Develop a project network Activity-on-Arrow (AOA) for the club’s tournament preparation process and show all activity schedule and duration of the project [show clearly all dummy activities]  kindly help in drawing a clear network please.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Alebwelelapo is planning a soccer tournament for the weekend of May 29–30. The club’s officers know that by April 30 they must send out acceptances to teams that have applied to enter, and by April 20 they must send out the tournament game schedule to teams that have been selected to play. Their tentative plan is to begin the initial activities for tournament preparation, including sending out the application forms to prospective teams, on January 20. Following is a list of tournament activities, their precedence relationships, and their duration in days.

Activity

Description

Predecessor

Duration (Days)

A

Send application forms

7

B

Get volunteer workers

18

C

Line up referees

10

D

Reserve fields

21

E

Receive and process forms

A

30

F

Determine age divisions

B, C, D, E

9

G

Assign fields to divisions

F

7

H

Sell program ads

B

2

I

Acquire donated items for team gift bags

B

20

J

Schedule games

G

14

K

Design ads

H

80

L

Fill gift bags

I

12

M

Process team t-shirt orders

E

10

N

Send acceptance letters

F

7

O

Design and print programs

J, K, L, N

18

P

Put together registration boxes (programs, gifts, etc.)

O

7

Q

Send out game schedules

J, K, L, N

8

R

Assign referees to games

J, K, L, N

7

S

Get trophies

F

8

T

Silk-screen t-shirts

M

17

U

Package team t-shirt orders

T

8

a) Develop a project network Activity-on-Arrow (AOA) for the club’s tournament preparation process and show all activity schedule and duration of the project [show clearly all dummy activities] 

kindly help in drawing a clear network please.

Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.