
Business in Action
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Projected sales for Vehicle Z are 534,000 units. Current inventory is 121,000 units and the inventory target is 30 days. What should the scheduled production be? Round to the nearest whole unit.arrow_forwardConsider the bill of materials (BOM) shown to the right. Part 2 If inventory consists of 33 units of B, 11 unitunit of F, and 33 units of G, how many units of G, E, and D must be purchased to produce 55 units of product A? enter your response here unit(s) of item G, enter your response here units of item E, and enter your response here units of item D. (Enter your responses as integers.)arrow_forwardComplete the following MRP record. Note that the minimum order quantity is 200. What is the average ending inventory over the six weeks? Click the icon to view the MRP record. Complete the material requirements plan (enter your responses as whole numbers). Week ***B3*** LT(weeks) = 1 ample Get more help. Min. order = 200 More Info Week ***B3*** LT(weeks) = 1 Min. order = 200 Gross requirements Scheduled receipts Projected ending inventory: 50 Net requirements Planned receipts Gross requirements Scheduled receipts Projected ending inventory: 50 Net requirements Planned receipts Planned orders Print 1 0 1 0 ☐☐☐ 2 500 2 500 Done 3 450 3 450 4 500 4 500 5 200 5 200 6 250 ☐☐☐ 6 250 - X r allarrow_forward
- Shown below is a partially completed MPS record for ball bearings. a. Develop the MPS for ball bearings. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: Ball bearings Quantity on Hand: 400 Forecast Customer orders (booked) Projected on-hand inventory MPS quantity MPS start 1 550 300 350 500 2 250 350 0 0 3 450 250 50 500 4 450 200 100 500 Order Policy: 500 units Lead Time: 1 week Week 5 250 150 350 500 6 400 100 450 500 7 200 50 250 0 8 250 100 To o 9 450 50 50 10 450 150 100 500 500arrow_forwardPlease do fastarrow_forwardThe following Table 1 presents the results of the XYZ Company's ERP system for expenditure cycle activities. It shows the number of times each employee performed a specific task. Table 1 Employee A Employee B Employee C Employee D Employee E Employee F Employee G Employee H Employee 1 Order Inventory 150 306 Maintain Supplier Master File (add, delete, edit) 7 Receive Inventory 425 300 Approve Supplier Invoices for Payment 5 10 10 400 Pay Suppliers Via EFT 100 10 Sign Mail Checks Checks 100 10 150 100 125 25 Reconcile Bank Account 1 Requirements: 1. Ready and exam the information provided in Table 1, and pay attention to the tasks performed by each employee (Hint: which employee performed what tasks?) 2. Identify 5 cases where the segregation of duties was violated as employees performed their tasks (Hint: at least 5 employees violated segregation of duties). 3. Then, use Table 2 (provided in next page) to complete this assignment. 4. For each case you have identified, answer questions…arrow_forward
- Coleman Rich, Ltd., has received the followingorders: The entire fabrication for these units is scheduled on onemachine. There are 2,250 usable minutes in a week, and eachunit will take 65 minutes to complete. Develop a capacityplan, using lot splitting, for the 10-week time periodarrow_forwardOh No!, Inc., sells three models of radar detector units. It buys the three basic models (E, F, and G)from a Japanese manufacturer and adds one, two, or four lights (component DLead times are one week for all items except C, which is two weeks. There are ample suppliesof the basic units (E, F, and G) on hand. There are also 10 units of B, 10 units of C, and 25 units ofD on hand. Lot-sizing rules are lot-for-lot ordering for all items except D, which must be ordered inmultiples of 100 units. There is a scheduled receipt of 100 units of D in week 1.The master schedule calls for 40 units of A in week 4, 60 units of B in week 5, and 30 units of Cin week 6. Prepare a material requirements plan for D and its parents) to further differentiate the models. D is bought from a domestic producer.arrow_forwardComplete the MPS record below for a single item. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: A Quantity on Hand: 80 Forecast Customer orders (booked) Projected on-hand inventory MPS quantity 1 70 40 ☐☐ January 2 70 65 80 Order Policy: 100 units Lead Time: 1 week February Week 4 40 0 5 45 35 50 70 45 0 8 50 0arrow_forward
- Ripeka, the warehouse manager at Hine would like to update the company’s inventory locator system so that the picking operation can be streamlined. While conceptually simple to do, she knows that there will be several steps to the update process that will have to be carefully managed. She needs to complete upgrade and train her staff in operating the new system before the busy season, which is only 4 months away. She identifies the various activities, expected time duration, predecessors and costs, as shown in the table. Identify the project cost. Ripeka is interested to complete the project three weeks early before starting the busy season. How much additional cost the project will incur for completing the project three weeks early?arrow_forwardRipeka, the warehouse manager at Hine would like to update the company’s inventory locator system so that the picking operation can be streamlined. While conceptually simple to do, she knows that there will be several steps to the update process that will have to be carefully managed. She needs to complete upgrade and train her staff in operating the new system before the busy season, which is only 4 months away. She identifies the various activities, expected time duration, predecessors and costs, as shown in the table. Draw the AON Network, and then determine the critical path. [Show your workings, using the grid network.] Identify the project duration – is this project feasible within the required timeframe?arrow_forwardsniparrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY