a) What is the expected time to complete the project?
Q: example of cost control for project
A: Cost Control A tool which is used by the organization’s management in controlling and regulating the…
Q: Ql: For activities shown in table below, find the new time of project after upd project manager…
A: Given that:Activities A-J What to do:First: Find the Critical path of the activities.Second:…
Q: Identify different options for reducing the costs of a project and discuss.
A: Project cost is the cost incurred by using different resources and materials throughout the project…
Q: Justify why it is necessary to hire an experienced project manager for challenging projects.
A: Challenging projects could be defined as projects with complex nature, These projects are subjected…
Q: What are the examples of non-functional requirements in a project management?
A: Project management involves the process of planning, organizing, and executing a project to meet…
Q: Describe approach to tracking a project. What kinds of issues would you focus on if you were a…
A: Keeping track of a project is a difficult task. A project manager may use this method to track down…
Q: What is the project standard deviation
A: A network diagram shows the link of each task with the duration taken by each activity with respect…
Q: . Calculate variance project and variance percentage 5 days' workshop trainees 20 person, and…
A: Variance is the difference between Actual cost and Budgeted costs. Variance = Budgeted costs -…
Q: b) Outline the possible sources of cost and time over-runs at different stages of a typical project.
A: Despite the extensive expertise of project management, delays and cost overruns are a common…
Q: Solve the following project by hand and submit your notes: Activity Normal Time (weeks) Crash…
A: NOTE: AS PER GUIDELINES, WE ARE ONLY ALLOWED TO DO THREE SUB-PARTS AT A TIME. PLEASE POST THE REST…
Q: c) Project life cycle diagrams d) Selection method for project (Names and Formulas)
A: Inventory management is a systematic approach to sourcing, storing, and selling inventory both raw…
Q: Determine the most efficient way to shorten the duration of a project?
A: The internal and external ecosystems must alter in order for projects to be productive and…
Q: )Project can involve a single individual or multiple individuals, a single organizational unit, or…
A: Project management includes various other activities like budgeting, scheduling, estimation of…
Q: What is the importance of variance analysis to project managers?
A: Variance analysis can be summed up as an analysis of the distinction between arranged and genuine…
Q: b) Outline the main stages of a typical project and explain the information produced as outputs of…
A: Projects typically involve a series of steps, from initiation to post-project review. Each of these…
Q: a) Construct a Gantt chart using MS Project 2016 b) Assuming the default 5-day workweek, calculate…
A: This question is related to the topic of Project Management and this topic falls under the…
Q: How can a business analyst communicate requirements (and associated models) for a project in project…
A: For every project to be successful, requirements must be communicated clearly. Project success…
Q: the working of the t
A: The triple constraint theory in project management states that undertaking works inside the limits…
Q: The following table represents a plan for a project: TIMES (DAYS) JOB NO. L234567BSGL 1 8 9 10 11…
A: 11 jobs with time estimates are given below:
Q: Explain the importance of a PERT diagram in a project plan.
A: PERT or Project Evaluation Review Technique in project management (PM) applies to a method that is…
Q: Write a detail study on ISO 21500 project management.
A: ANSWER : ISO 21500 gives the guidance and high-level descriptions of the concepts and the processes…
Q: Using an example explain the concept of project crashing
A: Project crashing is simply explained as the method in project management which aims at speeding up…
Q: what are some examples of real world projects?
A: Project management is described as the application of the experiences, knowledge, skills, methods,…
Q: What is the significance of a systems analyst's job in a project?
A: The system analyst's job is a very important position in the organization because it maintains,…
Q: 14 - In earned value analysis, we found that BCWP: $24,800 BCWS: $27,650 ACWP: $21,900 The project…
A: Earned Value Analysis (EVA): It is a system that enables the project manager to estimate the amount…
Q: Using the information in Table-1, assuming that the project team will work a standard working week…
A: Given data is Working days = 5
Q: Name the six key decisions in project management.
A: The success of projects depends upon key decisions pertaining to the following aspects of project…
Q: TIME SCALED EVENT NETWORK 3. From the following two table of informations; a. Draw the precedence…
A: Given data is
Q: When is project processing used?
