Phono Company manufactures a plastic toy cell phone. The following standards have been established for the toys materials and labor inputs:
During the first week of July, the company had the following results:
The purchasing agent located a new source of slightly higher-quality plastic, and this material was used during the first week in July. Also, a new manufacturing layout was implemented on a trial basis. The new layout required a slightly higher level of skilled labor. The higher-quality material has no effect on labor utilization. Similarly, the new manufacturing approach has no effect on material usage. (Note: Round all variances to the nearest dollar.)
Required:
- 1. CONCEPTUAL CONNECTION Compute the materials price and usage variances. Assuming that the materials variances are essentially attributable to the higher quality of materials, would you recommend that the purchasing agent continue to buy this quality, or should the usual quality be purchased? Assume that the quality of the end product is not affected significantly.
- 2. CONCEPTUAL CONNECTION Compute the labor rate and efficiency variances. Assuming that the labor variances are attributable to the new manufacturing layout, should it be continued or discontinued? Explain.
- 3. CONCEPTUAL CONNECTION Refer to Requirement 2. Suppose that the industrial engineer argued that the new layout should not be evaluated after only one week. His reasoning was that it would take at least a week for the workers to become efficient with the new approach. Suppose that the production is the same the second week and that the actual labor hours were 13,200 and the labor cost was $132,000. Should the new layout be adopted? Assume the variances are attributable to the new layout. If so, what would be the projected annual savings?
1.
Calculate the value of material price variance and material usage variance. Identify whether the plant manger could continue to purchase this quality product or purchase the usual quality.
Explanation of Solution
Variance:
The amount obtained when actual cost is deducted from budgeted cost is known as variance. Variance is calculated to find whether the cost is over applied or under applied.
Use the following formula to calculate material price variance:
Substitute $1.55 for actual price, 44,250 units for actual quantity and $1.50 for standard price in the above formula.
Therefore, the material price variance is $2,213(U).
Use the following formula to calculate material usage variance:
Substitute $1.50 for standard price, 44,250 units for actual quantity and 45,000 for standard quantity in the above formula.
Therefore, the material usage variance is $1,125(F).
The total variance is $1,088(U)
Working Note:
1. Calculation of standard quantity:
2.
Calculate the value of labor rate variance and labor efficiency variance. Identify whether the labor variances are attributable to the new manufacturing process should be continued or discontinued.
Explanation of Solution
Use the following formula to calculate labor rate variance:
Substitute $138,000 for actual cost, 10,800 hours for actual hours and $10 for standard rate in the above formula.
Therefore, the labor rate variance is $4,000(U).
Use the following formula to calculate labor efficiency variance:
Substitute $10.00 for standard rate, 13,400 hours for actual hours and 13,500 hours for standard hours in the above formula.
Therefore, the labor efficiency variance is $1,000(F).
The total labor variance is $3,000 (U)
Working Note:
1. Calculation of standard hours:
3.
Calculate the value of labor rate variance and labor efficiency variance. Identify whether the new process should be adopted.
Explanation of Solution
Use the following formula to calculate labor rate variance:
Substitute $132,000 for actual cost, 13,200 hours for actual hours and $10 for standard rate in the above formula.
Therefore, the labor rate variance is $0.
Use the following formula to calculate labor efficiency variance:
Substitute $10 for standard rate, 13,200 hours for actual hours and 13,500 hours for standard hours in the above formula.
Therefore, the labor efficiency variance is $3,000(F).
The total labor variance is $3,000 (F)
Working Note:
1. Calculation of standard hours:
Want to see more full solutions like this?
Chapter 10 Solutions
Managerial Accounting
- Company Name Price Variable manufacturing costs Fixed manufacturing costs Variable selling costs Fixed administrative costs Avocado Co 50 15 3,000 5 1,000 Banana Co 60 18 2,000 9 1,000 Cherry Co 35 8 4,000 2 2,000 Answer these questions 1. Which company has the lowest variable cost? 2. Which company has the lowest fixed cost? 3. Which company has the lowest breakeven point in units? 4. What is the breakeven point in units for the…arrow_forwardMatthew Incorporated, owns 30 percent of the outstanding stock of Lindman Company and has the ability to significantly influence the investee's operations and decision making. On January 1, 2024, the balance in the Investment in Lindman account is $335,000. Amortization associated with this acquisition is $9,000 per year. In 2024, Lindman earns an income of $90,000 and declares cash dividends of $30,000. Previously, in 2023, Lindman had sold inventory costing $24,000 to Matthew for $40,000. Matthew consumed all but 25 percent of this merchandise during 2023 and used the rest during 2024. Lindman sold additional inventory costing $28,000 to Matthew for $50,000 in 2024. Matthew did not consume 40 percent of these 2024 purchases from Lindman until 2025. Required: a. What amount of equity method income would Matthew recognize in 2024 from its ownership interest in Lindman? b. What is the equity method balance in the Investment in Lindman account at the end of 2024? a. Equity income b.…arrow_forwardPlease solve.arrow_forward
- Managerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning