Roy Creasey Enterprises, a machine shop, is planning to move to a new, larger location. The new building will be 60 feet long by 40 feet wide. Creasey envisions the building as having six distinct production areas, roughly equal in size. He feels strongly about safety and intends to have marked pathways throughout the building to facilitate the movement of people and materials. See the following building schematic. Room 1 Room 2 Room 3 Room 4 Room 5 Room 6 His foreman has completed a month-long study of the number of loads of material that have moved from one process to another in the current building. This information is contained in the flow matrix on the left below. Finally, Creasey also developed a matrix to indicate distances between the work areas shown in the building schematic, shown on the right below. From/To Material Welding Drills Lathes Grinders Benders Material 0 80 45 0 0 45 Welding 25 0 0 45 0 0 Drills 20 0 0 0 50 0 Lathes 0 20 0 0 20 0 Grinders 55 0 100 0 0 0 Benders 10 0 20 0 0 0 1 2 3 4 5 6 1 0 20 40 20 40 60 2 0 20 40 20 40 3 0 60 40 20 4 0 20 40 5 0 20 6 0 One of the layouts that could be designed is: Room 1 = Benders Room 2 = Materials Room 3 = Welding Room 4 = Drills Room 5 = Grinders Room 6 = Lathes The cumulative distance based on the overall movement of material between processes for this layout is ___ feet (enter your response as a whole number).
Roy Creasey Enterprises, a machine shop, is planning to move to a new, larger location. The new building will be 60 feet long by 40 feet wide. Creasey envisions the building as having six distinct production areas, roughly equal in size. He feels strongly about safety and intends to have marked pathways throughout the building to facilitate the movement of people and materials. See the following building schematic. Room 1 Room 2 Room 3 Room 4 Room 5 Room 6 His foreman has completed a month-long study of the number of loads of material that have moved from one process to another in the current building. This information is contained in the flow matrix on the left below. Finally, Creasey also developed a matrix to indicate distances between the work areas shown in the building schematic, shown on the right below. From/To Material Welding Drills Lathes Grinders Benders Material 0 80 45 0 0 45 Welding 25 0 0 45 0 0 Drills 20 0 0 0 50 0 Lathes 0 20 0 0 20 0 Grinders 55 0 100 0 0 0 Benders 10 0 20 0 0 0 1 2 3 4 5 6 1 0 20 40 20 40 60 2 0 20 40 20 40 3 0 60 40 20 4 0 20 40 5 0 20 6 0 One of the layouts that could be designed is: Room 1 = Benders Room 2 = Materials Room 3 = Welding Room 4 = Drills Room 5 = Grinders Room 6 = Lathes The cumulative distance based on the overall movement of material between processes for this layout is ___ feet (enter your response as a whole number).
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
Roy Creasey Enterprises, a machine shop, is planning to move to a new, larger location. The new building will be 60 feet long by 40 feet wide. Creasey envisions the building as having six distinct production areas, roughly equal in size. He feels strongly about safety and intends to have marked pathways throughout the building to facilitate the movement of people and materials. See the following building schematic.
Room
1
|
Room
2
|
Room
3
|
Room
4
|
Room
5
|
Room
6
|
His foreman has completed a month-long study of the number of loads of material that have moved from one process to another in the current building. This information is contained in the flow matrix on the left below. Finally, Creasey also developed a matrix to indicate distances between the work areas shown in the building schematic, shown on the right below.
From/To | Material | Welding | Drills | Lathes | Grinders | Benders |
Material | 0 | 80 | 45 | 0 | 0 | 45 |
Welding | 25 | 0 | 0 | 45 | 0 | 0 |
Drills | 20 | 0 | 0 | 0 | 50 | 0 |
Lathes | 0 | 20 | 0 | 0 | 20 | 0 |
Grinders | 55 | 0 | 100 | 0 | 0 | 0 |
Benders | 10 | 0 | 20 | 0 | 0 | 0 |
1 | 2 | 3 | 4 | 5 | 6 | |
1 | 0 | 20 | 40 | 20 | 40 | 60 |
2 | 0 | 20 | 40 | 20 | 40 | |
3 | 0 | 60 | 40 | 20 | ||
4 | 0 | 20 | 40 | |||
5 | 0 | 20 | ||||
6 | 0 |
One of the layouts that could be designed is:
Room 1 = Benders
|
Room 2 = Materials
|
Room 3 = Welding
|
Room 4 = Drills
|
Room 5 = Grinders
|
Room 6 = Lathes
|
The cumulative distance based on the overall movement of material between processes for this layout is ___ feet (enter your response as a whole number).
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 4 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Fundamentals of Structural Analysis](https://www.bartleby.com/isbn_cover_images/9780073398006/9780073398006_smallCoverImage.gif)
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
![Sustainable Energy](https://www.bartleby.com/isbn_cover_images/9781337551663/9781337551663_smallCoverImage.gif)
![Traffic and Highway Engineering](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning