Question
Chapter 10, Problem 2CS
Summary Introduction
Case summary:
Person K is the vice-president of operations at Company J, which received a request for quote of supplying 400 units per week. Employee must be permitted to perform the task for 17 times. The actual times observed were given below:
Number | Actual time (minutes) |
1 | 2.05 |
2 | 1.92 |
3 | 2.01 |
4 | 1.89 |
5 | 1.77 |
6 | 1.8 |
7 | 1.86 |
8 | 1.83 |
9 | 1.93 |
10 | 1.96 |
11 | 1.95 |
12 | 2.05 |
13 | 1.79 |
14 | 1.82 |
15 | 1.85 |
16 | 1.85 |
17 | 1.99 |
Performance rating is 115%, fatigue allowance is given as 8%, personal allowance is 6%, and delay allowance is 2%. Workday hour is 7.5 hours and the operators would be paid $12.50 per hour for 8 hours.
To determine: Whether the
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
How to Work sampling compared with stopwatch time study?
Explain the steps involved in conducting a time study,and discuss any difficulties you might envision at varioussteps.
State and describe some of the limitations of time study method ?
Chapter 10 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
Ch. 10 - Prob. 1EDCh. 10 - Prob. 1DQCh. 10 - Prob. 2DQCh. 10 - Prob. 3DQCh. 10 - Prob. 4DQCh. 10 - Prob. 5DQCh. 10 - Prob. 6DQCh. 10 - Prob. 7DQCh. 10 - Prob. 8DQCh. 10 - Prob. 9DQ
Ch. 10 - Prob. 10DQCh. 10 - Prob. 11DQCh. 10 - Prob. 12DQCh. 10 - Prob. 13DQCh. 10 - Prob. 14DQCh. 10 - Prob. 1PCh. 10 - Prob. 2PCh. 10 - Prob. 3PCh. 10 - Prob. 4PCh. 10 - Prob. 5PCh. 10 - Prob. 6PCh. 10 - Prob. 7PCh. 10 - Prob. 8PCh. 10 - Prob. 9PCh. 10 - Prob. 10PCh. 10 - Prob. 11PCh. 10 - Prob. 12PCh. 10 - Prob. 13PCh. 10 - Prob. 14PCh. 10 - Prob. 15PCh. 10 - Prob. 16PCh. 10 - Prob. 17PCh. 10 - Prob. 18PCh. 10 - Prob. 19PCh. 10 - Prob. 20PCh. 10 - Prob. 21PCh. 10 - Prob. 22PCh. 10 - Virginia College promotes a wide variety of...Ch. 10 - Prob. 24PCh. 10 - Prob. 25PCh. 10 - Prob. 26PCh. 10 - Prob. 27PCh. 10 - Prob. 28PCh. 10 - Prob. 29PCh. 10 - Prob. 30PCh. 10 - Prob. 31PCh. 10 - Prob. 32PCh. 10 - Prob. 33PCh. 10 - Prob. 34PCh. 10 - Prob. 35PCh. 10 - Prob. 36PCh. 10 - Prob. 37PCh. 10 - Prob. 39PCh. 10 - Prob. 40PCh. 10 - Prob. 41PCh. 10 - Prob. 42PCh. 10 - Prob. 44PCh. 10 - Prob. 1CSCh. 10 - Prob. 2CSCh. 10 - Prob. 3CSCh. 10 - Prob. 4CSCh. 10 - Prob. 1.1VCCh. 10 - Prob. 1.2VCCh. 10 - Prob. 1.3VCCh. 10 - Prob. 2.1VCCh. 10 - Prob. 2.2VCCh. 10 - Prob. 2.3VCCh. 10 - Prob. 2.4VC
Knowledge Booster
Similar questions
- Describe some of the limitations of time study method ?arrow_forwarderations Management Spring21 Time left 1:09:19 stion In a fabric manufacturing factory, the quality control process using control charts from SPC. In an hour there are a total of 5 samples are taken each having 5 observations regarding the thickness of fabric in measured in millimeters. In a particular hour, the sample means (X-bar) are noted to be: 156.46, 199.62, 189.31, 102.22, and112.09 respectively. In the same sample, the corresponding ranges are: 11.97, 12.17, 13.94, 11.86, and 11.83 respectively. What are the lower and upper control limits for the X-bar chart? et ered ed out of O a. None is correct lag O b. 156.55, 170.47 tion O C. 144.77, 159.11 O d. 145.40, 190.72 O e. 143.55, 165.47 Of. 142.92, 160.66 Fi PREVIOUS PAGE NEXT PAGE O Type here to search %23arrow_forwardII. Exercise You have been asked to develop a work sample for a receptionist position in a three-person law firm. The lawyers believe this might be the best way to evaluate applicants, especially because they are seeking someone with a disability and they do not believe in the practical credibility of standardized measures. 1. What information do you need to design the work sample? 2. What materials do you need? 3. What are the criteria for your observation schedule as the consumer performs the work sample?arrow_forward
- A Methods and Measurements Analyst needs to develop a time standard for a certain task. The task involves use of a ruler, square, and portable electric saw to mark and cut the "notch" in a rafter (a standard carpentry task of home construction). In a preliminary study, he observed one of his workers performing this task five times. The observations were made in an air-conditioned, well-lit training facility, at ground level, with all tools and equipment clean and readily available. Observation: 1 2 3 4 5 Task time (seconds): 82 74 80 83 76 a. What is the actual average time for this task? b. What is the normal time for this task if the employee worked at a 20% faster pace than is typical for adequately trained workers? c. What is standard time for this task if allowances sum to 14%? d. If the analyst then thought more carefully about his experiment and decided that the allowances needed to be increased to match the real (outside, not air-conditioned)…arrow_forwardWhat are motion study principles? How are they classified?arrow_forwardWhy should the procedure be flexible? What are they?arrow_forward
- TOYS AND JOB DESIGN AT THE HOVEY AND BEARD COMPANY The following is a situation that occurred in the Hovey and Beard Company, as reported by J. V. Clark. This company manufactured a line of wooden toys. One part of the process involved spray painting partially assembled toys, after which the toys were hung on moving hooks that carried them through a drying oven. The operation, staffed entirely by women, was plagued with absenteeism, high turnover, and low morale. Each woman at her paint booth would take a toy from the tray beside her, position it in a fixture, and spray on the color according to the required pattern. She then would release the toy and hang it on the conveyor hook. The rate at which the hooks moved had been calculated so that each woman, once fully trained, would be able to hang a painted toy on each hook before it passed beyond her reach. The women who worked in the paint room were on a group incentive plan that tied their earnings to the…arrow_forwardIn making a time study, differentiate elements and cycles. What is the advantage of breaking an operation into a more detailed list of elements?arrow_forwardA hospital administrator thinks that the X-ray equipment is only in use about 20 percent of the time. What number of observations in a work sampling study would be needed to estimate the true percentage of time to within 5 percent with a confidence of 98 percent?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.