A: Project management is mean by mapping the undertaking group to a knowledge area to attain the…
Step by step
Solved in 2 steps with 3 images
- The Morant Bay Urban Centre in St. Thomas is a major land development project spearheaded by the Ministry of Economic Growth and Job Creation, through the Factories Corporation of Jamaica (FCJ). The first of its kind to be built in Jamaica, the project so far has been plagued by long delays in its roll out, mostly due to the COVID – 19 outbreaks. The project’s location is former Good Year property and adjacent lands and slated to cost about $6 billion. This centre will serve Morant Bay's commercial, industrial and economic needs. Under the contract with China Harbour Engineering Company Limited (CHEC), 80 per cent of the labour force must be Jamaicans and reside in the area. Project managers assigned to this project are expected to manage the effective and efficient delivery of this venture. Key areas of focus will be planning, executing and monitoring. Develop a conceptual project budget for a section or phase of the project and explain how the project cost can be monitored and…A new motorway project is being planned in Ireland, with its construction expected to cost €1 billion. The 100km route will connect Ireland's second largest city, Cork, with the city of Limerick. The intended alignment for the motorway runs alongside the existing N20, which runs through Blarney, Mallow and Charleville. The new motorway forms part of the Project Ireland 2040 programme of infrastructure works. The first step in the project is to appoint a project manager and develop a project team. Once the team is selected and the staff is in place, the next task is to select a primary contractor to manage and oversee the construction. The following activities, their immediate predecessors, as well as the activity time estimates (in days) are standard for the planning and scheduling of this project: Activity Immediate predecessor Optimistic Most probable Pessimistic A 3 5 6. в 4 6 А, В A, B 5 6 7 D 7 9 10 E в 2 4 6 F 1 2 3 G D 5 8 10 H D, F 6 8 10 I E, G, H 3 4 5 a) What is the…A new motorway project is being planned in Ireland, with its construction expected to cost €1 billion. The 100km route will connect Ireland's second largest city, Cork, with the city of Limerick. The intended alignment for the motorway runs alongside the existing N20, which runs through Blarney, Mallow and Charleville. The new motorway forms part of the Project Ireland 2040 programme of infrastructure works. The first step in the project is to appoint a project manager and develop a project team. Once the team is selected and the staff is in place, the next task is to select a primary contractor to manage and oversee the construction. The following activities, their immediate predecessors, as well as the activity time estimates (in days) are standard for the planning and scheduling of this project: Activity Immediate predecessor Optimistic Most probable Pessimistic A 3 5 6 B 4 6 А, В А, В 5 6 7 D 7 9 10 E B 4 6 F 1 2 G 5 8 10 H D, F 8 10 I E, G, H 3 4 5 a) What are the critical…
- The EU has made changes in airline regulation that dramatically affect major European carriers such as British International Air, KLM, Air France, Alitalia, and Swiss. With ambitious expansion plans, British International Air (BIA) has decided it needs a second service hub on the continent, to complement its large Heathrow (London) repair facility. The location selection is critical, and with the potential for 4,000 new skilled blue-collar jobs on the line, virtually every city in Western Europe is actively bidding for BIA's business. After initial investigations by Holmes Miller, head of the Operations Department, BIA has narrowed the list to 9 cities. Each is then rated on 12 factors, as shown in the table below. City Italy France Germany Factor…Takealot to open massive new distribution centre in Cape Town in 2022 Takealot Property developer Atterbury says that construction is underway on a new distribution centre (DC)for online retailer Takealot in Cape Town, expected to launch in August 2022.The 24,000 sqm facility consists of 22,000 sqm of warehouse space and 2,000 sqm offices, designedto provide Takealot with expansion options to add an additional 50,000 sqm of warehousing to theinitial phase.“The new Takealot DC is designed for sustainability and will feature a dedicated solar PV installation,energy-efficient lighting systems, a rainwater harvesting system and water-saving xeriscapelandscaping. The cross-dock facility will provide clear racking height of up to 18 metres andspecialised floors,” Atterbury said.The developer said that a 6,700 sqm Takealot Customer Collection Centre – which includesexpansion opportunities with the potential to grow to 17,000 sqm – is also under construction atRichmond Park. “The Customer…Takealot to open massive new distribution centre in Cape Town in 2022 Takealot Property developer Atterbury says that construction is underway on a new distribution centre (DC)for online retailer Takealot in Cape Town, expected to launch in August 2022.The 24,000 sqm facility consists of 22,000 sqm of warehouse space and 2,000 sqm offices, designedto provide Takealot with expansion options to add an additional 50,000 sqm of warehousing to theinitial phase.“The new Takealot DC is designed for sustainability and will feature a dedicated solar PV installation,energy-efficient lighting systems, a rainwater harvesting system and water-saving xeriscapelandscaping. The cross-dock facility will provide clear racking height of up to 18 metres andspecialised floors,” Atterbury said.The developer said that a 6,700 sqm Takealot Customer Collection Centre – which includesexpansion opportunities with the potential to grow to 17,000 sqm – is also under construction atRichmond Park. “The Customer…
