a)
To determine: The normal time for the operation
Introduction: Time study is the basis that helps set the standard time; it would time a sample of the performance of the worker.
a)
Answer to Problem 25P
Thenormal time calculated as 3.23 minutes.
Explanation of Solution
Given information:
The allowance for tasks is given as 7% for personal, 10% for fatigue, and 3% for delay. The observed time and performance rating for each element is given as follows:
Element | Performance rating | Observation (minutes per cycle) | ||||
1 | 2 | 3 | 4 | 5 | ||
1 | 110% | 0.5 | 0.4 | 0.6 | 0.4 | 0.4 |
2 | 95% | 0.6 | 0.8 | 0.7 | 0.6 | 0.7 |
3 | 90% | 0.6 | 0.4 | 0.7 | 0.5 | 0.5 |
4 | 85% | 1.5 | 1.8 | 2 | 1.7 | 1.5 |
Formulae to calculate normal time:
Calculate the normal time:
Element | Performance rating | Observation (minutes) | Average time | Normal time | ||||
1 | 2 | 3 | 4 | 5 | ||||
1 | 110% | 0.5 | 0.4 | 0.6 | 0.4 | 0.4 | 0.46 | 0.51 |
2 | 95% | 0.6 | 0.8 | 0.7 | 0.6 | 0.7 | 0.68 | 0.65 |
3 | 90% | 0.6 | 0.4 | 0.7 | 0.5 | 0.5 | 0.54 | 0.49 |
4 | 85% | 1.5 | 1.8 | 2 | 1.7 | 1.5 | 1.7 | 1.45 |
Excel worksheet:
Calculate the average time for the first element:
The average time is calculated by taking an average of the observation given, which is summation of 0.5, 0.4, 0.6, 0.4, and 0.4 and dividing the result by 5. Hence, the average is 0.46 minutes.
Calculate the average time for the second element:
The average time is calculated by taking an average of the observation given, which is summation of 0.6, 0.8, 0.7, 0.6, and 0.7 and dividing the result by 5. Hence, the average is 0.68 minutes.
Calculate the average time for the third element:
The average time is calculated by taking an average of the observation given, which is summation of 0.6, 0.4, 0.7 0.5, and 0.5 and dividing the result by 5. Hence, the average is 0.54 minutes.
Calculate the average time for the fourth element:
The average time is calculated by taking an average of the observation given, which is summation of 1.5, 1.8, 2.0, 1.7, and 1.5 and dividing the result by 5. Hence, the average is 1.7 minutes.
Calculate the normal time for the first element:
The normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 0.46 minutes, and performance rating is given as 110%. Hence, the normal time is 0.51 minutes.
Calculate the normal time for the second element:
The normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 0.68 minutes, and performance rating is given as 95%. Hence, the normal time is 0.65 minutes.
Calculate the normal time for the third element:
The normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 0.54 minutes, and performance rating is given as 90%. Hence, the normal time is 0.49 minutes.
Calculate the normal time for the fourth element:
The normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 1.7 minutes, and performance rating is given as 85%. Hence, the normal time is 1.45 minutes.
Calculate the total normal time:
The normal time is calculated by adding the normal time of all the elements.
Hence, the total normal time is 3.08 minutes.
b)
To determine: The standard time for the operation.
Introduction: Time study is the basis that helps set the standard time, it would time a sample of the performance of the worker.
b)
Answer to Problem 25P
Thestandard time is calculated as 5.4 minutes.
Explanation of Solution
Given information:
The allowance for tasks is given as 7% for personal, 10% for fatigue, and 3% for delay. The observed time and performance rating for each element are given as follows:
Element | Performance rating | Observation (minutes per cycle) | ||||
1 | 2 | 3 | 4 | 5 | ||
1 | 110% | 0.5 | 0.4 | 0.6 | 0.4 | 0.4 |
2 | 95% | 0.6 | 0.8 | 0.7 | 0.6 | 0.7 |
3 | 90% | 0.6 | 0.4 | 0.7 | 0.5 | 0.5 |
4 | 85% | 1.5 | 1.8 | 2 | 1.7 | 1.5 |
Formulae to calculate standard time:
Calculate the allowance factor:
The allowance factor is calculated by adding personal allowance, fatigue, and delay allowance. Personal allowance is given as 7%, fatigue is 10%, and delay allowance is 3%. Hence, the allowance factor is 20%.
Calculate the standard time:
The standard time is calculated by dividing the normal time with the value attained by subtracting the allowance factor from 1. The normal time is calculated as 3.08 minutes and the allowance factor is calculated as 20%
Hence, the standard time is 3.85 minutes.
Want to see more full solutions like this?
