Draw the node network, perform the CPM calculations, mark the critical path, and complete the table below: Activity A B C D E F G H Duration IPA 6 2 8 5 3 6 5 2 I - A A, B B D, E C, D F, G ES EF LS LF TF FF Ten days after the start of the project. The following information was received: Activities A and B: Completed on time. Activity C: Started, 3 days left. Activity D: Started, 2 days left. Activity E: Has not started yet but duration adjusted to 5 days.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Draw the node network, perform the CPM calculations, mark the critical path, and complete the table
below:
Activity
A
B
C
D
E
F
G
U I
H
Duration IPA
6
2
8
5
3
6
5
2
A
A, B
B
D, E
C, D
F, G
ES EF LS LF TF FF
Ten days after the start of the project. The following information was received:
Activities A and B: Completed on time.
Activity C: Started, 3 days left.
Activity D: Started, 2 days left.
Activity E: Has not started yet but duration adjusted to 5 days.
Draw the updated network. Calculate the new project completion date. Check if there is any change on the
critical path.
Transcribed Image Text:Draw the node network, perform the CPM calculations, mark the critical path, and complete the table below: Activity A B C D E F G U I H Duration IPA 6 2 8 5 3 6 5 2 A A, B B D, E C, D F, G ES EF LS LF TF FF Ten days after the start of the project. The following information was received: Activities A and B: Completed on time. Activity C: Started, 3 days left. Activity D: Started, 2 days left. Activity E: Has not started yet but duration adjusted to 5 days. Draw the updated network. Calculate the new project completion date. Check if there is any change on the critical path.
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.