Chapter 10, Problem 22P
Summary Introduction

To determine: The standard time for the operation

Introduction: Time study is the basis that helps set the standard time; it would time a sample of the performance of the worker.

Expert Solution & Answer
Check Mark

Answer to Problem 22P

Thestandard time is calculated as 10.12 minutes.

Explanation of Solution

Given information:

The allowance factor is given as 10%. The observed time and performance rating for each element is given as follows:

Element Performance rating Observation (minutes per cycle)
1 2 3 4 5
Check mini-bar 100 1.5 1.6 1.4 1.5 1.5
Make one bed 90 2.3 2.5 2.1 2.2 2.4
Vacuum floor 120 1.7 1.9 1.9 1.4 1.6
Clean bath 100 3.5 3.6 3.6 3.6 3.2

Formulae to calculate the standard time:

Average time=Observed times for gift-wrappingn

Normal time=Average time×Performance rating

Standard time=Normal time1Allowance factor

Calculate the standard time:

Element Performance rating Observation (minutes per cycle) Average time Normal time
1 2 3 4 5
Check mini-bar 100% 1.5 1.6 1.4 1.5 1.5 1.5 1.5
Make one bed 90% 2.3 2.5 2.1 2.2 2.4 2.3 2.07
Vacuum floor 120% 1.7 1.9 1.9 1.4 1.6 1.7 2.04
Clean bath 100% 3.5 3.6 3.6 3.6 3.2 3.5 3.5
Total 9.11

Excel worksheet:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 10, Problem 22P

Calculate the average time to check mini-bar:

The average time is calculated by taking an average of the observation given, which is a summation of 1.5, 1.6, 1.4, 1.5, and 1.5 and dividing the result by 5. Hence, the average is 1.5 minutes.

Average time=Observationn=1.5+1.6+1.4+1.5+1.55=7.55=1.5 minutes

Calculate the average time to make one bed:

The average time is calculated by taking an average of the observation given, which is summation of 2.3, 2.5, 2.1, 2.2, and 2.4 and dividing the result by 5. Hence, the average is 2.3 minutes.

Average time=Observationn=2.3+2.5+2.1+2.2+2.45=11.55=2.3 minutes

Calculate the average time to vacuum floor:

The average time is calculated by taking an average of the observation given, which is summation of 1.7, 1.9, 1.9, 1.4, and 1.6 and dividing the result by 5. Hence, the average is 1.7 minutes.

Average time=Observationn=1.7+1.9+1.9+1.4+1.65=8.55=1.7 minutes

Calculate the average time to clean bath:

The normal average time is calculated by taking an average of the observation given, which is summation of 3.5, 3.6, 3.6, 3.6, and 3.2 and dividing the result by 5. Hence, the average is 3.5 minutes.

Average time=Observationn=3.5+3.6+3.6+3.6+3.25=17.55=3.5 minutes

Calculate the normal time to check mini-bar:

The normal time is calculated by multiplying average time and performance rating. The average time is given as 1.5 minutes, and performance rating is given as 100%. Hence, the normal time is 1.5 minutes.

Normal time=Average time×Performance rating=1.5×100%=1.5×1=1.5 minutes

Calculate the normal time to make one bed:

The normal time is calculated by multiplying average time and performance rating. The average time is given as 2.3 minutes, and performance rating is given as 90%. Hence, the normal time is 2.07 minutes.

Normal time=Average time×Performance rating=2.3×90%=2.3×0.9=2.07 minutes

Calculate the normal time to vacuum floor:

The normal time is calculated by multiplying average time and performance rating. The average time is given as 1.7 minutes, and performance rating is given as 120%. Hence, the normal time is 2.04 minutes.

Normal time=Average time×Performance rating=1.7×120%=1.7×1.2=2.04 minutes

Calculate the normal time to clean bath:

The normal time is calculated by multiplying average time and performance rating. The average time is given as 3.5 minutes, and performance rating is given as 100%. Hence, the normal time is 3.5 minutes.

Normal time=Average time×Performance rating=3.5×100%=3.5×1=3.5 minutes

Calculate the total normal time:

The normal time is calculate by adding the normal time to check the mini-bar, make one bed, vacuum floor, and clean bath.

Normal time=Sum of normal times=1.5+2.07+2.04+3.5=9.11 minutes

Hence, the total normal time is 9.11 minutes.

Calculate the standard time:

The standard time is calculated by dividing the normal time with the value attained by subtracting the allowance factor from 1. Normal time is calculated as 9.11 minutes and the allowance factor is calculated as 0.10 or 10%.

Standard time=Normal time1Allowance factor=9.11 minutes10.10=9.11 minutes0.9=10.12 minutes

Hence, the standard time is 10.12 minutes.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Galaxy Co. sells virtual reality (VR) goggles, particularly targeting customers who like to play video games. Galaxy procures each pair of goggles for $150 from its supplier and sells each pair of goggles for $300. Monthly demand for the VR goggles is a normal random variable with a mean of 157 units and a standard deviation of 41 units. At the beginning of each month, Galaxy orders enough goggles from its supplier to bring the inventory level up to 140 goggles. If the monthly demand is less than 140, Galaxy pays $20 per pair of goggles that remains in inventory at the end of the month. If the monthly demand exceeds 140, Galaxy sells only the 140 pairs of goggles in stock. Galaxy assigns a shortage cost of $40 for each unit of demand that is unsatisfied to represent a loss-of-goodwill among its customers. Management would like to use a simulation model to analyze this situation. (Use at least 1,000 trials.) (a) What is the average monthly profit (in dollars)? (Round your answer to the…
Hospital administrators must schedule nurses so that the hospital's patients are provided adequate care. At the same time, careful attention must be paid to keeping costs down. From historical records, administrators can project the minimum number of nurses required to be on hand for various times of day and days of the week. The objective is to find the minimum total number of nurses required to provide adequate care. Nurses start work at the beginning of one of the four-hour shifts given below (except for shift 6) and work for 8 consecutive hours. Hence, possible start times are the start of shifts 1 through 5. Also, assume that the projected required number of nurses factors in time for each nurse to have a meal break. Formulate and solve the nurse scheduling problem as an integer program for one day for the data given below. (Let x = number of nurses who start work at the beginning of shift t, t = 1, 2, 3, 4, 5.) Shift Time Minimum Number of Nurses Needed 1 12:00 A.M. - 4:00 A.M.…
The Kolkmeyer Manufacturing Company uses a group of six identical machines, each of which operates an average of 23 hours between breakdowns. With randomly occurring breakdowns, the Poisson probability distribution is used to describe the machine breakdown arrival process. One person from the maintenance department provides the single-server repair service for the six machines. Management is now considering adding two machines to its manufacturing operation. This addition will bring the number of machines to eight. The president of Kolkmeyer asked for a study of the need to add a second employee to the repair operation. The service rate for each individual assigned to the repair operation is 0.40 machines per hour. (a) Compute the operating characteristics if the company retains the single-employee repair operation. (Round your answers to four decimal places. Report time in hours.) W L = q W = ✓ X h × h (b) Compute the operating characteristics if a second employee is added to the…
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning
Text book image
Management, Loose-Leaf Version
Management
ISBN:9781305969308
Author:Richard L. Daft
Publisher:South-Western College Pub
Text book image
Foundations of Business (MindTap Course List)
Marketing
ISBN:9781337386920
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Text book image
Foundations of Business - Standalone book (MindTa...
Marketing
ISBN:9781285193946
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning