c) Determine the earliest starting time, in days, for Activity H. d) Determine the latest starting time, in days, for Activity J.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
c) Determine the earliest starting time, in days, for Activity H.
d) Determine the latest starting time, in days, for Activity J.
e) State the Critical Path through the network. (Use the table on the previous page as needed) AND the
minimum time between the start and the harvesting of produce.
f) Would the release of the album be delayed if Activity D took 2 days longer than normal? Explain why.
Watch m
g) By how many days would the duration of Activity G need to INCREASE by for there to be a change in the
Critical Path?
Transcribed Image Text:c) Determine the earliest starting time, in days, for Activity H. d) Determine the latest starting time, in days, for Activity J. e) State the Critical Path through the network. (Use the table on the previous page as needed) AND the minimum time between the start and the harvesting of produce. f) Would the release of the album be delayed if Activity D took 2 days longer than normal? Explain why. Watch m g) By how many days would the duration of Activity G need to INCREASE by for there to be a change in the Critical Path?
1:38
Given that, a
album
Step2
b)
A, 10
sol:-
Step3
c)
B. Sy
D₁2
can be released
Activity
A
B
с
D
2
Բ
LUIH
G
G3
J
DES D
le have to find duration and Breequisite for each
activity.
L
directed network below for an
dummy
-D
H.4
Duration
10
3
5
9
lept ww
6
4
2
G₁6
T₂3
?
$2,4
Preequisite
A
A
A
D
B
BIC
B, C
E, H
F
F
I
G, K,L
14
CD Finish
Required answer provided in above sten
vx
DO
Transcribed Image Text:1:38 Given that, a album Step2 b) A, 10 sol:- Step3 c) B. Sy D₁2 can be released Activity A B с D 2 Բ LUIH G G3 J DES D le have to find duration and Breequisite for each activity. L directed network below for an dummy -D H.4 Duration 10 3 5 9 lept ww 6 4 2 G₁6 T₂3 ? $2,4 Preequisite A A A D B BIC B, C E, H F F I G, K,L 14 CD Finish Required answer provided in above sten vx DO
Expert Solution
Step 1: Introduce the steps to calculate early and late times:

NOTE: We are allowed to do the first three sub-parts only. 

1. Take the ES of the initial activity as 0. 
2. Add duration to this ES to get EF. 
3. This EF will become the ES for the succeeding activity/s. 
4. If any activity has more than one preceding activity/s, then the higher EF will be taken as its ES. 
5. This process will continue till the last activity. 
6. For late times, start from the last activity and take its LF the same as its EF. 
7. If there is more than one activity at the end, then the higher EF, among them, will be taken as the LF of all last activities.
8. Subtract duration from this LF to get the LS of the activity. 
9. This LS will become the LF for the next previous activity/s. 
10. If any activity has more than one successor, then the lower LS will be taken as its LF. 
11. This process will continue till the first activity.
1. Take the ES of the initial activity as 0. 
2. Add duration to this ES to get EF. 
3. This EF will become the ES for the succeeding activity/s. 
4. If any activity has more than one preceding activity/s, then the higher EF will be taken as its ES. 
5. This process will continue till the last activity. 
6. For late times, start from the last activity and take its LF the same as its EF. 
7. If there is more than one activity at the end, then the higher EF, among them, will be taken as the LF of all last activities.
8. Subtract duration from this LF to get the LS of the activity. 
9. This LS will become the LF for the next previous activity/s. 
10. If any activity has more than one successor, then the lower LS will be taken as its LF. 
11. This process will continue till the first activity.

steps

Step by step

Solved in 4 steps with 2 images

Blurred answer
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.