Chapter 10 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- Peter Rourke, a loan processor a t Wentworth Bank,has been timed performing four work elements, with the resultsshown in the fo llowing table. The allowances for tasks such asth is are personal, 7%; fa tigue, 10%; and delay, 3%. a) What is the normal time?b) What is the standard time?arrow_forwardInstalling mufflers at the O'Sullivan Garage in Golden, Colorado, involves five work elements. Jill O'Sull ivanhas timed workers performing these tasks seven times, with the results shown in the following table: By agreement with her workers, Jill allows a 10% fatigue factor and a 10% personal-time factor, but no time for delay. To compute standard time for the work operatio n, Jill excludes all observations that a ppear to be unusual or nonrecurring. She does not want an error of mo re than ±5%.a) What is the standard time for the task?b) How many observations are needed to assu re a 95% confidence level?arrow_forwardNine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, five percent; fatigue, six percent; delay, five percent. Use the Work Measurement Excel template to determine the standard time for this operation. Work Observation Element 1 2 3 4 5 6 7 8 9 Performance Rating A 0.10 0.15 0.08 0.06 0.11 0.10 0.16 0.15 0.16 115% B 0.23 0.18 0.23 0.22 0.25 0.24 0.29 0.28 0.28 95% C 0.49 0.52 0.49 0.48 0.47 0.47 0.52 0.49 0.51 105% D 0.62 0.67 0.64 0.59 0.70 0.68 0.68 0.67 0.70 90% E 0.71 0.74 0.73 0.70 0.81 0.81 0.78 0.81 0.83 105% F 1.03 1.03 1.01 1.01 1.08 1.12 1.03 1.09 1.11 100% Round your answer to two decimal places. minutesarrow_forward
- Nine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, five percent; fatigue, five percent; delay, seven percent. Use the Work Measurement Excel template to determine the standard time for this operation. Work Observation Element 1 2 3 4 5 6 7 8 9 Performance Rating A 0.11 0.14 0.10 0.09 0.12 0.11 0.15 0.14 0.15 105% B 0.24 0.20 0.21 0.22 0.24 0.23 0.28 0.26 0.26 85% C 0.46 0.48 0.46 0.44 0.48 0.48 0.48 0.46 0.49 100% D 0.64 0.66 0.65 0.59 0.71 0.69 0.69 0.66 0.71 115% E 0.70 0.74 0.74 0.68 0.79 0.83 0.77 0.80 0.84 100% F 1.01 1.05 1.01 1.00 1.09 1.12 1.05 1.06 1.12 95% Round your answer to two decimal places. minutesarrow_forwardNine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, five percent; fatigue, six percent; delay, six percent. Use the Work Measurement Excel template to determine the standard time for this operation. Work Observation Element 1 2 3 4 5 6 7 8 9 Performance Rating A 0.09 0.13 0.06 0.05 0.11 0.09 0.14 0.13 0.14 85% B 0.25 0.18 0.23 0.20 0.24 0.24 0.27 0.26 0.26 115% C 0.47 0.51 0.47 0.46 0.49 0.49 0.51 0.47 0.48 110% D 0.61 0.69 0.65 0.60 0.71 0.67 0.67 0.69 0.73 90% E 0.72 0.76 0.74 0.68 0.79 0.81 0.76 0.80 0.81 115% F 1.02 1.04 0.98 1.02 1.08 1.12 1.04 1.07 1.09 85% Round your answer to two decimal places. minutesarrow_forward6- A time study on a manual work eycle was taken by observing times. There are three regular elements in the work eycle as follows: a, b, and d. Element e is an iregular element performed every 4 cycles. Observed times and performance ratings of the elements are also given in the figure. Determine a. the normal time b. the standard time for the work cycle, using an allowance factor of 25%. Select your choice according to part a and b's answer where both of them must be true. Work element Observed time Performance rating a b d 0,52min 0,25 min 1,20 min 0,26 min 80% 75% 92% 100% a) a:1.9675; b:1.9675 b) a:1.1395; b:1.1395 c) a: 1.1395; b:1.4814 d) a: 1.1395; b:1.4244 e) a: 1.9675; b:2.4594arrow_forward
- Nine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, five percent; fatigue, eight percent; delay, five percent. Use the Work Measurement Excel template to determine the standard time for this operation. Work Observation Element 1 2 3 4 5 6 7 8 9 Performance Rating A 0.09 0.14 0.08 0.07 0.10 0.09 0.15 0.14 0.15 110% B 0.23 0.20 0.22 0.20 0.24 0.23 0.29 0.27 0.27 90% C 0.49 0.51 0.49 0.46 0.49 0.49 0.51 0.49 0.48 95% D 0.64 0.66 0.63 0.62 0.69 0.67 0.67 0.66 0.70 115% E 0.72 0.74 0.74 0.69 0.81 0.82 0.79 0.80 0.82 105% F 1.01 1.03 0.99 0.99 1.09 1.12 1.03 1.07 1.12 85% Round your answer to two decimal places. minutesarrow_forwardDescribe some of the limitations of time study method ?arrow_forwardThe ISME Department at WSU promotes its industrial engineering program by mailing thousands of individually composed and typed letters to prospective students and their families. A time study has been conducted on teh task of preparing the letters for mailing (see data in the table below). WSU's personal, delay, and fatigue allowance factor is 13% of the shift time. What is the standard time of the overall job studied? Write your answer with one decimal point. Observations in Minutes Job Element (A) Compose and type letter (B) Type envelope address 2 1 2 3 4 5 Performance Rating 7 9 8 1 2 118 1 3 1 100 (C) Stuff, stamp, seal, and sort envelopes 1 4 2 1 111 Correct Answer: 11.46±1arrow_forward
- A direct time study was taken on a manual work cycle using the snapback timing method. The regular work cycle consisted of three elements, identified as a, b, and c in the following table. Element d is an irregular element performed every 5 cycles. Observed times and performance ratings of the elements given. Determine the standard time for the work cycle using an allowance factor of 15%. Work Element a с b 0.25min Observed Time 0.50min 0.56min 100% d 1.10min 100% Performance Rating 80% 110% Select one: a. None of the Above O b. 1.63 minutes c. 1.53 minutes O d. 1.95 minutes e. 1.76 minutesarrow_forwardFind out the standard time using the following data: Average time for machine elements = 6 min. Average time for manual elements = 3 min. Performance rating =110% Allowances = 11%arrow_forwardHow many work cycles should be timed to estimate the average cycle time to within 2 percent ofthe sample mean with a confidence of 99 percent if a pilot study yielded these times (minutes):5.2, 5.5, 5.8, 5.3, 5.5, and 5.1? The standard deviation is .253 minutes per cycle.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.