TABLE Q2a Immediate Expected Budget ID Task Predecessor Duration (days) (RM) A Meet with client 1 5 1,000 B Write the programme A 20 20,000 Debug the programme 5 3,000 D Prepare draft manual В 2,000 5 E Meet with clients 2 5 2,000 F Test the programme С, Е 20 4,000 Make modification F 10 16,000 Finalize manual G 10 10,000 J Advertise С, Е 20 16,000 TABLE Q2b Actual Actual ID Task Status Actual Start (days) Duration Costs (days) (RM) A Meet with client 1 100% +5 days 5 3,000 Write the programme 100% +15 days 30 18,000 C Debug the programme 100% As per other delays 10 5,000 D Prepare draft manual 100% As per other delays 5 2,000 Meet with clients 2 Test the programme Make modification Finalize manual E 100% As per other delays 2,000 F 50% As per other delays 20 1,500 As per other delays As per other delays G 0% 10 0% 10 +5 on top of other J Advertise 25% 20 2,000 delays

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Billy has worked for Meta Solution Sdn. Bhd. (MSSB) for five years, mainly in administrative positions. Three months ago, he was informed that he was being transferred to the firm's IT project management group. Billy was excited because he realized that project management was typically the career path to the top in the MSSB, and everyone had to demonstrate the ability to "get their feet wet" by successfully running projects. Billy had just left a meeting with his superior, Bob, who assigned him project management responsibilities for a new software development the company had successfully bid.

It is now Week 14 of the project. The performance of the project is as summarized in TABLE Q2b. Report the progress of the project as at Week 14 using a Gantt Chart. Perform an analysis of the project status at Week 14 by using EVA.
Use the CPI and SPI to determine project efficiency. Estimate the performance of the project at completion and propose suitable steps to enhance the overall performance

 

TABLE Q2a
Immediate
Expected
Budget
ID
Task
Predecessor
Duration (days)
(RM)
A
Meet with client 1
5
1,000
B
Write the programme
A
20
20,000
Debug the programme
5
3,000
D
Prepare draft manual
В
2,000
5
E
Meet with clients 2
5
2,000
F
Test the programme
С, Е
20
4,000
Make modification
F
10
16,000
Finalize manual
G
10
10,000
J
Advertise
С, Е
20
16,000
Transcribed Image Text:TABLE Q2a Immediate Expected Budget ID Task Predecessor Duration (days) (RM) A Meet with client 1 5 1,000 B Write the programme A 20 20,000 Debug the programme 5 3,000 D Prepare draft manual В 2,000 5 E Meet with clients 2 5 2,000 F Test the programme С, Е 20 4,000 Make modification F 10 16,000 Finalize manual G 10 10,000 J Advertise С, Е 20 16,000
TABLE Q2b
Actual
Actual
ID
Task
Status Actual Start (days)
Duration
Costs
(days)
(RM)
A
Meet with client 1
100%
+5 days
5
3,000
Write the programme
100%
+15 days
30
18,000
C Debug the programme
100% As per other delays
10
5,000
D
Prepare draft manual
100% As per other delays
5
2,000
Meet with clients 2
Test the programme
Make modification
Finalize manual
E
100% As per other delays
2,000
F
50%
As per other delays
20
1,500
As per other delays
As per other delays
G
0%
10
0%
10
+5 on top of other
J
Advertise
25%
20
2,000
delays
Transcribed Image Text:TABLE Q2b Actual Actual ID Task Status Actual Start (days) Duration Costs (days) (RM) A Meet with client 1 100% +5 days 5 3,000 Write the programme 100% +15 days 30 18,000 C Debug the programme 100% As per other delays 10 5,000 D Prepare draft manual 100% As per other delays 5 2,000 Meet with clients 2 Test the programme Make modification Finalize manual E 100% As per other delays 2,000 F 50% As per other delays 20 1,500 As per other delays As per other delays G 0% 10 0% 10 +5 on top of other J Advertise 25% 20 2,000 delays
Expert Solution
steps

Step by step

Solved in 8 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.