- Determine the amount of time in weeks that gives a probability of 97.5% until the seventh event in the network. Act. 1-2 2-3 2-5 2-4 3-4 3-7 5-6 6-7 4-7 0 8 4 7 7 4 7 10 10 4 M 10 5 8 9 6 8 14 14 5 24 12 21 11 8 15 24 24 Question 4: The following, and then find the following 12 The possibility of completing the project with a period of less than TE by 4 weeks what is it What is the probability of completing the project with a period exceeding TE by 2 weeks?In light of the recent death of former President Noynoy Aquino, the current government believes that no more Aquino is fit to lead the country, and therefore, also believes that their family has already lost relevance, the Philippine Government plans to demolish the Ninoy Aquino International Airport (NAIA). In its place, they shall build the new Paliparang Pandaigdig ng Pilipinas (PaPa Pi). Its manager, Papa P, is given a choice between two models: Model A, which is a relatively simple model that is a reasonable approximation of the airport to be built; and Model B, a thorough and complex model that almost resembles the exact plan for the proposed building. Model B is the most accurate possible representation of the future PaPa Pi to be built. Why might Papa P prefer to use Model A? Answor uithThe newly appointed board member of Zig-It Limited demands a reprioritisation of invested funds to expanding operations in Africa. She has identified factories in Kenya that can be merged into the current operations of the company to extend the motor manufacturing footprint across the continent.Explain to the board of directors the significance of the risk assessment process, and the anticipated risks that should as minimum be considered.
- A commercial company has a main branch located in Beirut with around 35 employees. The company is looking to expand its activities by opening 3 new branches in Lebanon. To facilitate information and data sharing, the company decided to implement a network in each branch, then to connect all the branches into a single network. Also, the new network will be based on giving employees the facility to use their laptops and smartphones in most of their operations. On the other hand, the company has a major problem with organizing its data. The human resource, finance, sales, and customer service departments have all developed separately their own systems and data files, which created a lot of redundancy and poor security. Managers can't have access to timely, accurate, or relevant information for analysis because the data have been poorly organized and maintained in separated files. The main concern for the company, regarding this problem, is to discover new and hidden patterns of customers'…Defy Opens a World Class Warehousing and Distribution Centre in Danskraal, Ladysmith Defy’s new Danskraal warehouse comes with an additional R170 million investment to the Ladysmith area, contributing to over 130 jobs. South Africa’s largest manufacturer and distributor of major domestic appliances, Defy, announces today the official opening of their new world-class distribution and warehousing centre in Danskrall, Ladysmith on 19 May. The new facility represents a R170 million investment into the Ladysmith area and will create over 130 jobs within the surrounding communities. The Defy Danskraal warehouse can process the loading and unloading of more than 200 trucks per day and has a storage capacity of 100,000m3 of product. The strategic location of the distribution centre creates the opportunity to move product by rail from the Ezakheni manufacturing facility to the Durban port 250 kilometres away. This drastically improves the export supply of Defy, and sister brand Beko appliances…World Vision International-Ghana has secured a 50 million Ghana Cedis from the Mastercard Foundation for a 3-year youth employment project. The project seeks to develop the capacity of Ghanaian Youth aged (15-24) years in entrepreneurial skills to enable them access capital and set up their own businesses. The youth entrepreneurial development and employment initiative covers various sectors like construction, agriculture, agro-processing, manufacturing, services among others. The first phase of the project which is the pilot is expected to cover some selected Ghanaian youth in Accra, Kumasi, Koforidua, Ho, Takoradi, Sunyani, and Tamale. Prior to approval of the project, Care International Ghana Project Management Unit devoted sometime to conduct a literature review in order to understand the current economic wellbeing of Ghanaian youth in terms employment and income levels among others. These were followed by needs assessment studies on current employment need of the Ghanaian youth.…