(b) By referring to information in Table 1, determine the critical path, non-critical paths, and slack for each activity by using Activity on Node (AoN) method. If the construction expected to start on 1st May 2022 (Assuming 8 labors working for 8 hours per day, 7 days of working per week, without public holiday), when will be the due date for the project? Table 1: Concreting Work Activity Activity Early Finish Date Predecessor A 26th May 2022 Start of activity B 8th June 2022 A C 10th June 2022 A D 7th June 2022 Start of activity E 18th June 2022 В, С, D F 20th June 2022 D, I G 12th June 2022 E, F 7th June 2022 E, G 5th June 2022 Start of activity 29th May 2022 Н, G K 27th May 2022 H, J L 20th May 2022 J, K

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
(b) By referring to information in Table 1, determine the critical path, non-critical paths, and slack for
each activity by using Activity on Node (AoN) method. If the construction expected to start on 1st May
2022 (Assuming 8 labors working for 8 hours per day, 7 days of working per week, without public
holiday), when will be the due date for the project?
Table 1: Concreting Work Activity
Activity
Early Finish Date
Predecessor
A
26th May 2022
Start of activity
B
8th June 2022
A
C
10th June 2022
A
D
7th June 2022
Start of activity
E
18th June 2022
В, С, D
F
20th June 2022
D, I
G
12th June 2022
E, F
7th June 2022
E, G
5th June 2022
Start of activity
29th May 2022
Н, G
K
27th May 2022
H, J
L
20th May 2022
J, K
Transcribed Image Text:(b) By referring to information in Table 1, determine the critical path, non-critical paths, and slack for each activity by using Activity on Node (AoN) method. If the construction expected to start on 1st May 2022 (Assuming 8 labors working for 8 hours per day, 7 days of working per week, without public holiday), when will be the due date for the project? Table 1: Concreting Work Activity Activity Early Finish Date Predecessor A 26th May 2022 Start of activity B 8th June 2022 A C 10th June 2022 A D 7th June 2022 Start of activity E 18th June 2022 В, С, D F 20th June 2022 D, I G 12th June 2022 E, F 7th June 2022 E, G 5th June 2022 Start of activity 29th May 2022 Н, G K 27th May 2022 H, J L 20th May 2022 J, K
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.