Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 60 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are as follows: Week Customer Orders 1 2 55 40 25 20 Use a production lot size of 85 units and no beginning inventory. (In the ATP row, enter a value of 0 (zero) in any periods where ATP should not be calculated. Leave no cells blank- be certain to enter "0" wherever required.) June July MPS ATP Forecast Customer Orders Projected On-Hand Inventory 2 60 55 25 85 85 30 89839 60 40 3 45 60 25 5075 85 40 60 20 15 0 0 60 0 40 85 85 60 0 66 85 85 7 60 0 5 0 0 60 0 30 85 85

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

need help with this question!

Note:-

• Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism.

• Answer completely.

• You will get up vote for sure.

Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 60 units. The
MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders
(committed) are as follows:
Week Customer Orders.
1
2
3
55
40
25
20
Use a production lot size of 85 units and no beginning inventory. (In the ATP row, enter a value of 0 (zero) in any
periods where ATP should not be calculated. Leave no cells blank - be certain to enter "0" wherever required.)
June
July
Forecast
Customer Orders
Projected On-Hand Inventory
MPS
ATP
1
60
55
25
60
40
50
1851 85
45
2
185 30
3
60
25
75
85
40
60
20
15
10
0
5
60
0
40
85
85
E
60
0
65
85
85
7
60
0
5
0
0
B
60
0
30
85
85
Transcribed Image Text:Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 60 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are as follows: Week Customer Orders. 1 2 3 55 40 25 20 Use a production lot size of 85 units and no beginning inventory. (In the ATP row, enter a value of 0 (zero) in any periods where ATP should not be calculated. Leave no cells blank - be certain to enter "0" wherever required.) June July Forecast Customer Orders Projected On-Hand Inventory MPS ATP 1 60 55 25 60 40 50 1851 85 45 2 185 30 3 60 25 75 85 40 60 20 15 10 0 5 60 0 40 85 85 E 60 0 65 85 85 7 60 0 5 0 0 B 60 0 30 85 85
Expert Solution
steps

Step by step

Solved in 4 steps with 6 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.