Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Normal Crash Normal Activity Time (weeks) Time (weeks) Cost A B с D E F G 4 2 3 8 6 3 4 3 1 3 4 3 2 2 $2,000 $2,300 weeks. $600 $2,300 $900 $3,200 $1,500 a) Based on the given information regarding the activities for the project, the project length = 16 weeks. b) The total cost required for completing this project on normal time = $ 12800. c) For reducing the duration of the project by one week, the activity that should be crashed first is activity D The cost of the project based on the first activity selected for crashing will increase by $ 75. d) The maximum weeks by which the project can be reduced by crashing = 7 Total cost of crashing the project to minimum (or maximum weeks possible) = $ Total Cost with Crashing Immediate Predecessor(s) $2,650 $2,900 $600 $2,600 $1,200 $4,400 $1,900 A B с D, E

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Only part D is needed to be solved.

Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this
project are listed in the following table:
Normal
Crash
Normal
Activity Time (weeks) Time (weeks) Cost
A
B
C
D
E
F
G
4
2
3
8
6
3
4
3
1
3
4
3
2
2
$2,000
$2,300
$600
$2,300
$900
weeks.
$3,200
$1,500
a) Based on the given information regarding the activities for the project, the project length = 16 weeks.
b) The total cost required for completing this project on normal time = $ 12800.
c) For reducing the duration of the project by one week, the activity that should be crashed first is activity D
The cost of the project based on the first activity selected for crashing will increase by $ 75
d) The maximum weeks by which the project can be reduced by crashing = 7
Total cost of crashing the project to minimum (or maximum weeks possible) = $
Total Cost
with
Crashing Immediate Predecessor(s)
$2,650
$2,900
$600
$2,600
$1,200
$4,400
$1,900
A
B
с
D, E
Transcribed Image Text:Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Normal Crash Normal Activity Time (weeks) Time (weeks) Cost A B C D E F G 4 2 3 8 6 3 4 3 1 3 4 3 2 2 $2,000 $2,300 $600 $2,300 $900 weeks. $3,200 $1,500 a) Based on the given information regarding the activities for the project, the project length = 16 weeks. b) The total cost required for completing this project on normal time = $ 12800. c) For reducing the duration of the project by one week, the activity that should be crashed first is activity D The cost of the project based on the first activity selected for crashing will increase by $ 75 d) The maximum weeks by which the project can be reduced by crashing = 7 Total cost of crashing the project to minimum (or maximum weeks possible) = $ Total Cost with Crashing Immediate Predecessor(s) $2,650 $2,900 $600 $2,600 $1,200 $4,400 $1,900 A B с D, E
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 6 steps with 1 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.