Question
Chapter 10, Problem 4CS
Summary Introduction
Case summary:
Person K is the vice-president of operations at Company J, which received a request for quote of supplying 400 units per week. Employee must be permitted to perform the task for 17 times. The actual times observed were given below:
Number | Actual time (minutes) |
1 | 2.05 |
2 | 1.92 |
3 | 2.01 |
4 | 1.89 |
5 | 1.77 |
6 | 1.8 |
7 | 1.86 |
8 | 1.83 |
9 | 1.93 |
10 | 1.96 |
11 | 1.95 |
12 | 2.05 |
13 | 1.79 |
14 | 1.82 |
15 | 1.85 |
16 | 1.85 |
17 | 1.99 |
Performance rating is 115%, fatigue allowance is given as 8%, personal allowance is 6%, and delay allowance is 2%. Workday hour is 7.5 hours and the operators would be paid $12.50 per hour for 8 hours.
To determine: The cost per unit for the task in direct labor cost.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Describe the job design to specify the work material and methods?
Describe work sampling and perform calculations.
Contrast and compare relevant ideas that might be utilised to reduce rework costs.
Chapter 10 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
Ch. 10 - Prob. 1EDCh. 10 - Prob. 1DQCh. 10 - Prob. 2DQCh. 10 - Prob. 3DQCh. 10 - Prob. 4DQCh. 10 - Prob. 5DQCh. 10 - Prob. 6DQCh. 10 - Prob. 7DQCh. 10 - Prob. 8DQCh. 10 - Prob. 9DQ
Ch. 10 - Prob. 10DQCh. 10 - Prob. 11DQCh. 10 - Prob. 12DQCh. 10 - Prob. 13DQCh. 10 - Prob. 14DQCh. 10 - Prob. 1PCh. 10 - Prob. 2PCh. 10 - Prob. 3PCh. 10 - Prob. 4PCh. 10 - Prob. 5PCh. 10 - Prob. 6PCh. 10 - Prob. 7PCh. 10 - Prob. 8PCh. 10 - Prob. 9PCh. 10 - Prob. 10PCh. 10 - Prob. 11PCh. 10 - Prob. 12PCh. 10 - Prob. 13PCh. 10 - Prob. 14PCh. 10 - Prob. 15PCh. 10 - Prob. 16PCh. 10 - Prob. 17PCh. 10 - Prob. 18PCh. 10 - Prob. 19PCh. 10 - Prob. 20PCh. 10 - Prob. 21PCh. 10 - Prob. 22PCh. 10 - Virginia College promotes a wide variety of...Ch. 10 - Prob. 24PCh. 10 - Prob. 25PCh. 10 - Prob. 26PCh. 10 - Prob. 27PCh. 10 - Prob. 28PCh. 10 - Prob. 29PCh. 10 - Prob. 30PCh. 10 - Prob. 31PCh. 10 - Prob. 32PCh. 10 - Prob. 33PCh. 10 - Prob. 34PCh. 10 - Prob. 35PCh. 10 - Prob. 36PCh. 10 - Prob. 37PCh. 10 - Prob. 39PCh. 10 - Prob. 40PCh. 10 - Prob. 41PCh. 10 - Prob. 42PCh. 10 - Prob. 44PCh. 10 - Prob. 1CSCh. 10 - Prob. 2CSCh. 10 - Prob. 3CSCh. 10 - Prob. 4CSCh. 10 - Prob. 1.1VCCh. 10 - Prob. 1.2VCCh. 10 - Prob. 1.3VCCh. 10 - Prob. 2.1VCCh. 10 - Prob. 2.2VCCh. 10 - Prob. 2.3VCCh. 10 - Prob. 2.4VC
Knowledge Booster
Similar questions
- List and explain the types of jobs today that would require time and motion studies to be a factor? Would any additional skills be required to be taught? Provide examples.arrow_forwardDescribe some of the limitations of time study method ?arrow_forwardGive at least 3 examples of jobs that requires Work Measurement and give a brief explaination.arrow_forward
- The ISME Department at WSU promotes its industrial engineering program by mailing thousands of individually composed and typed letters to prospective students and their families. A time study has been conducted on teh task of preparing the letters for mailing (see data in the table below). WSU's personal, delay, and fatigue allowance factor is 13% of the shift time. What is the standard time of the overall job studied? Write your answer with one decimal point. Observations in Minutes Job Element (A) Compose and type letter (B) Type envelope address 2 1 2 3 4 5 Performance Rating 7 9 8 1 2 118 1 3 1 100 (C) Stuff, stamp, seal, and sort envelopes 1 4 2 1 111 Correct Answer: 11.46±1arrow_forwardWhat is the need for “Background Checks” and “Medical Examinations” in the process of selection.arrow_forwardwhat are the advantages and disadvantages of continuous and snapback method of time study.arrow_forward
- Analyze the job to identify the standard elements.arrow_forwardState and describe some of the limitations of time study method ?arrow_forwardLatisha Simmons, a loan processor at Wentworth Bank, has been timed performing four work elements, with the results shown in the following table. Task Element 1 2 3 4 Performance Rating 110% 85% 90% 85% 1 0.6 0.6 0.5 1.4 Observation (minutes per cycle) 2 3 4 0.3 0.8 0.5 1.9 0.6 0.7 0.6 1.9 0.4 0.6 0.5 1.7 The allowances for tasks such as this are personal, 8%; fatigue, 12%; and delay, 3%. minutes (round your response to two a) The normal time for the complete operation : = decimal places). b) The standard time for this process = minutes (round your response to two decimal places). 0.5 0.8 0.5 1.4arrow_forward
- Identify to which category of “personal”, “fatigue”, or “delay” the following job elements belong to a) The hair-dresser takes the phone to confirm a booking, in the middle of a client haircut. b) The doctor takes a cup of coffee and a quick rest in a short time between visiting two patients. c) In a long-distance drive, the coach driver stops in a service area every two to three hours to have some food.arrow_forwardIf the normal time is 1.30 min for a repetitive task that produces one work unit per cycle, and the company uses a PFD allowance factor of 12%, determine (a) the standard time for the task and (b) how many work units are produced in an 8-hour shift at standard performance.arrow_forwardK Latisha Simmons, a loan processor at Wentworth Bank, has been timed performing four work elements, with the results shown in the following table. Task Element 1 2 3 4 Performance Rating 115% 95% 85% 80% 1 0.5 0.6 0.7 1.6 Observation (minutes per cycle) 2 3 4 0.4 0.9 0.4 1.9 0.5 0.7 0.6 2.1 0.3 0.6 0.4 1.7 5 0.3 0.7 0.4 1.5 The allowances for tasks such as this are personal, 8%; fatigue, 10%; and delay, 2%. a) The normal time for the complete operation = minutes (round your response to two decimal places). b) The standard time for this process = minutes (round your response to two decimal places).arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.