Construct the precedence network diagram. Compute the expected completion time and the variance (or standard deviation) for each activity. Determine the critical path, the expected project completion time, and the project standard deviation.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

The North Carolina Department of Transportation is undertaking a construction project to widen a large section of interstate highway near Charlotte, NC, which includes the construction of a number of new bridges, interchanges, and overpasses. The first step in the project is the appointment of a project manager and the development of a project team, some of which will be departmental employees and others will be private consultants and operatives. The team of a project of this size also requires a large support staff with varying technical skills. Once the team is selected and the staff is in place the first task is to select a primary contractor to manage and oversee the actual construction. The following table gives the standard activities required for the planning and scheduling of this process.

 

Activity

Description

Predecessor

Time (weeks)

Optimistic

a

Most Likely

m

Pessimistic

b

a

b

c

d

e

f

g

h

i

j

k

L

M

Select project manager

Develop a team recruitment plan

Implement a team recruitment plan

Staff needs assessment

Staff recruitment advertising

Staff selection evaluation procedures

Select project team members

Develop contractor bid requirements

Develop contractor bid evaluation procedure

Staff applicant evaluation and selection

Solicit contractor bids

Contractor bid evaluation

Select contractor and complete negotiations

A

B

B

D

B

C

A

G, H

E, F, G

I, J

K

L

1

1

3

1

1

1

2

1

2

2

4

3

2

2

2

6

2

1

2

4

4

3

4

6

6

3

2

3

8

3

1

4

         6

6

4

5

10

8

5

  1. Construct the precedence network diagram.
  2. Compute the expected completion time and the variance (or standard deviation) for each activity.
  3. Determine the critical path, the expected project completion time, and the project standard deviation.
  4. Determine the probability that the team and the contractor will be in place and the project started within: (i) 7 months (about 30 weeks), (ii) 9 months (about 39 weeks).
  5. Find the period (in weeks) by which you would be 90% sure of completing the process.
  6. Show breakdown of work
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 6 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.