In one of the construction projects, a bulldozer is used for a weekly rent of $150, with a work rate of 10 hours per day, 50 minutes per hour, and 6 days per week. If you know that the dimensions of the bulldozer blade are 3 lengths and 1 m height, the slope of the pushed soil is (1:1), its speed when loaded is 45 m/min and when returning is 80 m/min, and the time for loading, unloading, and changing is 0.35 minutes, the transported soil is sandy, weighing 1650 kg/m3 by Bank volume and 1300 kg/m3 by loose volume, the transport distance is 300 m. If you know that using a tractor shovel costs $0.5 per m3, ma a decision about choosing the economical equipment to use in the project.

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter10: Pricing Excavation And Backfill
Section: Chapter Questions
Problem 7RQ
icon
Related questions
Question
In one of the construction projects, a bulldozer is used for a weekly rent of $150,
with a work rate of 10 hours per day, 50 minutes per hour, and 6 days per week. If
you know that the dimensions of the bulldozer blade are 3 lengths and 1 m height,
the slope of the pushed soil is (1:1), its speed when loaded is 45 m/min and when
returning is 80 m/min, and the time for loading, unloading, and changing is 0.35
minutes, the transported soil is sandy, weighing 1650 kg/m3 by Bank volume and
1300 kg/m3 by loose volume, the transport distance is 300 m.
If you know that using a tractor shovel costs $0.5 per m3, ma a decision about
choosing the economical equipment to use in the project.
Transcribed Image Text:In one of the construction projects, a bulldozer is used for a weekly rent of $150, with a work rate of 10 hours per day, 50 minutes per hour, and 6 days per week. If you know that the dimensions of the bulldozer blade are 3 lengths and 1 m height, the slope of the pushed soil is (1:1), its speed when loaded is 45 m/min and when returning is 80 m/min, and the time for loading, unloading, and changing is 0.35 minutes, the transported soil is sandy, weighing 1650 kg/m3 by Bank volume and 1300 kg/m3 by loose volume, the transport distance is 300 m. If you know that using a tractor shovel costs $0.5 per m3, ma a decision about choosing the economical equipment to use in the project.
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,